ACEC 316 – Construction Management - Spring 2009 Dr. Christos Anastasiou
HOMEWORK 1 - Gantt Charts (Due: March 17, 2009)
INSTRUCTIONS: For the list of activities regarding the construction of a house (given in the table below), prepare a Gantt Chart that will help in the organization of the aforementioned project. Your deliverables should include a series of Gantt-type charts, as well as a cover page that should briefly outline this project (the last page of this document provides an example of how I expect this chart to look like). Make sure that you hand in the following: 1) a print-out of your work, 2) your Excel file via email. NOTE: The file name and the subject of the email should be “ACEC316 – HW1 – YOUR NAME”
Developing a Construction Schedule If you are building or remodeling a home, you will be confronted with the challenging task of scheduling several contractors. Unfortunately, construction is not a smooth process with definitive completion dates. Each construction project is unique in its process, scope of work, and goals. Because of this, you will need to analyze your project before it starts and develop a construction schedule. Before beginning, understand your plan must be flexible. If you are building a home from scratch, you may run into delays in receiving your permit. This has a domino effect that pushes out the start dates of every contractor. If you have hired a General Contractor to build or remodel your home, there may be scheduling conflicts with other projects. If this is the case, you will need to work directly with the builder on getting back on track. For the purpose of this exercise, it will be assumed you are hiring the contractors yourself and controlling the scheduling. Construction projects work through the following process: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16.
Home plan design Permitting process (including review, changes, and final approval) Establishing temporary power to the site (so contractors can run their tools) Site work Foundation Framing Roofing Installation of windows and doors Siding Rough mechanicals including plumbing, electrical and HVAC Insulation Drywall Painting Interior trim and other finish work Flooring Cabinets and countertops
1
As you can see, there are potentially 16 contractors that you will have to work with during the construction of a home. All of them will have numerous jobs in addition to yours. Products will arrive on site that are wrong or need to be switched out. Weather will hamper your efforts and make a contractor's job more difficult. So, how does one assemble any sort of construction schedule that will work? It begins with setting a deadline for completion. Typically, it takes between 10-12 months for someone to complete construction of a home. The more custom a home is, the longer it will take. Your particular project may be completed in six months, but the more detailed the plan or difficult the building lot, the more time it will take. After setting a deadline for completion, select the contractors you would like to hire. Many processes will be involved in choosing the right contractor, but through a process of elimination, you can select a handful of builders. With the handful of contractors selected, you can then plan your construction project according to their schedules. For example, there may be two framers of equal ability and reputation, but one can start next week and the other in five weeks. Knowing this can help you can make an informed decision on which one will fit into the schedule. Speak with all the contractors you have selected and make sure they understand your schedule. If you find that one or several are not willing to work within your time frame, search for another contractor. In construction, time is money and unnecessary waiting costs you time. The other key ingredient to scheduling is being able to multi-task. As each phase of construction progresses, you will need to schedule another contractor (and sometimes several at the same time). For example, while the rough framing is being completed, you will want to call the plumber and electrician to perform their duties. While the plumber and electrician are working, you should contact the insulation and drywall installers. Stay one step ahead of the contractors working for you. Below is a flowchart showing a typical scheduling path: • • • • • • •
During the permitting phase, schedule site work contractors. During site work, schedule foundation and framing contractors. When framing has started, contact mechanical contractors to start their "rough" phases. As framing approaches completion, schedule roofer and sider. As mechanical contractors are finishing their work, contact insulation and drywall contractors. When drywall is complete, schedule finish carpenter to install doors, mouldings, etc. Upon completion, schedule interior painter.
The final phases of your project will involve installing cabinets, countertops and flooring materials. Often times, these trades are performed very closely to each other. Do not be afraid to put contractors in touch with each other! Time is money to them too, and any coordination they can do between themselves makes everyone happy. Remember, a construction schedule is highly complex and filled with variables. This process cannot be mastered, but it can be controlled. This begins with setting goals and scheduling contractors beforehand (like assembling a puzzle). However, by understanding the general scheduling path, you can gain a better understanding of the way in which phases are completed.
