AMENDED EIA NOTIFICATION Of 14th September 2006

ADITYA ENVIRONMENTAL SERVICES PVT. LTD. 107, Hiren Light Indl. Estate, Magul Lane, Mahim, Mumbai – 400 016.

IMPORTANT PROVISIONS Development Projects / Activities classified as Cat. A & Cat. B Cat. A Projects – Clearance by MoEF Cat. B Projects – clearance by State Env. Impact Assessment Authority. Central Govt. to constitute a State level Impact Assessment Authority / State Level Expert Appraisal Committee in consultation with State Govt (Clause 3/4 (iii)) Environmental clearance shall be taken prior to all other clearances (Clause 4 (ii) / 4 (iii)) State level authority to divide projects into Category B1 or Category B2. Category B1 projects will require EIA to be conducted (Clause 7(i)) Clearances from other regulatory bodies not required unless clearance is sequentially dependant on it (Clause 8(v)) Structure / content of EIA Report given in Appendix III & structure of Ex. Summary for EIA in Appendix III-A Validity of clearance specified (Clause 9) - 10 years River Valley projects - 30 years Mining - 5 years other projects - Building construction projects upto occupation of property Submission of half yearly Report compulsory on 1st June & 1st December to concerned Regulatory Authority & to be public documents (Clause 10) EC to be Transferable during its validity to any other legal entity with written NOC of the Transferor (Clause 11) Amended EIA Notification of 2006 to supersede the 1994 Notification but MoEF may continue operation of some of the provisions of the Notification upto One year from Notification date.

STAGE I : INITIAL CHECK (PROJECT PROPONENT OR ENVIRONMENT CONSULTANT) Conceive a project - New Project - Expansion / Modernisation - Change of product mix See if project is covered in Schedule appended to EIA Notification Check Size of project v/s Threshold mentioned in Col. 3 / 4 of Schedule Decide if Project is Cat. A Or Cat. B Cat. A Project to be cleared by MoEF

Cat. B project to be cleared by State Level Env. Impact Asses. Agency

STAGE I : ADDITIONAL CHECK

Additional Check

No

Proceed

Check in column 5 of schedule for the term “specific conditions shall apply” Yes

with EC No

Check if industrial estate has obtained prior EC Yes Individual industries may not obtain EC provided Terms & conditions for industrial Estate / complex are complied with

STAGE I (contd) : ADDITIONAL CHECK FOR CAT. B PROJECTS

No

Check in column 5 of schedule for the term “General conditions shall apply” Yes

Approach State Level Impact Assessment Agency No

Check if project within10 km of Protected Area under Wildlife Protection Act / Notified Eco Sensitive Area / Inter-stateinternational Boundary / Critically Polluted Area as identified by CPCB Yes Project Category Changes to Cat. A

Approach MoEF for EC

OVERALL EC PROCESS

Screening (for Category B Projects only) Scoping Public Consultation

Appraisal by MoEF / Expert Appraisal committee

Recommendation for Grant of EC Grant of EC

SCREENING OF PROJECTS

(FOR PROJECTS TO BE CLEARED AT STATE LEVEL)

Conceive the Project Apply to SLEAC Documents : Prescribed Form I SLEAC to Decide if project requires Environmental Studies or EIA - Depending on Nature & Location specificity of Project - Guidelines maybe Issued by MoEF

Cat. B1 Projects Will require REIA studies Proceed for clearance as per procedure overleaf

Cat. B2 Projects Will not require REIA studies / public consultation Appraisal based on prescribed Form 1 / From 1A (if applicable) & Conceptual Plan

SCOPING

Cat. B project in Item 8 (construction / township/ commercial complex)

Cat. A/B1 Project as covered in Schedule to the Notification

Apply for prior EC to EAC Documents Required : Pre feasibility Project Report, List of Alternative sites, Prescribed Form I/IA, Draft TOR / Scope for REIA

Option

EAC may make Site Visit (if necessary) EAC shall determine Comprehensive & Detailed TOR or Scope for REIA

