Results of Facilities Study Facility Assessment

Oct. 12, 2016

1

What have we done? As promised, we have:  Conducted Facility Assessment of Goodhue Campus  Provided a Matrix of Condition of the facility  Looked critically at the facility to document current status of individual components

 Taken the information gathered and “scored” using a point system for each component and an overall value as the facility is measured as a whole  Provided a written narrative for the facility relating to the conditions we found  Assembled a Summary with recommendations for corrective action

2

What did we find? In general, the building scored rather low. The Goodhue facility scored 62.7 out of 100 resulting in a ‘Moderate Remodel’ rating. This is at the low end of “Moderate Remodel,” however

3

Facility Assessment

Moderate Remodel Rating Findings were a bit of a surprise: • • • •

Serious mechanical issues Several exterior wall issues Improper wall flashings Heating system is seriously outdated and subject to imminent failure • Cooling systems very limited and not centralized • Building circulation is extremely poor

4

Goodhue School- Scoring Results

PRIMARY STRUCTURE Foundation Columns & Ext Wall Floor System Roof System Subtotal

MAXIMUM 12.0 12.0 8.0 8.0 40.0

SECONDARY STRUCTURE Ceiling System Int Walls and Partitions Window Systems Door System Subtotal

3.0 3.0 2.0 1.0 9.0

ACTUAL 10.5 7.2 6.4 5.9 30.0*

2.4 2.1 1.5 0.6 6.6*

5

Goodhue School - Scoring Results SERVICE SYSTEMS Cooling Heating Plumbing Electrical Conveying Subtotal SAFETY STANDARDS Safety

MAXIMUM 10.0 10.0 6.0 8.0 2.0 36.0

ACTUAL 3.8 3.8 3.4 5.0 1.4 17.3*

5.0

3.4*

FUNCTIONAL STANDARDS Assignable Space 3.0 Adaptability 3.0 Suitability 4.0 Subtotal 10.0

1.8 1.3 2.3 5.4* 6

Goodhue School - Scoring Results PRIMARY STRUCTURE SECONDARY STRUCTURE SERVICE SYSTEMS SAFETY STANDARDS FUNCTIONAL STDS TOTAL

40.0

30.0

9.0

6.6

36.0

17.3

5.0

3.4

10.0 100.0

5.4 62.7*

*Numbers may not total to 100 due to rounding BUILDING RATING Fully Satisfactory Minor Remodel – less than 10% needed Moderate Remodel – 10 – 25% needed Substantial Remodel – more than 25% needed Unacceptable – replacement/demolition needed

95 – 100 75-94 55-74 35-54 0-34 7

Final Tally

Goodhue School Total Possible Points Actual Points Scored

100 62.7

8

What are the big issues?

There are several major deficiencies which stand out: • • • • • • • •

Steam heating system needs to be replaced 1953 electrical systems need to be replaced Exterior masonry and stucco finishes need remedial action Roof flashings/reglets are not high enough above roof Plumbing system in older portion of building needs upgrade/replacement Science labs and FACS lab sorely need remodel Security system is severely lacking Technology is very limited throughout building

9

What to do?

Reinvest in the building to restore fundamental components to safe and modern standards • •

• • •

Requires a significant investment Would require major disruption of building to accomplish infrastructure upgrades Would improve thermal efficiencies Would not address circulation issues Should be part of a ‘right-sizing’ study

10

Thoughts • Analyze current curriculum and project future curriculum needs • Generate/evaluate population demographic studies • Develop short- and long-term facility plan • Review and prioritize recommended actions in Narrative • Define and establish formal goals • Initiate formal movement forward

11

Questions?

12

Randy Lutz Presentation on 10-12-16.pdf

Sign in. Page. 1. /. 12. Loading… Page 1 of 12. Facility Assessment. Results of. Facilities Study. Oct. 12, 2016. 1. Page 1 of 12. Page 2 of 12. What have we done? As promised, we have: Conducted Facility Assessment of Goodhue Campus. Provided a Matrix of Condition of the facility. Looked critically at the facility to ...

