Project Summary Report 4147-S Project 0-4147: Investigation of Settlement at Bridge Approach Slab Expansion Joint Authors: Jean-Louis Briaud, Jeongbok Seo, Hunsoo Ha, and Tom Scullion

Investigation of Settlement at Bridge Approach Slab Expansion Joint: Bump at the End of Bridge A number of recently constructed bridge approach slabs using an articulation at mid span and the wide-flange terminal anchorage system have experienced settlement at their expansion joints (see Figures 1 and 2). This problem is more commonly referred to as the bump at the end of the bridge. It is estimated that the Texas Department of Transportation (TxDOT) spends $7 million each year for maintenance associated with the bump at the end of the bridge. This project investigated reasons for the bumps and recommended ways to improve the current situation. As part of the results, a new wide-flange terminal anchorage/bridge approach slab system that is less sensitive to weak embankments was designed and tested. The bump at the end of the bridge may look like a simple problem at first glance: the embankment

Figure 1. An Example of Bridge Approach Slab (US 290 at FM 362).

settles more than the bridge because soil compresses more than abutments on deep foundations. But the bump at the end of the bridge is a very complex problem due to many factors including compaction, drainage, embankment height, traffic level, temperature cycles, and downdrag on the abutment.

What We Did… The first year of this project undertook: • a comprehensive review of the literature,

Project Summary Report 4147-S

–1–

• a series of visual inspections, and • a series of field and laboratory tests for two selected sites. Based on first-year results, second-year work focused mainly on minimizing bumps and developing a new approach slab design. To find out possible causes of the bridge approach slab problem, the research team reviewed many publications related to bridge approach bumps. A survey of TxDOT

The investigation at the two test bridge sites with significant bumps indicated: • soil near the abutment was weaker (Figure 3) and wetter than soil away from the abutment,

Figure 2. Settlement at Approach Slab (US 290 at FM 362).

districts provided information regarding problems encountered and solutions used to minimize bumps in Texas. The researchers distributed 25 questionnaires and received 16 completed surveys. A visual survey of some bridges in the Houston District was conducted. This survey consisted of inspecting 18 bridge sites to study the bump problem and identify bridge candidates for a more advanced study. Based on results of these previous tasks and after proper consultation with the project director, researchers selected two bridge sites for detailed investigation: SH 249 at Grant Road and US 290 at FM 362. An extensive series of laboratory and field tests was performed at each site. During the second year of the project, the finite-element computer program ABAQUS evaluated behavior of the current approach slab design and of a possibly more effective design. The BEST device (Bridge to Embankments Simulator of Transition) was built to simulate the bump at the end of the bridge

Project Summary Report 4147-S

problem. Multiple BEST tests simulated a range of parameters. Finally, a new approach slab design was proposed based on accumulated data.

What We Found… Though the researchers identified many causes, interaction between cause and effect remains very complex. According to the National Cooperative Highway Research Program (NCHRP) synthesis 234, the main causes of the differential settlement at bridge approach slabs are: • settlement of the natural soil under the embankment, • compression of the embankment fill material due to inadequate fill compaction, and • a poor drainage behind the bridge abutment and related erosion of the embankment fill. The surveys received from the TxDOT districts indicated that the problem is widespread (about 25 percent of all bridges have a bump problem) and that it is costly ($7 million in maintenance and repair per year in Texas).

–2–

• soil near the abutment had a relatively high PI (Plastic Index) for an embankment fill, and • there were no voids under the pavement. Some of the most important conclusions from the numerical analyses are: • the presence of a vertically rigid abutment wall creates a major difference in settlement between the abutment wall and the embankment, • transition zone is about 40 ft with 80 percent of the maximum settlement occurring in the first 20 ft for a uniform load case, and • the optimum width of the support slabs under the approach slab is 5 ft. The new proposed approach slab design (Figure 4) is 20 ft to 40 ft long and has one span from the abutment to the sleeper slab. It is designed to carry the full traffic load without support on the soil except at both ends. The BEST test, which represents a 1/20th scale model of the typical transition, indicated that the proposed one-span approach slab

gives a smaller bump than the current two-span approach slab (Figure 5).

