Brian Isherwood, Nadir Ansari, Peter McDonald

147

St Clair River Rail Tunnel, Sarnia Design and Construction of a Shaft for the TBM Cutterhead Retrieval Brian Isherwood IsherWood Associates Mississauga, Ontario Nadir Ansari Isherwood Associates Mississauga, Ontario Peter McDonald Deep Foundations Contractors Inc. Thornhill, Ontario Abstract The planning, design and construction of the new St Clair River Tunnel has been described in several previous papers with some mention of the unplanned Retrieval Shaft which was necessary to remove and service the Cutterhead of the Tunnel Boring Machine before it passed under the St. Clair River. This paper describes the design and construction of the shaft and touches on the difficulties and risks involved with crash-programme rescue operations.

Introduction

In late 1993 difficulties were encountered in the operation of the Tunnel Boring Machine (TBM) during mining for the new rail tunnel in Sarnia. These necessitated removing and servicing the Cutterhead before the TBM continued under the St Clair River. This paper describes the design and construction of the retrieval shaft from the viewpoint of the specialist contractor and consultant charged with its execution. Previous papers by other authors (References 2 and 4) have described the overall project and provided some comment on the shaft. The new tunnel replaces an existing 1890 rail tunnel, and accommodates modern

double stacked automobile transporter cars. It is located parallel to and approximately 27m north of the older tunnel which will be "mothballed" . The original 1890 tunnel under the St Clair River between Sarnia and Port Huron, built by the Grand Trunk Railway, continues to be recognised as an outstanding engineering achievement. It was the first international submarine tunnel.

Shaft proposals

In January 1994 the St Clair Tunnel Construction Company through its agents, Traylor Associates, invited proposals from

148

St. Clair River Rail Tunnel, Samia Design and Construction of a Shaft for the TBM Cutterhead Retrieval

specialist contractors to provide a shaft for retrieval of the TBM Cutterhead for servicing. The shaft was to be located on the Imperial Oil Refinery property about 130m from the edge of the river, in a deep (45m) deposit of near normally consolidated clay. At this location the TBM invert would be 29m below the ground surface. The shaft required a clear hoisting space of 10.1 m x 3.7m to allow the 9.5m diameter Cutterhead to be retrieved in one piece. Traylor received two proposals which it presented to the owner and owner's consultants for review: One proposal was to construct a 15.8m diameter polygonal diaphragm wall to allow excavation to 15m. From this level to 3m below the TBM a soil-crete mass would be placed by jet grouting. Additionally, soil anchors were proposed below this base to hold down the plug under a central 8xl0x 11.5m deep excavation. Deep Foundations Contractors Inc. (Deep) proposed an interlocking caisson wall scheme comprising drilled caissons 33m deep, arranged to form walls around the rectangular shaft and surrounded by a cylindrical compression wall. Various methods for a soil and/or concrete plug were still under consideration. The owner's consultant reconunended the caisson wall scheme based on potential speed of construction. Figures 1 and 2 show the site geometry. Deep had extensive experience in caisson wall installations and success in installing watertight walls in difficult saturated soil conditions, but none to this depth - the practical limit of their equipment. They had considered a number of different configurations of walls including patterns of

rectangular cells and a global pattern of caissons to form a so lid cylindrical mass, before offering the compression wall scheme. Their proposal to Traylor was subject to further investigations including a full-scale drilling test, and approval of the design. Deep had already installed an open hole caisson wall on the Imperial property 350m to the east in July 1993 as part of advance protection works for the Christina Street sewer. This was to a maximum depth of 24m, not to the 33m depth required for the proposed shaft.

Shaft Contract

Traylor gave Deep the go-ahead for the test progranune on January 21, and Deep retained Isherwood Associates (Isherwood) for the design. During the next week, Deep successfully completed the test caisson, a deep exploratory borehole (BH-l, see Figure 1) was sunk at the site, and much other data needed for design was collected. Deep's approximately two million dollar contract with Traylor dated January 28, 1994 was based on Deep's proposal and predesign sketches and specified a 12m deep 5 MPa concrete plug into which the TBM would bore. The time allowed for this work including excavation was 38 calendar days, with bonus or penalty of $1,000 per day to a limit of $10,000. The contract provided for extensions of the contract period for causes beyond the control of Deep. Because of the urgency, Deep conunenced work on January 31, 1994 based on preliminary drawings.