Reject Application

Scoping Prepare EIA (as per Appendix III format) & Executive Summary of EIA (as per Appendix III A format)

PUBLIC CONSULTATION

Yes Proceed to MoEF

Check if Project Excluded from Public Hearing No

Send 1 Soft / Hard copy to MoEF

Apply to MS / SPCB with 10 copies of Draft EIA + Ex. Summary

Send soft / hard copy to District Magistrate / Mun. Corp. / ZP / District Ind. Officer / Concerned RO of MoEF

Display draft EIA on Web Site Conduct Public Hearing

Invite Written Comments

APPRAISAL

Conduct Public Hearing Prepare proceedings of the hearings

Send to Impact Assessment Agency

Invite Written Comments Compile written comments / objections

Send to Applicant Prepare final EIA Report incorporating comments from PC Process Apply to MoEF Appraisal by EAC Recommendation for grant of prior EC

Documents (20 copies each) Final REIA, Video Tape / CD Public Hearing, Final Layout Plan, Project Feasibility Report

FINAL GRANT OF EC Recommendation for grant of prior EC Accept

MoEF may Accept / Reject recommendations

EC Granted

Reject May Ask Reconsideration by EAC EAC to Inform Final Views

If No Decision then final recommendation of EAC is ultimate decision

Final Decision to be conveyed by MoEF

All documents to be Public

PUBLIC CONSULTATION PROCESS DETAILED PROCEDURE Two Components

Public Hearing

Written Comments / objections

Conducted by SPCB, Chaired by District Magistrate / representative

SPCB Documents tobe submitted -10 hard / soft copies of draft EIA Report -Ex. Summary – EIA in English & local language Place Advt. within 7 days

Hold Public Hearing in 30 days Record Proceedings

District Magistrate, ZP / Mun. Corpn., District Ind. Office, RO of MoEF Documents tobe submitted - 1 hard / soft copy of draft EIA + Ex. Summary Advertise / Display the Report District Magistrate Send to MoEF / Applicant for review of EIA

To be obtained by concerned Regulatory Authority & SPCB MoEF / SLEAC

Place EIA Ex. Summary & Form – I on the web site, Place draft EIA for viewing

Documents tobe submitted - 1 hard/ soft copy of draft EIA + Ex. summary Display on Web Site

Send comments received to applicant

TIME SCHEDULE

Screening Time Limit : Not Mentioned Scoping Time Limit : 60 days Public Consultation Time Limit : 45 days Appraisal & Recommendation for Grant of EC Time Limit : 60 days Grant of EC Time Limit : 135 days

Total Time : 300 days (Excluding EIA Preparation Time)

THANK YOU !

AMENDED EIA NOTIFICATION Of 14th September ... -

EC to be Transferable during its validity to any other legal entity with written NOC of the Transferor (Clause 11). ▫. Amended EIA Notification of 2006 to supersede ...

150KB Sizes 0 Downloads 159 Views

Recommend Documents

NOTIFICATION OF AMENDED GRADE PAY FOR APO IN BIHAR.pdf ...
Page 2 of 2. NOTIFICATION OF AMENDED GRADE PAY FOR APO IN BIHAR.pdf. NOTIFICATION OF AMENDED GRADE PAY FOR APO IN BIHAR.pdf. Open.

RAVEN BLCN Amended Amended Further Amended Statement of ...
Constitution Act, 1982, being Schedule B to the Canada Act 1982 (U.K.), ... RAVEN BLCN Amended Amended Further Amended Statement of Claim-0001.pdf.

RAVEN BLCN Amended Amended Further Amended Statement of ...
RAVEN BLCN Amended Amended Further Amended Statement of Claim-0001.pdf. RAVEN BLCN Amended Amended Further Amended Statement of ...

(Amended)
Dec 30, 1994 - from IEEE Electron Device Letters, Feb. 12, 1991, vol. 12,. No. 2, pp. ... sile Seeker Simulation” by W.S.Chan, J.S.Shie, C.H.Wang,. V.K.Raman ...

