Comments: Please see the following anticipated schedule for milestones on the project. These dates may be adjusted during the course of the project as needed. Milestone:
Dates:
Approval of contract by Owner ....................................................................................... October 13, 2015 Schematic Design Start Schematic Design ........................................................................................October 29, 2015 Owner Review Meetings ............................................................................... November 10, 2015 Schematic Design Owner Approval .................................................................... December 2, 2015
Design Development Start Design Development .................................................................................. December 3, 2015 Consultant Coordination Meetings............................................................................................ TBD Owner Review Meetings ........................................................................................................... TBD Design Development Owner Approval....................................................................January 6, 2016
Construction documents Start Construction documents ................................................................................January 7, 2016 50% Construction Documents Review Set ...........................................................January 20, 2016 100% Construction Documents .......................................................................... February 16, 2016 Approval of Plans by Owner ............................................................................... February 17, 2016
Bidding and Negotiation Plans Available to Contractors / Plan Rooms ..................................................... February 18, 2016 Pre-Bid Meeting ........................................................................................................ March 3, 2016 Bid Date (4 week bid window) ................................................................................ March 22, 2016
Construction Administration Construction Starts .....................................................................................................May 31, 2016 Substantial Completion (anticipated) ..................................................................... August 19, 2016 Owner Occupies Building (kids return) .................................................................. August 22, 2016
Board/Owner Meeting Dates: 2015 – Nov 11, Dec 9 / 2016: Jan 13, Jan 27, Feb 10, Feb 24, Mar 9, Apr 13, April 27, May 18 T:\2012\2012204.10 GN HS Central Office - Envelope\schedule\Project schedule Grinnell HS Windows 11-5-15.docx