Brian Ishetwood, Nadir Ansari, Peter McDonald

Preliminary design

The preliminary design by Isherwood is illustrated on Figure 3 and was based on Deep's schematic sketches. The concept was to create a.circular unreinforced compression ring comprising 1.2m diameter interlocked caissons at 0.9m centres as an outer line of defence. The smaller rectangular shaft would be excavated inside this ring employing similar secant wall shoring reinforced with steel beams in every second caisson. The steel beams would terminate above the area to be bored by the TBM. The ring was to be constructed with 5 MPa concrete and intended to reduce soil pressure on the internal cross walls, which could not feasibly support the full soil pressure without strutting. The 'D' shaped areas between the walls were treated as bins, and soil load on the straight walls estimated by bin theory. A tentative plug design comprising a global pattern of 1.5m diameter caissons was included. The total number of caissons in this preliminary design was 78-1.2m and 421.5m diameter for a total of 120 caissons. Busbridge et al (1993) provided historical background and information on the soil conditions (Reference 1). Four previous shafts, two on each side of the river had been sunk in early tunnelling attempts in the 1880's, all of which were abandoned after severe difficulties with soil conditions were met, including base failure of a 7m diameter shaft on the Canadian side at a depth of 27m. The TBM data indicated that overcut in the concrete could result in a 50mm gap outside the shield. The design position then adopted was to assume no contribution of support by the TBM within the shaft structure. High strength reinforcing caissons were added in the interim whilst the effect of the resulting large voids was being further analyzed.

149

Because of the challenge of the project, the time restraints and the potential impact on the tunnelling operation, Isherwood sought design review from several sources during the project. In the early stages the primary focus was the design and installation of a plug to withstand uplift. Design alternatives under consideration included extending the cut-off walls to the underlying till, or providing anchors either to the rock or inclined within the plug as reinforcement.

Installation

Open hole caisson installation commenced January 31, 1994. Eight of nine attempted caissons were successfully installed in the first two days. The plan was to drill every fourth caisson around the ring. A blowout occurred at the second location in a granular seam at a depth of 24m when attempting to drill three diameters from the freshly poured first caisson. A repeat of this problem was avoided by staged pouring, but the remaining caissons took between 5% and 40% excess concrete over theoretical volumes. By the afternoon of February 3, 1994 clay squeeze in the holes prevented full depth drilling and only one caisson was successfully completed. Various alternative approaches to the drilling methods were tried over the next several days. An open hole closure (or interlock) caisson was attempted on the east side of the shaft (numbered 12 on Figure 3), but encountered saturated collapsing ground. Drilling under water or slurry at other locations allowed holes to be completed but was unsatisfactory for maintenance of alignment. Different configurations ofliners and vibrators were tested to achieve fifteen more caissons, by which time it was clear that major revisions to the original scheme would be necessary.

• 150

SI. Clair River Rail Tunnel, Sarnia Design and Construction of a Shaft for the TBM Cutterhead Retrieval

Shaft as designed

The design incorporating the eye reinforcement was completed during this time and is illustrated in Figure 4. The reinforcement was achieved by providing additional concrete bearing area above and below the openings by doubling the wall caissons. At the same time the plug was revised to employ 68-1.2m instead of 421. Sm diameter caissons, so that the caisson count was now 122 plus 68 for a total of 190 caissons. Further finite element analysis was undertaken to model behaviour of the structure, the effect of the tunnel eye openings, and load paths in the plug. These provided confirmation of the assumed arching behaviour and a closer appraisal of the more highly stressed areas.

Approach of TBM

As work was commencing on the shaft caissons the TBM was advancing under greatly reduced face pressures. It had just passed under the last oil storage tank on the Imperial property where surface settlements up to 130mm were reported, and then passed under a number of pipe racks before parking under 14th Street (roughly 20m east of the shaft) on February 4, 1994. Monitoring points along the tunnel centreline showed surface settlement generally in the order of 100mm following passage of the TBM. Point LT30, 7m ahead of the parked position settled from 30mm to l1Smm on Feb 4. It was expressed by others that this drawdown was possibly due to the drilling for the shaft 13m away. Figure 9 compares distance in tunnel diameters and caisson diameters from this point and shows correlation between TBM approach and the

settlement.