2
Project Name: Custom House Construction Company Name: Christos's Construction Company Project Start: 12-May-2004 Project Finish: 27-Apr-2005
Task Name
Duration
Contracts
Start
Finish
12-May-2004
12-May-2004
Precedents
Supply Lot Sale Agreement
0 days
12-May-2004
12-May-2004
Supply Construction Agreement
0 days
12-May-2004
12-May-2004
Supply Contract Plans
0 days
12-May-2004
12-May-2004
Supply Construction Agreement
Supply Contract Specifications
0 days
12-May-2004
12-May-2004
Supply Construction Agreement
Supply Contract Site Plan 0 days
12-May-2004
12-May-2004
Supply Construction Agreement
Secure Financing
0 days
12-May-2004
12-May-2004
Construction Loan Settlement
0 days
12-May-2004
12-May-2004
12-May-2004
16-Jun-2004
Document Review & Revision
Secure Financing
Review & Finalize Plans
15 days
12-May-2004
02-Jun-2004
Supply Contract Plans, Supply Lot Sale Agreement, Supply Construction Agreement, Supply Contract Specifications, Supply Contract Site Plan, Construction Loan Settlement
Review & Finalize Specifications
20 days
12-May-2004
09-Jun-2004
Supply Contract Specifications
Review & Finalize Site Plan
1 day
02-Jun-2004
03-Jun-2004
Supply Contract Site Plan, Review & Finalize Plans
Print Construction Drawings
5 days
09-Jun-2004
16-Jun-2004
Review & Finalize Plans, Review & Finalize Specifications, Review & Finalize Site Plan
Approve Revised Plans
0 days
16-Jun-2004
16-Jun-2004
Print Construction Drawings
Approve Revised Specifications
0 days
16-Jun-2004
16-Jun-2004
Print Construction Drawings
Approve Revised Site Plan
0 days
16-Jun-2004
16-Jun-2004
Print Construction Drawings
16-Jun-2004
20-Jul-2004
Bids & Contracts Make Copies of Plans
3 days
16-Jun-2004
21-Jun-2004
Approve Revised Plans, Print Construction Drawings
Make Copies of Specifications
2 days
16-Jun-2004
18-Jun-2004
Approve Revised Specifications
Distribute Plans &
1 day
21-Jun-2004
22-Jun-2004
Make Copies of Plans, Make Copies of
3
Specifications
Specifications
Receive Bids
10 days
22-Jun-2004
06-Jul-2004
Distribute Plans & Specifications
Review Bids
5 days
06-Jul-2004
13-Jul-2004
Receive Bids
Execute Subcontractor Agreements
5 days
13-Jul-2004
20-Jul-2004
Review Bids
16-Jun-2004
02-Aug-2004
Grading & Building Permits Schedule lot stake-out
1 day
16-Jun-2004
17-Jun-2004
Print Construction Drawings
Stake lot
1 day
21-Jun-2004
22-Jun-2004
Schedule lot stake-out
File Grading Permit Application
1 day
16-Jun-2004
17-Jun-2004
Approve Revised Site Plan
File Building Permit Application
3 days
16-Jun-2004
21-Jun-2004
Approve Revised Plans, Approve Revised Specifications, Approve Revised Site Plan
Post Lot Identification
1 day
22-Jun-2004
23-Jun-2004
Stake lot, File Grading Permit Application, File Building Permit Application
Meet Sed. Control Insp.
1 day
23-Jun-2004
24-Jun-2004
File Grading Permit Application, Stake lot, Post Lot Identification
Walk Lot w/ Owner
1 day
20-Jul-2004
21-Jul-2004
Meet Sed. Control Insp., Execute Subcontractor Agreements
Install Construction Entrance
1 day
21-Jul-2004
22-Jul-2004
Meet Sed. Control Insp., Walk Lot w/ Owner
Install Sediment Controls 2 days
21-Jul-2004
23-Jul-2004
Meet Sed. Control Insp., Walk Lot w/ Owner
Sediment Control Insp.
1 day
23-Jul-2004
26-Jul-2004
Install Construction Entrance, Install Sediment Controls
Grading Permit Issued
1 day
26-Jul-2004
27-Jul-2004
Sediment Control Insp.