The Researchers Recommend… Based on results of this project, the researchers recommend the following: • Use controlled-quality backfill within 100 ft of the abutment (PI less than 15, less than 20 percent passing #200 sieve, coefficient of uniformity larger than 3). Gradually pass from that backfill to the embankment fill. Compact all fills to 95 percent of modified proctor controlled by inspection. Within the zone 100 ft from the abutment, control the compaction result with an increased frequency of measurement. • If such backfill cannot be achieved, the embankment fill within that 100 ft zone should be cement stabilized with a smooth transition to the unstabilized backfill.

Figure 3. Cone Penetration Testing Result (US 290 at FM 362).

Figure 4. Proposed New Approach Slab Design.

Use a 20 ft to 40 ft long singlespan approach slab designed to carry the full traffic in free span. The articulation in the current approach slab should be eliminated but the wide flange should be kept on the embankment side as a temperature elongation joint.

Figure 5. New Approach Slab versus Current Approach Slab: BEST Results.

Project Summary Report 4147-S

–3–

For More Details . . . The research is documented in the following reports: Report 4147-1, Investigation of Settlement at Bridge Approach Slab Expansion Joint: Survey and Site Investigations Report 4147-2, Investigation of Settlement at Bridge Approach Slab Expansion Joint: Numerical Simulations and Model Tests Research Supervisor: Jean-Louis Briaud, TTI, [email protected], (979) 845-3795 Researchers: Jeongbok Seo, Hunsoo Ha, Tom Scullion, Lee Gustavus TxDOT Project Director: Jon Holt, TxDOT, [email protected], (713) 802-5350 To obtain copies of reports, contact Dolores Hott, Texas Transportation Institute, TTI Communications, (979) 845-4853, or e-mail [email protected]. See our online catalog at http://tti.tamu.edu.

TxDOT Implementation Status December 2003 The recommendations of this study are being implemented in the majority of the new projects in the Houston District. At this point no formal implementation project is being planned. For more information contact: Dr. German Claros, P.E., Research and Technology Implementation Office, (512) 467-3881, [email protected]

YOUR INVOLVEMENT IS WELCOME! Disclaimer The contents of this report reflect the views of the authors, who are responsible for the opinions, finding, and conclusions presented herein. The contents do not necessarily reflect the official views or policies of the Texas Department of Transportation (TxDOT) or the Federal Highway Administration (FHWA). This report does not constitute a standard, specification, of regulation, nor is it intended for construction, bidding, or permit purposes.

Project Summary Report 4147-S

–4–

ITEC.PSR0301.1203.500

Investigation of Settlement at Bridge Approach Slab ...

approach slab system that is less sensitive to ... Based on results of these previous tasks .... (TxDOT) or the Federal Highway Administration (FHWA). This report ...

2MB Sizes 0 Downloads 123 Views

Recommend Documents

Differential Settlement at Bridge Approaches' in Bangladesh - IJET
bridge approaches and give possible solutions of this problem using available materials and .... DATA ANALYSIS OF FIELD TEST SITES. Fig. 4. Hatirjheel 4th ...

Lead_DC_Env_Exposure_Detection-Monitoring-Investigation-of ...
... of the apps below to open or edit this item. Lead_DC_Env_Exposure_Detection-Monitoring-Investig ... l-and-Chronic-Diseases-regulations(6CCR1009-7).pdf.

Act of Settlement [1700].pdf
X3 interlined on the Roll. Modifications etc. (not altering text). C2 S. 1 amended by His Majesty's Declaration of Abdication Act 1936 (1 Edw. 8 & 1 Geo. 6 c. 3), s.

Dynamic comparison of different types of slab tracks ...
while the FEM the flexibility of the rail and the slab to be taken into account. ... software, which allows for the study of dynamic phenomena in a wide frequency ...

Slab Leak Dallas.pdf
If the problem doesn't reappear after two days, chances are it's nothing to worry over. Of. course, it's best to keep an eye on it for a bit just to make sure. Step​ ​#2:​ ... First, go to your circuit breaker box. Find the ... the main breaker

Settlement Motion.pdf
Page 1 of 18. PLAINTIFFS' UNOPPOSED MOTION FOR. PRELIMINARY APPROVAL OF SETTLEMENT. Master Docket No. C 10-564 MJP. ROBBINS UMEDA ...

