Post-Production schedule
Monday
Tuesday
week 1 (February)
1st
2nd
2nd Semester start. (Major Project and Post-Production) Beginning planning Schedule
week 2 (February)
8th
Presenting animatic and redrawn mother design in Major Project and PostProduction lecture. :D -Begin animating rough scene (sequence 32: Ghoul attacks Werewolf) :D -Feedback: -Allow the film to have more breathing room -change reaction to characters that feel generic -give the mother her moment to shine -change the age of boy to add contiunity and purpose to his role in the plot -Change the vulnerability to truly feel like a horror themed film. :D -Revisit storyboard (start) :D
week 3 (February)
15th *Continue storyboard (7-30) :D *start scene 8 :D *continue scene 15-16 (rough sketch) :D *update blog from today's feedback :D *update employability blog with entry notes of previous session and research and rough up of action plan :D *blog post of rough sketch vids on vimeo, updated character designs and updated storyboards.:D
week 4 (February)
22nd
-1st employability lecture. -revisit mother anatomy design. -Start to be objective with animatic. 9th
-Continue with redesigning storyboard based on yesterday's notes -sort out ending when it comes the mother getting her moment to shine so it has something finish from. -2nd employablity lecture. :D -start scene 7: sequence 35-36 (werewolf hears howl) :D *start 1st scene (basic scene of camera panning of moon shot down to building):D
16th
*finish updated storyboard (detail) :D *finish mother character and breakdown sheet :D *employabiliy lecture with speaker Lisa Law :D 23rd
Week 5 (Feb-March)
Week 6 (march)
Week 7 (March)
*present to lecturers and peers of previous week's work flow :D *afternoon off :D
*start updating animatic :D *begin keyframing sequence 1-4 :D
29th
1st
*present to lecturers and peers of previous week's work flow (x) **Continue Keyframing (sequence 11-15 continue)
Unwell
7th
8th
*present two weeks worth of work to lecturers and peers *using garage band to create sounds :D keyframing sequences 32-35 :D
*finisn keyframing :D
14th
15th
show keyframing so far to lecturers with music *sound booth 12:15-16:15pm
Easter holiday (march)
easter holiday (march-april)
week 8 (April)
*trip to silent signal event in birmingham university
21st
22nd
animating sequence 20-21
animating sequence 13-14, 3
28th
29th
continue animating seqeunces 17-18
continue animating sequences 33, 35
4th
5th
week 9 (April)
week 10 (April)
target to get half of the animation's lineart *continue sequences 5 and 36 *continue action plan
update blog posts :D *continue portfolio research *continue animating
11th
12th
show animation so far to lecturers :D *deadline for synopsis :D *animating sequence 22, continue 34 :D
*relitavely most of the lineart animation done :D *animate sequences 22, 35 :D
18th
19th
*finish animation inbetweens :D *start clean up (sequence 13) :D
week 11 (April)
week 12th (may)
*continue promotion poster :D *continue skills audit, business plan and summarize research :D *edit music into finished inbetweens and publish on vimeo :D *begin showreel edit :D
25th
26th
*deadline for the prey poster (TARGET) :D *continue clean up and editing (sequences 4,5, 8, 22, 26 and 27) *continue presentation of industry role *showreel editing
*mock presentation *continue clean up and editing *
2nd
3rd
*presenation of industry role *continue aniamtion clean up of final scenes *continue notes on evaluation and reflection most of clean up finished
week 13 (may handin)
9th
10th
Wednesday
Thursday
Friday
Saturday
3rd
4th
5th
6th
*basic pratice on female anatomy *finish testing out more potnetial shapes for *research industry roles for mother character employability module.
