PMP Questions 101 - 120

PMP Questions 101 - 120 PMP Studying Process PMP Essence Notes Introduction Project Life Cycle and Org Project Management Processes RITA's Chart

PMP Preparation Worksheets PMP Question Bank 1 - 20 21 - 40 41 - 60 61 - 80 81 - 100 101 - 120 121 - 140 141 - 160 161 - 180 181 - 200 201 - 220 221 - 240 241 - 260 261 - 280 PMI Global Standards PMPBOK Glossary Noteworthy Links

101. The totality of characteristics of an entity that bear on its ability to satisfy stated or implied needs is the definition for: a. Modern quality management b. Quality assurance c. Quality d. Quality control 102. A large project is being worked on by a large company. The client is interested in knowing how the company will be able to meet the quality needs of the project. In order to satisfy this request of the client the project manager arranges a meeting between the client and the: a. General manager b. Quality control manager c. Quality assurance manager d. Chief designer 103. One of the fundamental tenets of quality management is that quality: a. Must exceed customer expectation b. Is planned in and not inspected in c. Will increase cost d. Costs must all be passed onto the customer 104. A category or rank given to products that have the same functional use but different technical characteristics is called the product’s: a. Quality b. Functional characteristics c. Grade d. Technical characteristics 105. The quality manager of a company wishes to analyze the data that is coming to him in the form of a list of defects that have occurred in the shipping department. The report comes with defects listed chronologically as they occurred, the cost of the repair necessary to correct each defect, the person involved, and a description of the defect. The manager would like to determine which of the defects should be corrected first according to the frequency of the defect occurring. He should use which of the following quality tools? a. Cause and effect diagram

106. A project manager from the quality control area is trying to categorize the number of mistakes that are made in the area that paints the right front fender of the Mercedes 560 SL. She list all the possible defects on a sheet of paper and asks the inspector to make a mark each time one of the listed defects is found. This is an example of using which of the following quality tools? b. Statistical measurements c. Check sheet d. Random sampling 107. The project management team should be aware that modern quality management complements modern project management. For example, both disciplines recognize the importance of: a. Completion in the shortest possible time frame b. Making a maximum profit c. Having lower cost than competitor d. Customer satisfaction 108. In a manufacturing process that is being controlled by control charts there are variables occurring that will affect the process output. Variations in the process that are considered to be normal process variables are called: a. Common causes b. Uncommon causes c. Special causes d. Random causes

4/14/2012 11:54 PM

101-120 - PMP Bank

2 of 3

http://sites.google.com/site/pmpbank/101-120

109. Work results, quality checklists, operational definitions, and the management plan are: a. Inputs to quality control b. Outputs from quality control c. Inputs to quality assurance d. Outputs from quality assurance 110. A control chart is being used to control a manufacturing process. As part of the control a sample of five years is taken from the manufacturing process each hour of operation. Each of the five parts is measured, and the dimension is recorded on the work sheet. The average of the five parts is plotted on the control chart. This is called which of the following values? a. X b. X bar c. Sample average d. Control average

111. A project manager for the quality department is trying to solve a problem with a machine that makes die cast aluminum parts that are used in automobiles. These parts are frequently made with defects. The project manager has decided to hold a meeting to discuss the process of making the parts. He creates a diagram that has branches that show the possible causes of the problems. Each of the branches breaks the cause down into more and more detail. This diagram is called a: a. Pareto diagram b. Fishtank diagram c. Cause and effect diagram d. Scatter diagram 112. As the manager of the production department where electrical circuits are being made you observe the inspection station where the completed printed circuit assemblies are being inspected. In this operation the inspector takes the printed circuit assembly and puts it into a fixture. The fixture is part of the testing machine that has three digital readouts. The inspector records the readings on the three digital readouts on his inspection report. This is an example of: a. Attribute inspection b. Variable inspection c. Sampling inspection d. Process control 113. One of the important advantages of using control charts in managing a production operation is that the control chart tells you when to take corrective action on the process being controlled. Another important result of using control charts is: a. The control chart identifies the special causes b. The control chart tells you when you should not take corrective action c. The control chart shows how much the defects are costing d. The control chart shows who is responsible for the defects 114. According to the ideas behind modern quality management, quality improvements should be made: a. In large steps through detailed study of problems and then implemented as comprehensive solutions when they are funded b. In small incremental steps c. By assignment of permanent quality improvement teams d. By hiring ISO certification consultants to point out quality deficient areas 115. The Japanese developed a method of modern quality management that relies on continuing small improvements involving everyone from the top management to the lowest level worker in the organization. This is called: a. Kamban b. Kaizen c. PDCA d. Deming cycle 116. The primary benefits of meeting quality requirements are: a. Cost and delays are reduced, production improves, cost to customers goes up, and profits go up b. Cost and delays are reduced, production improves, market share increases, and profits go up c. Cost and delays are reduced, capital expenditures go down, market share increases, and profits go up d. Cost and delays are reduced, production improves, market share increases, and profits are maintained 117. When the quality management discipline is implemented, the benefits to costs ratio should at least be: a. Unable to be evaluated b. Less than one c. Of little importance d. Greater than one 118. The quality management plan provides input to __________________ and addresses quality control, quality assurance, and quality improvement. a. The overall project plan b. The WBS c. The project scope d. External stakeholders 119. Project quality assurance: a. Includes policing the conformance of the project team to specs b. Provides the project team and stakeholders with standards, by which the project performance is measured