825KB Sizes 1 Downloads 142 Views

Recommend Documents

Presentation - Optimising the guidance on significant benefit ...
Apr 25, 2017 - Industry stakeholder platform on research and development support. Presented by Matthias Hofer on 25 ... authorisation application. Page 2. Orphan environment after 16 years of EU orphan legislation. Recent developments ...

Presentation on Ebola Virus.pdf
Page 2 of 19. Ebola Awareness Ebola Awareness. Toolbox Talk. March 2014. Disclaimer: This awareness talk has been developed for educational. purposes onl It i t b tit t f f i l di l d i ly. It is not a su. bstitute for professional medical a. d. vice

Randy Ziegenfuss.pdf
Dr. Ziegenfuss knew that the librarians in the district wanted to be included in the. modernizing ... Randy Ziegenfuss.pdf. Randy Ziegenfuss.pdf. Open. Extract.

Presentation on Pre-election environment.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. Presentation on ...

Media presentation on Hepatitis B.pdf
Manufactured by Serum Institute, India. • Supplied in the Multi dose (10ml) Hepatitis B. Vaccines (rDNA). • Importer - Norvik Enterprises Ltd. • Batch number. • Manufacturing and expiry dates. • Shelf-life of 3 years. • Two purple bands (

Presentation on Pre-election environment.pdf
Issues dominating the news headlines immediately. before and during the survey. Page 4 of 80. Presentation on Pre-election environment.pdf. Presentation on ...

PowerPoint Presentation on BIMSTEC.pdf
GDP growth in BIMSTEC (approx 6%) much higher than world's (2.5% in. 2016). FDI inflows was ... Page 3 of 12. PowerPoint Presentation on BIMSTEC.pdf.

Presentation
A fast, cheap and simple analytical method. .... limited data from Jordan ... data. • Some of those: Mishor Yamin,. Revivim – Mashabim, Sde-. Boker, Shivta ...

KansansCan - Randy Watson.pdf
equate to Student SUCCESS! Creating a Vision for Kansas. Page 4 of 22. KansansCan - Randy Watson.pdf. KansansCan - Randy Watson.pdf. Open. Extract.

Town of Silverthorne v. Lutz - Inverse Condemnation
Feb 11, 2016 - real property by condemnation through the power of eminent domain.” Id. at § 9. .... source of the funds with which the Town would pay for the property it sought to ..... consider alternative locations for the Trail. ¶ 36. Assuming

Lutz selected as 2016 South Dakota Teacher of the Year
Oct 15, 2015 - Education Melody Schopp. As a member of her ... technology package from SMART Technologies and a $1,000 honorarium from the South.

Presentation Title Presentation Sub-Title
April 2010, Prahran, Melbourne. • Direct impacts ... Victoria. Currently infrastructure and facilities are designed based on past climate, not future climate. ... Sensitivity of Materials to Climate Change Impacts. Material. CO. 2. Cyclones. & Stor

Presentation Title Presentation Sub-Title
Climate change impacts – impact upon cycling conditions and infrastructure. Infrastructure and climate change risks for Vic. Primary impacts – impact upon ...

pdf-1494\quicklet-on-randy-pausch-jeffrey-zaslows-the-last ...
Try one of the apps below to open or edit this item. pdf-1494\quicklet-on-randy-pausch-jeffrey-zaslows-the-last-lecture-by-christina-st-jean.pdf.

Presentation Title Presentation Sub-Title
Helen Millicer, Member, Glen Eira BUG and Bicycle. Victoria Board. Thanks for permission to use slides from presentations given to PACIA members in Vic and ...

A presentation in LaTeX Beamer on TeX/LaTeX - GitHub
Hello World from \LaTeX ! \begin{equation}. \sum_{n .... pacman -S texlive-most. Debian/Ubuntu/Mint: ... '\input'. pdfTEX will produce a PDF file. Jack Rosenthal.

Paper Presentation On Programming FPGA's Using ...
methodology combines a C-based software design targeting FPGAs as a device and .... Company. Architecture Logic Block Type Programming Technology. Actel ... ISO/ANSI-C, it has extensions required for hardware development. ..... program size and algor