10th
11th
1pm-9pm part-time Work
12th
*continue storyboard. *continue finishing designs for improved boy :D and mother concepts. :D *only do scenes based on feedback such as changed designs of characters, reactions, actions, the vulnerability of the character and giving the mothe her moment to change into werewolf herself. :D *redesign the boy character by aging *continue rough sequences :D him down to 13 :D Day off *begin sequence 15-16 :D 17th
13th
*1pm-9pm work shift
18th
19th
20th
*update blog post for week 2 :D *finish ghoul character sheet :D *start sequence 7-8 :D *continue sequence 17-18 :D
*have morning off *finish boy character sheet :D
*start sequence 23-27 (boy is attacked but turns into werewolf) *start linart for sequence 32 to see where the final look should go *update blog for week 3 :D
*1pm-9pm work shift *continue rough line scenes
24th
25th
26th
27th
*continue keyframing (sequence 5-7) *South Booth 12:15- 16:00pm
*Continue keyframing (sequence 810)
*Continue keyframing (Sequence 11-15) *help set up lighting and blue screen for andrew
1pm-9pm part-time Work 5th
2nd
3rd
4th
*Continue Keyframing (sequence 16-20)
*Continue keyframing (sequence 2128) *look at blog and record what needs updating *update wall schedule
*Continue keyframing (Sequence 29-35) *update blog fropm recorded notes from previous workflow *start an action plan and note strength and weaknesses 1pm-9pm part-time Work
9th
10th
11th
*Continue lineart and animation inbetween *improve the mother characteristics *south booth 12;15-16:00pm *write a rough action plan for *plan major project reflection and evaluation employability module :D
*animating *look for old CV* :D *sound booth 12:15-16:15pm *start editing the music to the sound
16th
18th
trip to dudley zoo
17th begin aniamting backgrounds for each scene *continue drawing studies of animals from zoo trip and from the photos
12th
1pm-9pm part-time Work *animating 19th
1pm-9pm part-time Work 23rd
24th
25th
26th
animating sequence 9 continue sequence 20
continue animating sequence 15
animating sequence 15-18
continue animating seqeunce 17-18 1pm-9pm part-time Work
30th
31st
1st continue animating seqeunce 28
animating sequence 6-8
animating sequence 4, continue 6-8
2nd continue animating 33, 35 1pm-9pm part-time Work
6th
7th
8th
9th
*continue portfolio research *animating sequence 5, 36
animating sequence 10-12, 22
animating sequence 23-25, 29, 34
13th
14th
15th blog for final film week 9: *feedback and festival talk and links :D *music and sound effects :D *press kit so far no contact details before its done :D *drawing of zoo animals ;D *paul ward talk :D
1pm-9pm part-time Work *Prey synopsis *action plan building 16th
blog for porfoilio *lizz hobbs talk *porfolio drawings *sound booth 12:15-16:15pm sound effects :D continue life drawings of animals for portfolio :D
*start writing up the press kit :D *update blog :D *continue portfolio buildingpersonal action plan, CV and research :D
*continue portfolio (success points, ideal situation.... *Scan portfolio drawings :D *CV building :D *finishing structure of portfolio :D
20th
21st
22nd
clean up and colour to animation ;D
*Finish promotional poster :D *continue Evaulation and reflection :D *continue clean up and colour :D clean up and colour to animation ;D *edit better version of the first scene :D *Update Blog from final film posts :D
27th
28th
Animation and clean up :D 4th
1pm-9pm part-time Work 23rd 1pm-9pm part-time Work *continue Evaulation and reflection (night after work) *continue clean up and colouring (morning before shift) 30th
Animation and clean up :D
29th *Sound booth 10:00am- 14:00pm :D *clean up poster :D *finish showreel by the end of the day (PRIORITY) :D *Setup presentation *finish bio and send to cherai :D *email with details of film to degree show :D *clean up and edit animation
5th
6th
7th
1pm-9pm part-time Work
Finish all clean up *finish evaulation and start reflection * 11th
*continue editing the music, sound and aniamtion effects together *tweak the animation (title at the beginning, bite shot, blur some background for more character focus and add moon reverse back into clouds after howl and before reverse back into human form :D *finish CV, Creative Cv and Business cards (print out and photographed for portfolio *sound booth 13:45pm- 16:30pm *finish press kit and reflection *continue portfolio (partularly the *sound booth 10:00am- 14:00pm industry role based on the *finish editing and start rendering presentation research. * 13th
1pm-9pm part-time Work 14th
Sunday 7th
1pm-9pm part-time Work
14th
*1pm-9pm work shift
21st
*1pm-9pm work shift *begin adding background and detail to roughed out scenes 28th
Floating day *Continue keyframing 6th
1pm-9pm part-time Work *continue writing action plan 13th
1pm-9pm part-time Work 20th
1pm-9pm part-time Work 27th animating sequence 19 holiday 3rd animating sequence 30-32 holiday 10th
portfolio building 1pm-9pm part-time Work 17th
1pm-9pm part-time Work 24th 1pm-9pm part-time Work *continue clean up and colouring (morning before shift) *continue career research presentation 1st
1pm-9pm part-time Work 8th
1pm-9pm part-time Work 15th