Municipal Permit Process 10 days
21-Jun-2004
05-Jul-2004
File Building Permit Application, File Grading Permit Application
Building Permit Approved
1 day
27-Jul-2004
28-Jul-2004
Municipal Permit Process, Grading Permit Issued
Pay Permit Fees and Taxes
1 day
30-Jul-2004
02-Aug-2004
Building Permit Approved
Building Permit Issued
0 days
02-Aug-2004
02-Aug-2004
Pay Permit Fees and Taxes
27-Jul-2004
09-Aug-2004
27-Jul-2004
30-Jul-2004
Grading Permit Issued
Strip Topsoil & Stockpile 1 day
02-Aug-2004
03-Aug-2004
Clear Lot, Building Permit Issued
Stake Lot for Excavation
1 day
03-Aug-2004
04-Aug-2004
Clear Lot, Strip Topsoil & Stockpile
Rough grade lot
1 day
04-Aug-2004
05-Aug-2004
Clear Lot, Stake Lot for Excavation
Excavate for foundation
2 days
05-Aug-2004
09-Aug-2004
Building Permit Approved, Stake Lot for Excavation, Clear Lot, Rough grade lot
09-Aug-2004
10-Sep-2004
09-Aug-2004
10-Aug-2004
Site Work Clear Lot
3 days
Foundation Layout footings
1 day
4
Excavate for foundation
Dig Footings & Install Reinforcing
1 day
10-Aug-2004
11-Aug-2004
Layout footings
Footing Inspection
0 days
11-Aug-2004
11-Aug-2004
Dig Footings & Install Reinforcing
Pour footings
1 day
11-Aug-2004
12-Aug-2004
Footing Inspection
Pin Footings
1 day
12-Aug-2004
13-Aug-2004
Pour footings
Stock Block, Mortar, Sand
1 day
13-Aug-2004
16-Aug-2004
Pin Footings
Build Block Foundation
15 days
16-Aug-2004
06-Sep-2004
Pin Footings, Stock Block, Mortar, Sand, Footing Inspection
Foundation Certification
0 days
06-Sep-2004
06-Sep-2004
Build Block Foundation
Fill Block Cores w/ Concrete
1 day
06-Sep-2004
07-Sep-2004
Build Block Foundation, Foundation Certification
Steel Delivery
1 day
07-Sep-2004
08-Sep-2004
Fill Block Cores w/ Concrete
Set Lintels, Bolts, Cap Block
2 days
08-Sep-2004
10-Sep-2004
Steel Delivery
Lumber Delivery
1 day
07-Sep-2004
08-Sep-2004
Fill Block Cores w/ Concrete, Stake Lot for Excavation
Waterproofing and Drain Tile
1 day
08-Sep-2004
09-Sep-2004
Lumber Delivery
10-Sep-2004
27-Oct-2004
Rough Carpentry Set Steel
1 day
10-Sep-2004
13-Sep-2004
Set Lintels, Bolts, Cap Block, Lumber Delivery
1st Floor Deck Framing
4 days
13-Sep-2004
17-Sep-2004
Set Steel
1st Floor Wall Framing
4 days
17-Sep-2004
23-Sep-2004
1st Floor Deck Framing
2nd Floor Deck Framing
2 days
23-Sep-2004
27-Sep-2004
1st Floor Wall Framing
2nd Floor Wall Framing
3 days
27-Sep-2004
30-Sep-2004
2nd Floor Deck Framing
Set Roof Trusses
2 days
30-Sep-2004
04-Oct-2004
2nd Floor Wall Framing
Frame Roof
7 days
04-Oct-2004
13-Oct-2004
Set Roof Trusses
Install Roof Plywood
5 days
13-Oct-2004
20-Oct-2004
Frame Roof
Install Windows & Doors 2 days
25-Oct-2004
27-Oct-2004
Install Roof Plywood, Roofing Paper Installed
Frame Basement
21-Oct-2004
26-Oct-2004
Frame Roof, Pour Basement Slab
14-Oct-2004
26-Oct-2004
3 days
Concrete Slabs Basement Slab Preparation
2 days
14-Oct-2004
18-Oct-2004
1st Floor Deck Framing, Plumbing Sub-slab, Waterproofing and Drain Tile, HVAC Layout & Measure
Termite Treatment Basement Slab
1 day
18-Oct-2004
19-Oct-2004
Basement Slab Preparation
Slab Inspection
1 day
19-Oct-2004
20-Oct-2004
Termite Treatment Basement Slab
Pour Basement Slab
1 day
20-Oct-2004
21-Oct-2004
Slab Inspection
Prep Garage Slab
1 day
21-Oct-2004
22-Oct-2004
Pour Basement Slab
Termite Treatment
1 day
22-Oct-2004
25-Oct-2004
Prep Garage Slab
5
Garage Slab Pour Garage Slab
1 day
H.V.A.C.