Changed Conditions

Whatever the cause, it was clear the clay with a sensitivity measured by field vanes between 2 and 6 and with a typical value of 3 was being disturbed, and the design should consider soil strengths less than peak in-situ strengths. Further, the most efficient method for reliably installing the caissons was to vibrate in liners with inevitable disturbance of the immediately surronnding clay. The TBM in its parked position was settling, and there was concern that entry of the TBM into the shaft would cause shaft settlement. Several schemes involving additiomil caissons for support of the TBM were examined including piled underpinning of the whole shaft as illustrated in Figure S. Numerous alternatives were considered; these included relocating the shaft to undisturbed gronnd, jet grouting or freezing below 20m depth, and a scheme employing stiff steel sheet piling for the lower shaft as shown on Figure 6. The problem which now faced the contractor was that although he could install caissons to the full 33m depth with the liner technique, he could not feasibly achieve satisfactory interlock. This impasse was overcome when Deep devised a satellite caisson scheme. In essence this involved a pattern of tangent caissons installed with liners, plus open hole closure (or dowel) caissons to achieve interlock. This scheme required a greater number of cased holes, which took more than twice the time to install as open drilled holes, and lengthened the projected schedule considerably. After considering the available options, the

Brian Isherwood, Nadir Ansari, Peter McDonald

owner decided to continue with the caisson scheme but rely on the contractors to solve the technical problems and complete the extended work in the shortest possible time. The revised design had to consider all the caissons by this time installed, and the resulting complex pattern employed 2-l.Sm, ISS-1.2m, 20-1.0Sm and SO-0.9m diameter' caissons for a total of 227 caissons (See Figure 7).

Quality Assurance

After the majority of the caissons had been installed and before attempting the excavation, additional measures were reviewed to provide further quality assurance. Much of the concrete supplied had tested significantly below strength, and records of the early installation indicated three caissons of doubtful continuity. In order to remedy these, 29 additional caissons were incorporated as indicated on Figure 8. The interlocks in the remaining closure holes were to be inspected by camera, and additional test holes during excavation, where necessary, were to probe for clay intrusions. Two extensometers through the plug and underlying clay to the till would be installed; temporary struts would be used between the walers as added security; strain gauges would be used to monitor stresses in the walers, and additional inclinometers to measure lateral movements would be installed in the shaft. The settlement of the shaft structure was to be assessed based on estimates of weight at different stages of excavation and TBM entry, and monitored at eight top-of-shaft survey locations.

151

Settlement and TBM Entry

Because the concrete weighed about IS% more than the soil, additional load on the underlying clay increased steadily during caisson installation. The liner technique required some of the casings to penetrate 2m below the base, which may account for disturbed founding soil, found in additional boreholes (BH-4, BH-S and BH-6, see Figure 1) drilled in May, 1994. The settlement history during caisson installation is shown on Figure 10. The additional vertical stress on this underlying soil was estimated at a maximum of 93 kPa, which occurred after caisson construction and prior to excavation. Subsequent operations would unload the base to an average negative surcharge of 80 kPa at full excavation. After backfilling of the shaft the surcharge stress was estimated at 42 kPa above overburden. Preparation for TBM restart commenced early May, and excavation of the rectangular shaft commenced May 17. The TBM passed under the road on May 17 and drilled into the base of the shaft on May 21. A pronounced settlement trough appeared at the road, and the fence on the west side settled an additional 700mm (Figure 11). The total settlement of900mm (Figure 12) agrees with the figure quoted by Kramer et al (Reference S) although not with their comment that this was due to the shaft excavation. The inclinometers and top-of-shaft survey recorded approximately ISmm additional eastward tilt of the shaft structure. As well, the TBM arrived in the shaft some 2S0mm low.

152

SI. Clair River Rail Tunnel, Sarnia Design and Construction of a Shaft for the TBM Cutterhead Retrieval

Shaft Excavation

Concluding Comments

The plug caissons were installed from ground surface. and therefore all the shaft excavation was in concrete. The upper portion was excavated by backhoe, but below its reach excavation was assisted by using a large diameter auger to break t~e concrete. Some clay intrusions between caissons were encountered on the west and south sides of the structure as it was excavated, but these virtually disappeared below 12m. The concrete at critical depths appeared consistent and sound. Test results on cores all exceeded design strengths. Monitoring indicated small deformations of the walls and low stresses in the walers. Based on better than expected performance the lower bracing was reduced by eliminating the poured concrete side walls and two lower walers within the depth of the TBM (Figures 13 and 14). The excavation was completed June 21. Unfortunately no meaningful information on base heave was obtained from the extensometers.