4/14/2012 11:54 PM

101-120 - PMP Bank

3 of 3

http://sites.google.com/site/pmpbank/101-120

c. Is a managerial process that defines the organization, design, resources, and objectives of quality management d. Provide confidence that the project will satisfy relevant quality standards 120. What are the major advantages of the functional type of organization? a. Single point of contact for the customer b. Stable organizational structure c. Project orientation d. Multifunctional teams are easy to form

Have these questions helped you in preparing for your PMP test? We would like some feedback or testimonial from you. Please kindly email us with your comments. Thank you very much.

Answers: 101. C Quality 102. C Quality assurance manager 103. B Is planned in and not inspected in 104. C Grade 105. C Pareto diagram 106. C Check sheet 107. D Customer satisfaction 108. A Common causes 109. A Inputs to quality control 110. B X bar 111. C Cause and effect diagram 112. B Variable inspection 113. B The control chart tells you when you should not take corrective action 114. B In small incremental steps 115. B Kaizen 116. B Cost and delays are reduced, production improves, market share increases, and profits go up 117. D Greater than one 118. A The overall project plan 119. D Provide confidence that the project will satisfy relevant quality standards 120. B Stable organizational structure

"PMI", "PMP" "PMBOK" are marks of the Project Management Institute (PMI) which are registered in the United States of America and in other nations PMI has not participated in the creation of this self assessment test and has not reviewed it for correctness. This test is for self assessment only and no guarantee is given for passing the PMP®. No content from this site can be reproduced without the permission of the owner. The owner of this website is not responsible for contents of external pages via hyperlinks.

Sign in | Report Abuse | Print Page | Remove Access | Powered By Google Sites

4/14/2012 11:54 PM

101-120 - PMP Bank http://sites.google.com/site ... -

Work results, quality checklists, operational definitions, and the management plan are: a. Inputs to quality control b. Outputs from quality control c. Inputs to quality assurance d. Outputs from quality assurance. 110. A control chart is being used to control a manufacturing process. As part of the control a sample of five years is ...

261KB Sizes 1 Downloads 115 Views

Recommend Documents

PMP Cheatsheet.pub
Pareto Diagram: Identify problems and frequency. 80/20 Rule. Flow Charts ... Tools: Interviews, Sensitivity Analysis, Decision Tree Analysis,. Simulation, Monte ...

PMP-Pocket-Guide-The-Ultimate-PMP-Exam-Cheat-Sheets.pdf
... and this file pdf available at Monday 9th of May 2016 08:09:21 AM, Get many Ebooks from our on the web. library associated with The PMP Certification Exam ...

Head First PMP
Bonne exam de PMP!

[PMP] 3_INSTRUMEN_PMP2016_SISWA.pdf
3 Internet o Tidak Mampu o Kurang Mampu o Mampu o Sangat Mampu ... siswa di sekolah pada umumnya mencakup hal-hal sebagai berikut (25 Pertanyaan).

kuesiner PMP guru.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. kuesiner PMP ...

PMP Exam Review.pdf
PMP Exam Review.pdf. PMP Exam Review.pdf. Open. Extract. Open with. Sign In. Main menu. Displaying PMP Exam Review.pdf.

pmp dumps pdf
Loading… Whoops! There was a problem loading more pages. Whoops! There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. pmp dumps pdf. pmp dumps pdf. Open. Extra

Computer Question Bank - Bank Exams Today
a) supercomputer b) personal computer c) Laptop d) PDA e) None of these. 3. ... 10. The software that is used to create text-based documents are referred to as ...

pmp dumps pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. pmp dumps pdf.

PMP Course Outline.pdf
Configuration management. • Close project or phase. 4. Project Scope Management. • Plan scope management. • Collect requirements. • Define scope. • Create work breakdown structure. • Decomposition. • Validate scope. • Control scope. P

Computer Question Bank - Bank Exams Today
What feature adjusts the top and bottom margins so that the text is centered vertically on ... Fourth generation mobile technology provides enhanced capabilities .... A USB communication device that supports data encryption for secure wireless ...