25-Oct-2004
26-Oct-2004
13-Oct-2004
04-Nov-2004
Termite Treatment Garage Slab
HVAC Layout & Measure
1 day
13-Oct-2004
14-Oct-2004
Frame Roof
HVAC Rough-in
5 days
25-Oct-2004
01-Nov-2004
HVAC Layout & Measure, Roofing Paper Installed
HVAC Set Indoor Units
2 days
01-Nov-2004
03-Nov-2004
Pour Basement Slab, HVAC Rough-in
HVAC Temporary Heat
2 days
02-Nov-2004
04-Nov-2004
Install Electric Service Panel
17-Sep-2004
09-Nov-2004
Plumbing Rough-in Plumbing Sub-slab
2 days
17-Sep-2004
21-Sep-2004
1st Floor Deck Framing
Plumbing Layout
1 day
01-Nov-2004
02-Nov-2004
Plumbing Sub-slab, HVAC Rough-in
Plumbing rough-in
5 days
02-Nov-2004
09-Nov-2004
Plumbing Layout, Municipal Plumbing Sub-slab Inspection
Municipal Plumbing Sub0 days slab Inspection
21-Sep-2004
21-Sep-2004
Plumbing Sub-slab
Municipal Plumbing Rough-in Inspection
09-Nov-2004
09-Nov-2004
Plumbing rough-in
27-Oct-2004
23-Nov-2004
0 days
Electric Rough-in Set Electric Boxes
2 days
27-Oct-2004
29-Oct-2004
Install Windows & Doors
Install Electric Service Panel
2 days
29-Oct-2004
02-Nov-2004
Set Electric Boxes
Electrical Walk-through
1 day
02-Nov-2004
03-Nov-2004
Install Electric Service Panel
Electrical Rough-wire
14 days
03-Nov-2004
23-Nov-2004
Electrical Walk-through
23-Nov-2004
07-Dec-2004
Specialty Rough-ins Central Vacuum Roughin
5 days
23-Nov-2004
30-Nov-2004
Electrical Rough-wire
Alarm System Rough-in
5 days
23-Nov-2004
30-Nov-2004
Electrical Rough-wire
Telephone System Rough-in
5 days
23-Nov-2004
30-Nov-2004
Electrical Rough-wire
Television System Rough-in
5 days
30-Nov-2004
07-Dec-2004
Telephone System Rough-in
Audio Visual Rough-in
5 days
23-Nov-2004
30-Nov-2004
Electrical Rough-wire
Municipal Electrical inspection
0 days
23-Nov-2004
23-Nov-2004
Electrical Rough-wire
Municipal Framing Inspection
0 days
24-Nov-2004
24-Nov-2004
Municipal Plumbing Rough-in Inspection, Municipal Electrical inspection
20-Oct-2004
24-Jan-2005
Roofing Roofing Paper Installed
3 days
20-Oct-2004
25-Oct-2004
Install Roof Plywood
Stock Roof Shingles
1 day
25-Oct-2004
26-Oct-2004
Roofing Paper Installed
Install Roof Shingles
7 days
13-Jan-2005
24-Jan-2005
Stock Roof Shingles, Brick Veneer
6
Exterior Finishes
27-Oct-2004
13-Jan-2005
Siding
3 days
27-Oct-2004
01-Nov-2004
Install Windows & Doors
Exterior Trim
7 days
01-Nov-2004
10-Nov-2004
Siding
Brick Arch Forms
1 day
10-Nov-2004
11-Nov-2004
Exterior Trim
Brick Veneer
45 days
11-Nov-2004
13-Jan-2005
Brick Arch Forms
24-Nov-2004
01-Dec-2004
Insulation Caulk & Air Seal
1 day
24-Nov-2004
25-Nov-2004
Municipal Framing Inspection
Draft & Fire Stop
1 day
25-Nov-2004