EIA Information.pdf
of government agency, state enterprise. or private project which are ... resort, mass transit system. and expressway ... EIA Information.pdf. EIA Information.pdf.

amended
(63) Continuation-in-part of application No. ..... paper that included a ?exible paper web based sheet and an ... development by reaction with a dye precursor.

HYDERABAD NOTIFICATION In continuation of Press Notification of ...
Aug 3, 2013 - ANDHRA PRADESH PUBLIC SERVICE COMMISSION :: HYDERABAD. NOTIFICATION. In continuation of Press Notification of the ...

HYDERABAD NOTIFICATION In continuation of Press Notification of ...
Jul 29, 2013 - In continuation of Press Notification of the Commission, Dt. ... informed that the list of Provisionally Qualified Candidates picked up in place of ...

HYDERABAD NOTIFICATION In continuation of Press Notification of ...
Jul 29, 2013 - In continuation of Press Notification of the Commission, Dt. 09-07-2013, it is hereby informed that the list of Provisionally Qualified Candidates ...

NOE\Amended NOEs\Amended Painter, Exam 4012\NOE - NYC.gov
Nov 6, 2013 - THE TEST: The multiple-choice test may be given at a computer terminal or in paper and pencil format. You will be informed of the format on your Admission Notice. Your score on this test will be used to determine your place on an eligib

amended motion Services
Sep 9, 2013 - intelligence-mining-data-from-nine-us-intemet-companies—in-broad-secret ... providers. Regrettably, the parties reached an impasse and mutually agreed to ask this Court to stay the proceedings to permit Google to amend its ... the bri

Notification
Jul 25, 2012 - served by frequent bus services from all sides. ..... Park” means an area developed exclusively for locating software ...... Revenue Accounting.

September
Sep 1, 2017 - September. 2017. Badminton Open Gym. Sunday. Monday. Tuesday. Wednesday. Thursday. Friday. Saturday. 1. 2. 3. 4. 5. 6. 7. 8. 9. Lindbergh.

Second Amended Complaint.pdf
Page 3 of 50. Whoops! There was a problem loading this page. Retrying... Second Amended Complaint.pdf. Second Amended Complaint.pdf. Open. Extract. Open with. Sign In. Main menu. Displaying Second Amended Complaint.pdf. Page 1 of 50.

EIA Expost del Muelle Caraguay.pdf
7. Oficinas bancarias varias. Whoops! There was a problem loading this page. EIA Expost del Muelle Caraguay.pdf. EIA Expost del Muelle Caraguay.pdf. Open.

Notification
Jul 25, 2012 - Year Number of Persons Growth Rate (percentage) ... 1. Kundli- Manesar-Palwal (KMP) Expressway passing by the southern side of ..... Around High School, village Garhi Bazidpur declared vide Haryana ..... Wholesale Trade.

*AMENDED-PR-R405ChallengerDeep.pdf
May 2, 2012 - The resolution's adoption shows strong bi-partisan support of its intent. "You can't explore ... approval of Resolution 405 is a smart business decision for Guam and the region. The ... *AMENDED-PR-R405ChallengerDeep.pdf.

07.20.2013 amended complaint.pdf
-Jac k Vetter , SBN 7302. LAW OFFICE OF JACK ... MOTOR VEHICLE IXI OTHER fspec/fy);. 1 ^ Property .... 07.20.2013 amended complaint.pdf. 07.20.2013 ...

Stormy Amended Complaint.pdf
Page 1 of 41. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. FIRST AMENDED COMPLAINT. Michael J. Avenatti, Bar No. 206929. AVENATTI & ASSOCIATES, APC. [email protected]. 520 Newport Center Dr

EIA & eval Oxec II.pdf
Page 1 of 1. EIA & eval Oxec II.pdf. EIA & eval Oxec II.pdf. Open. Extract. Open with. Sign In. Main menu. Displaying EIA & eval Oxec II.pdf. Page 1 of 1.

EIA Expost del Muelle Caraguay.pdf
... below to open or edit this item. EIA Expost del Muelle Caraguay.pdf. EIA Expost del Muelle Caraguay.pdf. Open. Extract. Open with. Sign In. Main menu.