Improving Word Alignment with Bridge Languages - Research at Google
quality of a phrase-based SMT system (Och and ... focussed on improving the word alignment quality ... parallel data from Spanish (Es), French (Fr), Rus-.

2017.03.29 PSE SV investigation list - 317 investigations at 228 ...
MD JOHNS HOPKINS UNIVERSITY 8/8/2014. Page 3 of 7. 2017.03.29 PSE SV investigation list - 317 investigations at 228 institutions.pdf. 2017.03.29 PSE SV ...

NR 7-INVESTIGATION CONTINUES INTO FATAL SHOOTING AT ...
NR 7-INVESTIGATION CONTINUES INTO FATAL SHOOTING AT RICHMOND BUS STATION.pdf. NR 7-INVESTIGATION CONTINUES INTO FATAL SHOOTING ...

an occurrence at owl creek bridge
executioners—two private soldiers of the Federal army, directed by a sergeant who in civil life may .... Encompassed in a luminous cloud, of which he was now.

Improving Word Alignment with Bridge Languages - Research at Google
Google Inc. 1600 Amphitheatre .... We first express the posterior probability as a sum over all .... We now present experiments to demonstrate the ad- vantages of ...

2017.07.12 PSE SV investigation list - 344 investigations at 242 ...
2017.07.12 PSE SV investigation list - 344 investigations at 242 institutions.pdf. 2017.07.12 PSE SV investigation list - 344 investigations at 242 institutions.pdf.

Act of Settlement [1700].pdf
On 24th December 2001 victim Sunita along. with victim Saurabh and accused came to the place. ::: Uploaded on - 15/06/2016 ::: Downloaded on - 21/06/2016 11:52:45 ::: WWW.LIVELAW.IN. Whoops! There was a problem loading this page. Retrying... Act of S

Settlement Schedule - NSE
Aug 3, 2017 - In pursuance of Regulation 6.2 of National Securities Clearing Corporation (Capital Market Regulations,. 1997) it is hereby notified that the ...

Settlement Calendar - NSE
Feb 5, 2018 - Trade Date. Daily Settlement Date. 01-Mar-18. 05-Mar-18. 05-Mar-18. 06-Mar-18. 06-Mar-18. 07-Mar-18. 07-Mar-18. 08-Mar-18. 08-Mar-18. 09-Mar-18. 09-Mar-18. 12-Mar-18. 12-Mar-18. 13-Mar-18. 13-Mar-18. 14-Mar-18. 14-Mar-18. 15-Mar-18. 15-

Settlement schedule for July 2018 - Physical Settlement in ... - NSE
Jun 28, 2018 - All Members. Sub: Settlement schedule for July 2018 - Physical Settlement in Equity Derivatives. Further to circular no. NSCCL/CMPT/38039 ...

Dynamic comparison of different types of slab tracks ...
available online at: ... while the FEM the flexibility of the rail and the slab to be taken into account. .... which involves the highest computational costs. .... interest, and these are uncoupled from the track dynamics by means of the primary and

Discovery, Settlement, and Demographics
39.2. 69.5. 34.5. 22.3. 32.4. 20th. 219.7. 121.5. 152.6. 156.0. 68.9. 138.4. 49.9. 54.6. 43.0 the most inhabited island, with a population of 164,136 and a density of ...

Settlement Statement.pdf
~men! agent are shown. ltom•. malbcl "(p.o.c.)" were paid outside tho .... Settlement Statement.pdf. Settlement Statement.pdf. Open. Extract. Open with. Sign In.

Approach The Best Lawyer at The Time of Company Insolvency.pdf ...
Page 1 of 1. Approach The Best Lawyer at The Time of Company Insolvency.pdf. Approach The Best Lawyer at The Time of Company Insolvency.pdf. Open.

Settlement Calendar - NSE
Apr 6, 2017 - Office : Exchange Plaza, Bandra Kurla Complex, Bandra (E), Mumbai – 400 051. Page 1 of 2. NATIONAL ... Telephone No. Fax No. Email id.

Approach The Best Lawyer at The Time of Company Insolvency.pdf ...
Page 1 of 1. Approach The Best. Lawyer at The Time of. Company Insolvency. Doing a business is not so easy. It requires your attention 24/7. You have to.