26-Nov-2004
Caulk & Air Seal
Batt Insulation
3 days
26-Nov-2004
01-Dec-2004
Caulk & Air Seal, Draft & Fire Stop
Municipal Insulation Inspection
0 days
01-Dec-2004
01-Dec-2004
Batt Insulation
01-Dec-2004
06-Jan-2005
Drywall Stock Drywall
1 day
01-Dec-2004
02-Dec-2004
Municipal Insulation Inspection, HVAC Temporary Heat
Hang Drywall
5 days
02-Dec-2004
09-Dec-2004
Stock Drywall
Remove Scrap Drywall
1 day
09-Dec-2004
10-Dec-2004
Hang Drywall
Tape and Finish Drywall
15 days
10-Dec-2004
31-Dec-2004
Hang Drywall, Remove Scrap Drywall
Sand Drywall
1 day
31-Dec-2004
03-Jan-2005
Tape and Finish Drywall
Drywall Point-up
3 days
03-Jan-2005
06-Jan-2005
Sand Drywall
07-Jan-2005
11-Apr-2005
Floor Finishes Ceramic Tile
15 days
07-Jan-2005
28-Jan-2005
Prime Paint Drywall
Install Hardwood Floor
4 days
23-Mar-2005
29-Mar-2005
Finish Coat Drywall
Sand, Stain, Seal Hardwood
5 days
29-Mar-2005
05-Apr-2005
Install Hardwood Floor
Install Carpet
4 days
05-Apr-2005
11-Apr-2005
Sand, Stain, Seal Hardwood
Final Coat Hardwood
2 days
05-Apr-2005
07-Apr-2005
Sand, Stain, Seal Hardwood
03-Jan-2005
25-Mar-2005
Paint Prep Drywall for Prime Coat
2 days
03-Jan-2005
05-Jan-2005
Sand Drywall, HVAC Set Indoor Units
Prime Paint Drywall
2 days
05-Jan-2005
07-Jan-2005
Prep Drywall for Prime Coat
Prep Trim for Prime Coat 2 days
17-Jan-2005
19-Jan-2005
Prime Paint Drywall, Install Interior Doors
Prime Trim
2 days
19-Jan-2005
21-Jan-2005
Prep Trim for Prime Coat
Finish Coat Trim
10 days
17-Feb-2005
03-Mar-2005
Prime Trim, 1st Punch-out Interior Trim, Install Grills & Registers for Paint
Finish Coat Drywall
14 days
03-Mar-2005
23-Mar-2005
Finish Coat Trim, Drywall Point-up
Caulk Exterior Windows & Doors
1 day
23-Mar-2005
24-Mar-2005
Finish Coat Drywall, Exterior Trim
Finish Coat Exterior Trim 1 day & Siding
24-Mar-2005
25-Mar-2005
Caulk Exterior Windows & Doors
7
Interior Trim
07-Jan-2005
17-Feb-2005
Interior Trim Delivery
1 day
07-Jan-2005
10-Jan-2005
Prime Paint Drywall
Install Interior Doors
5 days
10-Jan-2005
17-Jan-2005
Interior Trim Delivery
Install Interior Trim
15 days
17-Jan-2005
07-Feb-2005
Install Interior Doors
Install Cabinetry
5 days
07-Feb-2005
14-Feb-2005
Install Interior Trim
Install Appliances
1 day
14-Feb-2005
15-Feb-2005
Install Cabinetry, Central Vacuum Rough-in, Alarm System Rough-in, Audio Visual Rough-in, Television System Rough-in
1st Punch-out Interior Trim
2 days
15-Feb-2005
17-Feb-2005
Install Appliances, Prime Trim
03-Jan-2005
17-Jan-2005
H.V.A.C. Trim Install Grills & Registers for Paint
1 day
03-Jan-2005
04-Jan-2005
Sand Drywall
Set Outdoor Units
1 day
