IV Semester M.B.A. (Eve.) Degree Examination, July 2016 (2008 Scheme) MANAGEMENT F – 6 : Project Appraisal and Finance Time : 3 Hours

Max. Marks : 75

Instruction : Use of Tables permitted. SECTION – A Answer any six of the following. Each question carries two marks.

(6×2=12)

1. a) What do you mean by Project Appraisal ? b) What do you mean by preliminary screening ? c) What is Technical analysis ? d) What do you mean by Capital budgeting ? e) What do you mean by Cost leadership ? f) What do you mean by Vertical integration ? g) What is Cpm ? h) What do you mean by Social Cost Benefit Analysis ? SECTION – B Answer any three of the following. Each carries eight marks.

(3×8=24)

2. Briefly explain the different facets of Project Analysis. 3. Briefly explain the Porter’s Five force model of driving industry competition. 4. How the firm can scout for project ideas ? Suggest the firm with a wide variety of sources to get good project ideas. 5. Write a short note on : a) Venture Capital

b) Factoring.

6. What is CAPM ? Briefly explain the assumptions and limitations of CAPM. P.T.O.

PG – 982

-2-

*PG982*

SECTION – C Answer any two questions. Each carries twelve marks.

(2×12=24)

7. Explain the five broad phases of Capital budgeting. 8. What do you mean by demand forecasting ? Explain the various methods of demand forecasting. 9. A project consists of 12 activities and their time estimates are shown below :

Activity

Time (in weeks) to

tm

tp

(1-2)

4

6

10

(1-3)

3

7

12

(1-4)

5

6

9

(1-7)

2

4

6

(2-4)

6

10

20

(2-6)

3

4

7

(2-7)

5

9

15

(3-4)

3

7

12

(4-5)

2

4

5

(5-6)

1

3

6

(3-7)

2

5

8

(6-7)

1

2

6

a) Draw the network diagram. b) Determine the critical path. c) Calculate event slacks and activity floats.

*PG982*

PG – 982

-3-

SECTION – D Compulsory :

(1×15=15)

10. Phoenix Company is considering two mutually exclusive investments, project P and Project Q. The expected Cash flows of these projects are as follows : in (000's)

Year

Project P

Project Q

0

(10,000)

(16,000)

1

8,000

2,000

2

6,000

4,000

3

5,000

6,000

4

2,000

8,000

5

4,000

10,000

You are required to calculate a) Pay back period and Discounted pay back period for Projects P and Q. b) Construct the NPV profiles for project P and Q. c) What is the IRR of each project ? d) Calculate Benefit Cost Ratio for P and Q.

______________________

Project appraisal and finance.pdf

Page 1 of 3. PG – 982. IV Semester M.B.A. (Eve.) Degree Examination, July 2016. (2008 Scheme). MANAGEMENT. F – 6 : Project Appraisal and Finance.

66KB Sizes 3 Downloads 159 Views

Recommend Documents

Project appraisal and finance.pdf
for each project. Project X Project Y. NPV estimate (Rs.) Probability NPV estimate (Rs.) Probability. 45,000 0.1 45,000 0.2. 90,000 0.4 90,000 0.3. 1,80,000 0.4 1 ...

unit 4 project appraisal-ii (economic feasibility)
During the course of our discussion in the last unit on technical feasibility analysis, the concept of ..... Output of Secondary Education, health,. These benefits may.

Teacher Appraisal Guide.pdf
Page 3 of 32. Teacher Appraisal Guide.pdf. Teacher Appraisal Guide.pdf. Open. Extract. Open with. Sign In. Main menu. Displaying Teacher Appraisal Guide.pdf ...

appraisal report of
393 East Riverside Drive Ste. 102. St. George, Utah 84790. (435) 673-7720. PROFESSIONAL DESIGNATIONS. Certified General Appraiser by the State of Utah.

pdf performance appraisal
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. pdf performance ...

pdf performance appraisal
Page 1. Whoops! There was a problem loading more pages. Retrying... pdf performance appraisal. pdf performance appraisal. Open. Extract. Open with. Sign In.

Teacher Appraisal Guide.pdf
Hence an operational definition of evaluation is the. placement of value on an activity after considering the available and collected data. The. terms evaluation ...

Performance appraisal-Primary.pdf
Page 1 of 2. ,izg;G-2. Mrpupau; nrayhw;Wif juq;fzpg;G 01.01.201... - 31.12.201... ( juk; 1 – 5 ). Mrpupau; ngau;: epakd tif: ghlrhiy: jw;Nghija ,.M.Nr. tFg;G: Nfhl;lk;: ... gpd;tUtdtw;Ws ; nghUj;jkhd ml;ltizia njupT nra;f. ml;ltiz (A) : Kjd;ik epiy

Health appraisal form.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. Health appraisal ...