CAPACITY PLANNING Teknik Industri Universitas Brawijaya

Referensi  Wiratno, S. E., Lecture PPT: Capacity Planning, IE-ITS, 2009. • Smith, Spencer B., Computer-Based Production and Inventory Control, Prentice-Hall, 1989.

Definition • Capacity is the rate at which a productive system can produce

Capacity Planning Process Prepare production schedule

Determine required capacity

Required capacity = Available capacity ? Plan adjusted capacity No

Capacity plan satisfactory

STOP

Yes

STOP

The Hierarchy of Capacity Planning Resource Planning

Production planning

Rough-cut Capacity planning

Master Production scheduling (MPS)

Capacity Requirement planning

Demand management

Material requirements planning (MRP)

Finite Loading

Input/output analysis

Shop floor control (SPC)

Vendor follow-up systems

The Relationship of Capacity Plan with Production Plan Resource plan

Production plan

Planning horizon Long

Rough-cut capacity plan

Master production schedule

Capacity requirements plan

Material requirement plan

Resource plan

Long medium

Rough-cut Capacity plan Capacity requirements plan

Medium short

Plant Production activity control

Department

Work center

Degree of detail

Resources Planning • Determines the resource needed to meet Production Plan

• The longest planning horizon (5 years) • Time bucket : month • Planning the capacity of departments or plant • Main purpose is to change or not the capacity of departments or plant (plant expansion)

• Method : Capacity Planning Factor

Rough-cut Capacity Planning • Determines the capacity required to meet MPS

• Planning horizon : the same as the MPS • Time bucket : week • Planning the capacity of departments or work centers • Main purpose is to change or not the capacity of work centers (acquire to new machine tools)

• Method : Bill of Capacity

Capacity Requirement Planning • Determines the capacity required to meet MRP

• Planning horizon : the same as the MRP • Time bucket : week • Planning the loads of machines or work centers

• Take into account : inventory and lot sizing • Main purpose : authorization of overtime or selection of alternative machines

• Method : Capacity Requirement Planning

Capacity Planning Factors (1) • Example : • Total standard hours produced last quarter 840 • Number of units of product produce last quarter 120 • Average standard hours per unit = 7.0

Department

Standard Labor Hours Produced Last Quarter

Percentage

1

305

36.3

2

535

63.7

Total

840

100

Capacity Planning Factors (1) Production Plant Next Quarter

Month

Jan

Feb

Mar

Total

Units

40

48

50

138

= 840/120 x 0.363 x 40 Resources Plan in Standard Labors Hours Dept

Jan

Feb

Mar

Total

1

101.67

122.00

127.08

350.75

2

178.33

214.00

222.92

615.25

Total

280.00

336.00

350.00

966.00

Rough-cut Capacity Planning (1)

OPERTATION ITEM NO U V W X Y

10 10 10 20 10 20 10 20

DEPT. NO

WORK CENTER NO.

RUN TIME/UNIT (STANDARD HOURS)

SETUP TIME (STANDARD HOURS)

AVERAGE LOT SIZE

1 1 2 2 2 2 2 2

15 15 35 40 35 40 35 40

1.6 2.4 1.2 0.4 1.1 0.6 0.5 2.1

2 3 1 0.5 2.1 0.6 1.4 0.5

4 6 20 20 8 8 6 6

Rough-cut Capacity Planning (2) Standard hours per unit ITEM

DEPARTMENT

WORK CENTER

STANDARD HOURS PER UNIT

U V W

1 1 2 2 2 2 2 2

15 15 35 40 35 40 35 40

2.100 2.900 1.250 0.425 1.363 0.675 0.733 2.183

X Y

= Run time per unit + (Setup time / Lot size) = 2.1+ (0.5/6) 13

Rough-cut Capacity Planning (3) Bill of Capacity DEPT

PRODUCT U WORK CENTRE

STANDARD LABOR HOURS PER UNIT

1

15

2.100

2

35

2.613

40

1.100

DEPT

PRODUCT V WORK CENTRE

STANDARD LABOR HOURS PER UNIT

1

15

2.900

2

35

1.983

40

2.608

= 1,250 + 0,733

Rough-cut Capacity Planning (4) Master Production Scheduling Week

1

2

3

4

5

6

7

8

9

10

11

12

13

U

4

3

3

3

3

4

4

5

5

6

7

7

8

V

6

7

7

7

8

8

8

8

5

4

3

3

2

Total (week)

