FACILITIES UPDATE Revere and Stoddard Board Presentation March 11, 2015
David A. Rivera, Assistant Superintendent, Administrative Services Patrice Langevin, Director, Facilities & Planning
BOARD OF EDUCATION KEY GOAL • To provide facilities that meet the present and future needs of students and staff … and ensure that facilities are well maintained
STODDARD ELEMENTARY SCHOOL Modernization Construction Update Anticipated Completion December 2015
MOVING TO THE KEY INTERIM SITE Factoids: • 28 M&O support staff / 360 hours • 9 TIS support staff / 288 hours • 29 classrooms moved • 1,740 boxes moved • 4.5 miles of packing tape • 4,000 moving labels used • 5 classroom partition walls reconfigured • Disassembled furniture from 8 classrooms and office areas for storage • Filled four sea containers • Started move Dec 15, finished Jan 12
• 525 students bused to interim site
• Seismic upgrades
• All buildings renovated • Existing library remodel
Existing Library
Example of New Library
STODDARD ADDITIONAL IMPROVEMENTS • 21st Century Learning • Computer labs • Parking, landscape, new playground • Project Costs: $15.2m
Questions or Comments
PAUL REVERE ELEMENTARY SCHOOL Seismic Upgrades Project
HISTORY • Phase 1 (2004) • Campus modernized and new two-story classroom building constructed
• Phase 2 (2015) • Seismic retrofit work • Restroom upgrades • State matching funds $474,624
SCOPE OF WORK • Seismic and restroom upgrades of buildings A, B and C classrooms, library, and administration offices (same as Juarez seismic upgrades) • Structural seismic upgrades to provide better stability in the event of an earthquake • Restroom upgrades to meet current accessibility standards
SCOPE OF WORK • Same team as Juarez Seismic Upgrades • Completed over two periods - spring and summer breaks, 2015
SPRING BREAK • New steel braces measured and preordered • Braces will reside above current ceiling
SUMMER BREAK • New steel braces are installed • Exterior masonry wing walls strengthened • Kindergarten and administration restrooms remodeled
Disassembled furniture from 8. classrooms and office areas for storage. ⢠Filled four sea containers. ⢠Started move Dec 15, finished Jan 12. ⢠525 students bused ...