Due to the adverse conditions encountered the sinking of the shaft proved considerably more difficult than anticipated. In hindsight, significant improvements could have been made, particularly in information flow and inter-party cooperation. However, we believe the method used for TBM rescue was the best choice available, and provided a shaft which fulfilled its purpose. It is hoped that this case history of the sinking of an emergency rescue shaft in difficult soils may benefit others faced with a similar challenge.

Correction of Alignment

ACKNOWLEDGEMENTS

It was decided to raise the TBM to the correct elevation before removing the cutterhead. Explosives were used to create a 0.3m clearance in the shaft concrete above the TBM. This caused "considerable damage" to the machine (Reference 4), but had no apparent affect on the remaining shaft structure. A substantial steel mat was installed under the leading edge to spread load (Figure 14), while the articulation of the machine was used to raise the front of the TBM.

The authors wish to thank the following who provided valuable review, comment and input:

The Cutterhead was removed from the TBM and hoisted on June 30, 1994.

Dr. J.B. Curran, University of Toronto; Professor N.R Morgenstern, University of Alberta; Peter Sheffield, P.Eng., Principal, Peter Sheffield Associates; Roy Walker, P.Eng., Principal, RWB Engineering Ltd.; Richard Anderson, P.E., Tim Bedenis, P.E., Soil and Materials Engineers, Plymouth, Michigan; R Loughney, P.E., New Milford, Counecticut; and Antonio Blanco Amador, Director General, Tecnosuelo, Mexico.

Brian Isherwood, Nadir Ansari, Peter McDonald

REFERENCES 1.

Busbridge, l.R., Shirlaw, IN., Feberwee, lJ. and Ruel, M.A., (1993). "A Review of the Problems Experienced During the Construction of the 1890 St. Clair Tunnel Using Recent Geotechnical Data", Canadian Tunnelling 1993, pp. 155 - 164.

2.

Charalambu H., Finch A.P., and MacLennan D.G. (1993). "The New St. Clair River Tunnel - An Overview", Canadian Tunnelling 1993, pp. 137 - 154.

3.

Gilbert, Clare, (1991). "St. Clair Tunnel, Rails Beneath the River", Stoddart Publishing, Toronto.

4.

Harrison, N., Kerrigan, R.E. and "The MacLennan, D.G., (1994). New St. Clair River Railway Tunnel, Concept and The Project Construction", Canadian Tunnelling 1994, pp. 277 - 289.

5.

Kramer, GJ.E., Tavares, P.D., Drooff, E.R., (1994). "Settlement Protection Works for the New St. Clair River Rail Tunnel", Canadian Tunnelling 1994. pp. 291 - 302.

153

...'" ~

N 4. 8H1

-(jj)-

OF SHAFT

If\

~~

g.

+

<;;

6

[

~

IL_

,.

-/~ - '" --oda! I ~-I-I-4-"£ ~----+.4 ... I c -, 1-7------- - -

---__

PT4! /

.....

c,~,

- - .- -

i

2 .)(l

()

r:t. ()

71 i

A \) -----~ \

"oo ::;.-.,

_.

,..,,:<> .,

",Ci

-"'" -.., ""~ ;:;,:<>

o~ ..., -

-

'" """ ...,g. '" "

~APPROX. LOCATION TEST HOLE.

OJ"

«II!)!

g:::g>

'" _. "

lprn

(")2

-~ ~

[ la't/i

4~U"

Figure 1:

Site Plan

SITE PLAN

~~=~~~~~--:'==~"7i;=""==--:::;:::~~r=~

-::;";'-=""-=/--::;-

<

'~"

'"

*

+

+

<:)

<:)

(j

Z

~

i=

0

-(

iii

'" ,i!