10

10

10

10

11

12

12

13

10

10

10

10

10

Total (mounth)

40

48

50

Total (quarter)

138

Rough-cut Capacity Planning Week

1

2

3

4

5

6

7

8

9

10

11

12

13

WC 15

25.8

26.6

26.6

26.6

29.5

31.6

31.6

33.7

25

24.2

23.4

23.4

22.6

Dept 1

25.8

26.6

26.6

26.6

29.5

31.6

31.6

33.7

25

24.2

23.4

23.4

22.6

WC 35

22.4

21.7

21.7

21.7

23.7

26.3

26.3

28.9

23.0

23.6

24.2

24.2

24.9

WC 40

20.1

21.6

21.6

21.6

24.2

25.3

25.3

26.4

18.5

17.0

15.5

15.5

14.0

Dept 2

42.4

43.3

43.3

43.3

47.9

51.6

51.6

55.3

41.5

40.6

39.8

39.8

38.9

68.2

69.9

69.9

69.9

77.4

83.2

83.2

89.0

66.5

64.8

63.2

63.2

61.5

Total (week) Total (mounth) Total (quarter)

277.8

332.7

319.2 929.7

Rough-cut Capacity Planning (5) Infinite Loading 60 51.6 51.6 50

55.3

47.9 42.4 43.3 43.3 43.3

41.5 40.6 39.8 39.8 38.9

40 30 25.8 26.6 26.6 26.6

29.5

31.6 31.6

33.7 25

24.2 23.4 23.4 22.6

20 10 0 1

16

2

3

4

5

6

7

8

9

10

11

12

13

Capacity Requirements Planning

OPERTATION ITEM NO U V W X Y

10 10 10 20 10 20 10 20

DEPT. NO

WORK CENTER NO.

RUN TIME/UNIT (STANDARD HOURS)

SETUP TIME (STANDARD HOURS)

AVERAGE LOT SIZE

1 1 2 2 2 2 2 2

15 15 35 40 35 40 35 40

1.6 2.4 1.2 0.4 1.1 0.6 0.5 2.1

2 3 1 0.5 2.1 0.6 1.4 0.5

4 6 20 20 8 8 6 6

Capacity Requirements Planning (1) Item W Order quantity: 2 weeks net requirements Week Gross requirements Scheduled receipts Projected available balance Planned order releases

6

Lead time: 2 weeks Safety stock : 0 1 10 30 26

2 10

3 10

4 10

5 11

6 12

7 12

8 13

9 10

10 10

11 10

12 10

13 10

16 15

6

-4 24

-15

-27 23

-39

-52 20

-62

-72 20

-82

-92

-102

Item X Order quantity: 2 weeks net requirements Week Gross requirements Scheduled receipts Projected available balance Planned order releases

10

Lead time: 2 weeks Safety stock : 0 1 4

2 3

3 3

4 3

5 3

6 4

7 4

8 5

9 5

10 6

11 7

12 7

13 8

6

3 6

0

-3 8

-6

-10 10

-14

-19 13

-24

-30 15

-37

-44

-52

Item Y Order quantity: lot for lot Week Gross requirements Scheduled receipts Projected available balance Planned order releases

Lead time: 2 weeks Safety stock : 0 1 6 15

9

2 7 9 11 3

3 7

4 7

5 8

6 8

7 8

8 8

9 5

10 4

11 3

12 3

13 2

4 8

-3 8

-11 8

-19 8

-27 5

-35 4

-40 3

-44 3

-47 2

-50

-52

18

Capacity Requirements Planning (2) Week

Over due

1

2

3

4

5

6

7

8

U

8.4

6.8

6.8

6.8

6.8

8.4

8.4

10

V

17.4

19.8

19.8

19.8

22.2

22.2

22.2

Total (week)

25.8

26.6

26.6

26.6

29

30.6

30.6

9

10

11

12

13

10

11.6

13.2

13.2

14.8

22.2

15

12.6

10.2

10.2

7.8

32.2

25

24.2

23.4

23.4

22.6

Dept. 1 WC 15

Total (month)

