Answer THREE questions All questions carry equal marks Attached: Supplied:
Heriot-Watt University
Q1
D19CR Contracts and Procurement - August - 2007/08
The successful use of the Construction Management procurement route requires that the employer and project management team have expertise and experience in certain areas. Discuss what these competencies are and why the use of this procurement route is unlikely to be successful if they are not present. (33 marks)
Q2
A contractor’s submission of a claim for loss and expense is often thought to be the result of a poorly managed project that has “gone wrong” in some way. Discuss whether or not you agree with this view, making reference to the contractual basis on which a claim for loss and expense may be submitted under the JCT Standard Building Contract form. (33 marks)
Q3
An Employer is about to construct a new facility that will require close collaboration between the Employer and the Contractor to ensure success. (a)
Recommend whether adjudication or arbitration would be a suitable dispute resolution method by analysing the suitability of both techniques to this project. (16 marks)
(b)
Discuss how the recommended dispute resolution method would be used in practice, following the requirements of the JCT Standard Building Contract form. (17 marks)
Page 2 of 3
Heriot-Watt University
Q4
(a)
D19CR Contracts and Procurement - August - 2007/08
Under what circumstances would the Contractor become liable for the payment of liquidated and ascertained damages to the Employer? (11 marks)
Q5
(b)
Review the contractual provisions available to the Contractor in the JCT Standard Building Contract to ensure that it does not unnecessarily pay such damages. (22 marks)
(a)
You have been appointed by the owner of a building located next to a plot of land on which a new apartment block will soon be constructed. Summarise the two ways in which the Employer procuring the new apartment block can ensure that its Contractor will be liable for any damage to your building. (16 marks)
(b)
Recommend which of these two methods should be used and support your position with reasoned argument. (17 marks)
make this recommendation and why the alternative is not, in your view, appropriate. ... provide a process for paying the Contractor extra money. Advise the Client ...
Dec 7, 2012 - bution under a uniform light source for good sun-shading properties. Loutzenhiser et al. [12] noted that building energy simulation programs ...
Law and the Built Environment
Download at => https://pdfkulonline13e1.blogspot.com/1405197609
Law and the Built Environment pdf download, Law and the Built Environment audiobook download, Law and the Built Environment read online, Law and the Bui
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. CLAHRC BITE 13 Built Environment HI.pdf. CLAHRC BITE 13 Built Environment HI.pdf. Open. Extract. Open with.
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. CLAHRC BITE ...
Our website. www.clahrc-sy.nihr.ac.uk. Whoops! There was a problem loading this page. CLAHRC BITE 13 Built Environment HI.pdf. CLAHRC BITE 13 Built ...
Oct 27, 2014 - The School of the Environment at WSU is a new ... include studies of gene flow and the development and application of environmental DNA.
... Read Best Book Design and Security in the Built Environment Online, Pdf Books Design ... offices, hospitals, schools, and other public and private facilities.
http://jed.sagepub.com. The online version of this article can be found at: ... significant shortcomings. For a start, sustainability is seen pri- ... instance, human and labor rights, anticorruption, and the role of business in weak governance zones