Rationale for Reducing Project Duration • Time Is Money: Cost-Time Tradeoffs –Reducing the time of a critical activity usually incurs additional direct costs. • Cost-time solutions focus on reducing (crashing) activities on the critical path to shorten overall duration of the project.
–Reasons for imposed project duration dates: • Time-to-market pressures • Unforeseen delays • Incentive contracts (bonuses for early completion) • Imposed deadlines and contract commitments • Overhead and public goodwill costs • Pressure to move resources to other projects 9–3
Options for Accelerating Project Completion • Resources Not Constrained
• Resources Constrained
–Adding resources
–Fast-tracking
–Outsourcing project work
–Critical-chain
–Scheduling overtime
–Compromise quality
–Reducing project scope
–Establishing a core project team –Do it twice—fast and then correctly 9–4
Explanation of Project Costs • Project Indirect Costs –Costs that cannot be associated with any particular work package or project activity. • Supervision, administration, consultants, and interest
–Costs that vary (increase) with time. • Reducing project time directly reduces indirect costs.
• Project Direct Costs –Normal costs that can be assigned directly to a specific work package or project activity. • Labor, materials, equipment, and subcontractors
–Crashing activities increases direct costs. 9–5
Reducing Project Duration to Reduce Project Cost Identifying direct costs to reduce project time Gather information about direct and indirect costs of specific project durations. Search critical activities for lowest direct-cost activities to shorten project duration. Compute total costs for specific durations and compare to benefits of reducing project time.
9–6
Project Cost–Duration Graph
FIGURE 9.1 9–7
Constructing a Project Cost–Duration Graph • Find total direct costs for selected project durations. • Find total indirect costs for selected project durations. • Sum direct and indirect costs for these selected project durations. • Compare additional cost alternatives for benefits.
9–8
Constructing a Project Cost–Duration Graph • Determining Activities to Shorten –Shorten the activities with the smallest increase in cost per unit of time. –Assumptions: • The cost relationship is linear. • Normal time assumes low-cost, efficient methods to complete the activity. • Crash time represents a limit—the greatest time reduction possible under realistic conditions.
• Slope represents a constant cost per unit of time. • All accelerations must occur within the normal and crash times. 9–9
Activity Graph
FIGURE 9.2 9–10
Cost–Duration Trade-off Example
FIGURE 9.3 9–11
Cost–Duration Trade-off Example (cont’d)
FIGURE 9.3 (cont’d) 9–12
Cost–Duration Trade-off Example (cont’d)
FIGURE 9.4 9–13
Cost–Duration Trade-off Example (cont’d)
FIGURE 9.4 (cont’d) 9–14
Summary Costs by Duration
FIGURE 9.5 9–15
Project Cost–Duration Graph
FIGURE 9.6 9–16
Practical Considerations • Using the Project Cost–Duration Graph • Crash Times • Linearity Assumption
• Choice of Activities to Crash Revisited • Time Reduction Decisions and Sensitivity
9–17
What if Cost, Not Time Is the Issue? • Commonly Used Options for Cutting Costs –Reduce project scope –Have owner take on more responsibility –Outsourcing project activities or even the entire project
–Brainstorming cost savings options
9–18
Key Terms Crashing Crash point Crash time Direct costs
âCritical-chain. âReducing project scope. âCompromise quality. Whoops! There was a problem loading this page. Retrying... 10 Reducing project duration.pdf.
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. 10) Project ...
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. 10 ps project ...
but I want to do my own thing. TWO people (20%) might call themselves Christians, but their obedience to Jesus is doubtful. Jesus? â He is my Lord and Savior.
Jan 14, 2011 - views of the OECD or of the governments of its member countries. ...... seeking to punish downloaders of copyright material, against the .... to focus more on the process of analysing risk rather than simply having a long list ... abou
Jan 14, 2011 - patches to operating systems and applications; the deployment of anti-malware, firewall and intrusion detection products and services; the use ...
existing security and safety systems mean that it would not be easy for ..... introduce at least modest security improvements, including alarm systems and ...
Jan 14, 2011 - such as satellites, cellular base stations and switches. ..... may also be difficult: investigations can be technically challenging and cross national.
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. Radon reducing ...
Introduction. In this paper, we demonstrate that our programming en- vironment, called ABCDEFG (FG for short) [9], reduces source code size for out-of-core implementations of ... IBM. 1Supported in part by DARPA Award W0133940 in collaboration with.
Transactions Running Parallel. 6. T1. T2. T3. Instruction parts that can fit into L1-I. Threads. Transaction. T123. Common instructions among concurrent threads ...
Nov 30, 2007 - between model predicted class distributions on unlabeled data and class priors. .... can choose the instance that has the highest expected utility according to .... an oracle that can reveal the label of each unlabeled instance.
Janusz Piasecki. Tech Lead: UdjinM6. JIRA project: https://dashpay.atlassian.net/browse/CD. JIRA status: Trac is being used by the team (Jira with next release).
Recently, exemplar-based sparse representation phone identification features ... quite large (many millions) for large vocabulary systems. This makes training of ...
IBM. 1Supported in part by DARPA Award W0133940 in collaboration with. IBM and in part by National Science Foundation Grant IIS-0326155 in ... First, we must overlap work. Since we often use disk I/O and interprocessor communication, we can overlap t
Apr 18, 2006 - action client, VPN gateway and digital signatures in an e- mail client), we achieved a considerable reduction in code size and complexity.
permutation, and FG supplies auxiliary buffers for this pur- pose. Finally, FG ensures that buffers traverse the pipeline in sequential order. A stage does not have ...