105.6

122.4

118.6

Total (quarter)

346.6

Dept. 2 WC 35 W

19

29.8

28.6

25

25

X

8.7

10.9

13.1

16.4

18.6

Y

2.9

5.4

5.4

5.4

5.4

3.9

3.4

2.9

2.9

2.4

30.6

5.4

46.1

5.4

47.1

3.9

44.8

2.9

46.5

2.4

Total (week) Total (month)

82.1

101.2

51.8

Total (quarter)

235.1

Dept. 2 WC 40 W

6.5

10.1

9.7

8.5

8.5

X

4.2

5.4

6.6

8.4

9.6

Y

19.4

6.8

17.3

17.3

17.3

17.3

11

8.9

6.8

6.8

4.7

Total (week)

19.4

17.5

17.3

32.8

17.3

33.6

11

25.8

6.8

24.9

4.7

Total (month) Total (quarter)

54.2

94.7

62.2 211.1

19

Capacity Requirements Planning (2) 47.1

46.1

50 40

46.5

44.8

Capacity

30.6

30 20 5.4

10

5.4

3.9

2.9

2.4

CRP for WC 35 before Leveling

0 1

2

3

4

5

6

7

8

9 10 11 12 13

50 40 29

30 20

28 23

22

19 17

25 23.5 25 23.5

Capacity

CRP for WC 35 after Leveling

10 0 1

2

3

4

5

6

7

8

9 10 11 12 13

20

BAB VII Capacity Planning - RCCP & CRP.pdf

There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. BAB VII ...

593KB Sizes 3 Downloads 180 Views

Recommend Documents

BAB VII Capacity Planning - RCCP & CRP.pdf
planning (MRP). Shop floor. control. (SPC). Demand. management. Vendor. follow-up. systems. Page 5 of 20. BAB VII Capacity Planning - RCCP & CRP.pdf.

BAB VII PERBANDINGAN.pdf
Suatu pekerjaan pembangunan rumah jika dikerjakan oleh 8 orang akan selesai. dalam waktu 2 bulan, berapa lama jika pekerjaan pembangunan rumah itu.

BAB VII PERBANDINGAN.pdf
BAB VII PERBANDINGAN.pdf. BAB VII PERBANDINGAN.pdf. Open. Extract. Open with. Sign In. Main menu. Displaying BAB VII PERBANDINGAN.pdf. Page 1 of ...

Capacity planning for the Google backbone network
Jul 13, 2015 - Page 1 ... Multiple large backbone networks. B2: Internet facing backbone ... Service level objectives (SLO): latency, availability. ➔ Failures are ...

Generation Capacity Expansion Planning under ...
2014 IEEE Power & Energy Society General Meeting (IEEE-PES-GM 2014), National Harbour, USA, Jul. 27-31, 2014. ... of reliability constraints [4], renewable integration [5], [6], emissions control ... 2-stage Stochastic Mixed-Integer Programming (SMIP

An Optimal Capacity Planning Algorithm for ...
a three-tier web-based service system with multiple server clusters. To the best ..... service deployment. The service provisioning network supports 5 types of ab-.

Ergodic Capacity and Outage Capacity
Jul 8, 2008 - Radio spectrum is a precious and limited resource for wireless communication ...... Cambridge, UK: Cambridge University Press, 2004.

BAB III.pdf
Peningkatan komunikasi dan informasi melalui media radio. 5. Program Pengkajian dan penelitian bidang informasi dan komunikasi. Kegiatannya : 1.

Bab 1 Fungsi.pdf
Page 1 of 2. Stand 02/ 2000 MULTITESTER I Seite 1. RANGE MAX/MIN VoltSensor HOLD. MM 1-3. V. V. OFF. Hz A. A. °C. °F. Hz. A. MAX. 10A. FUSED.

BAB 4 PERNYATAAN.pdf
Page 1 of 148. Read and Download Ebook The Limits Of The Criminal Sanction PDF. The Limits of the Criminal Sanction. PDF. The Limits of the Criminal ...

Bab 1.pdf
Whoops! There was a problem loading more pages. Retrying... Bab 1.pdf. Bab 1.pdf. Open. Extract. Open with. Sign In. Main menu. Displaying Bab 1.pdf.