14-Jan-2005
17-Jan-2005
Rough Final Grade
29-Mar-2005
05-Apr-2005
Plumbing Trim Set Fixtures
4 days
29-Mar-2005
04-Apr-2005
Ceramic Tile, Install Hardwood Floor, Finish Coat Drywall, Install Cabinetry
Connect Appliances
1 day
04-Apr-2005
05-Apr-2005
Set Fixtures, Install Appliances
Municipal Final Plumbing 0 days Inspection
05-Apr-2005
05-Apr-2005
Connect Appliances
Exterior Landscaping
13-Jan-2005
28-Feb-2005
Rough Final Grade
1 day
13-Jan-2005
14-Jan-2005
Brick Veneer
Patios
7 days
14-Jan-2005
25-Jan-2005
Rough Final Grade
Porches
5 days
25-Jan-2005
01-Feb-2005
Patios
Sidewalks
7 days
01-Feb-2005
10-Feb-2005
Porches
Decks
7 days
10-Feb-2005
21-Feb-2005
Sidewalks
Driveways
2 days
21-Feb-2005
23-Feb-2005
Rough Final Grade, Decks
Final Grade and Seed
3 days
23-Feb-2005
28-Feb-2005
Driveways, Patios, Porches, Sidewalks, Decks, Set Outdoor Units
07-Jan-2005
16-Feb-2005
Electrical Final Trim Switch & Plug
2 days
07-Jan-2005
11-Jan-2005
Prime Paint Drywall, Electrical Rough-wire
Install Fixtures
1 day
11-Jan-2005
12-Jan-2005
Switch & Plug
Connect Appliances
1 day
15-Feb-2005
16-Feb-2005
Install Fixtures, Install Appliances
23-Mar-2005
14-Apr-2005
Hardware Door Hardware
2 days
23-Mar-2005
25-Mar-2005
Finish Coat Trim, Finish Coat Drywall, Install Interior Doors
Bath Hardware
2 days
23-Mar-2005
25-Mar-2005
Finish Coat Drywall, Finish Coat Trim
Mirrors
5 days
25-Mar-2005
01-Apr-2005
Bath Hardware
Shower Doors
10 days
25-Mar-2005
08-Apr-2005
Bath Hardware
8
Final Building Inspection 0 days
11-Apr-2005
11-Apr-2005
Shower Doors, Finish Coat Trim, Finish Coat Exterior Trim & Siding, Connect Appliances, Pour Garage Slab, Install Carpet, Mirrors, Door Hardware, Connect Appliances, Final Grade and Seed, Install Roof Shingles
Use & Occupancy Certificate
0 days
14-Apr-2005
14-Apr-2005
Municipal Final Plumbing Inspection, Final Building Inspection
First Walk-thru
0 days
14-Apr-2005
14-Apr-2005
Use & Occupancy Certificate
Final Punch-out
14-Apr-2005
27-Apr-2005
Punch Out Walk-thru List 4 days
14-Apr-2005
20-Apr-2005
First Walk-thru
Trim and Adjust Doors
2 days
20-Apr-2005
22-Apr-2005
Punch Out Walk-thru List
Paint Touch-up
3 days
22-Apr-2005
27-Apr-2005
Trim and Adjust Doors
23-Mar-2005
27-Apr-2005
Cleaning Windows
3 days
23-Mar-2005
28-Mar-2005
Finish Coat Trim, Finish Coat Drywall
Rough Clean
3 days
28-Mar-2005
31-Mar-2005
Windows
Final Clean
2 days
22-Apr-2005
26-Apr-2005
Rough Clean, Trim and Adjust Doors
Final Walk-through
0 days
26-Apr-2005
26-Apr-2005
Final Clean, Use & Occupancy Certificate
Move-in
0 days
27-Apr-2005
27-Apr-2005
Final Walk-through
9