!4TH STREET II

II

LGO

180

180

go

z I zl o : o :

~o

~I o '

l .K\j Il."j Z!Ji Zill

f ~uj

I,

i!'1l': i!'1l':

!60

'"

_ n .. , _ ,

zo I:

~o

;;.

z0

I:

i=

Il."il Zill

y.~:

II i!'1Il'll

i!'1l':

\

IIV

II

150

J' 160

150

-;e'" w

g-

'-

z0

o o p.

i=

~

[

~

"'.

j i

~

.,g

0:

ST. CLAJR TILL 140

;.)':;:<:<-»v:''''~)~~~::%~s>/';:.-%\~:

LONGITUDINAL SECTION

LOY-lER TILL

SEE FIG.1 FOR PLAN VIEW

;-·'-·r-i-r~Yrr~1 130

Figure 2:

KETTLE POINT SHALE

Longitudinal Section

91!!!

l'

Ipm

>-'

~

CI

>-'
->;;.

~ i),.

Illi:,s...:rALLATIC N CHRONOLOGY

FACE TO FACE Of PILE

JANUARY 31 - FEBRUARY :3 JAN. FEB. FEB. FEB.

~i'00~.,;:.•

.y • • /

@O·,.J

V)

'.

'.

~'O!:. /

/

;--- _

31 I 2 ;,3

HOLES HOLES HOLE HOLES

1-4 5-C! 10 11,!2

.

6

li'

~.

____ L'-"'-C

-;0-:,:"5(---"

I I \

! \ (

\ /

I \

\

I I \ /

~

2 ~ ":::-. .(')

)

~~;+'f---~------~~~~n~'~RF;,~.T-.-_.4.,-----~

.\'

o -e: . o ~

~

'"'"

., _.

i

.,-""~" _.

e ci <:i

'""'"

r/l(;

~.,

o· _ ->-l c: ~

""'" ">-lg.'"

to;;::f(' (')2

)

s.

I

V--..

,

N

PLAN -

Preliminary Sha-IT -DeSIgn

PREUMlNARYSCHEME

/

-L_L

o

-@-

/

I

~Je' "_':._:,: ...::. ~

CONGRETE

Figure 3:

[

o

INDICATES LOCATION OF INCLINOMETERS 11 SHOHN)

2:3

! !

4

5m !

J.

~~

f-a.

S;.

r

-'~'''.'-~

----- -,

--~,-~~.--.

.,----,

-",

~.---,,:>,,-"'

--~-

I'

Ii

II

II

I

Ii

r

II

~"'
Ii (}.



"

FACE TO FACE OF PtLE

W'

@

,p<3' ",1 .

.'"

(

I

ttl

\



-"'

00

",.

)

\/

~

~

"'u~

In

,..:

I \ I I

\

\

/

)

J \/

~-

~

---.l.

C~

~

0 0

p.

~

0. ::;.

~

g; p. ."

it ~

~

0

S:'"

N

-@-

o

PLAN Figure 4:

Shaft Design

INDICATES -LOCATION OF INCUNOMETI:RS SHO"'N)

tT

DESIGN ISSUE SCHEME

o

2

B

! !

4

5m !

~

U>

-..]

~--.

1\

I I \

v.lHF42x2!2

ROD HAN6ER5

I \ ! \ /

(

I \ I

\

\

)

\ J

/

~

--..!

HPI2x8CJ PILES (8 - REQUIRED)

PLAN Figure 5:

Piled Underpinning Scheme

UNDERPINNING SCHEME

o 2 B 4 5m .. I _""-_ _1 ............''-----'1_.....1

159

Brian Isherwood, Nadir Ansari, Peter McDonald

I

i

'i I

180

~'t~~ .....';

:[2 110

!

~i~ C_I=~

I

ii

""' u-

160

:.t/ :t:;~

\ (\

!J

1UNNE

T.B.a

\

~

ci

()

,

\ /

~

150

HZ

-

SHEETI~

5Z SHEETING

02468!Om ~I__~I__~I__-LI__~I__~I 140

SEt,; linN

LOWER TILL

Figure 6:

Sheet Piling Alternative Scheme

-

rplllN~ :::'LMt

LINED HOLES INTERLOCK HOLES

" SATELLITE." DRILL PATTERN

o I

PLAN Figure 7:

CHANGED SOIL CONPITIONS pESIGN SCHEME

Revised Design for Changed Soil Conditions

2 !

345m !

!

!

,~"

"-''';.

REPAIR / QlJAUTr' ASSURANGE HOLE

tl)

~.

~ ~

o o J'-

[::;.

~

p.

*~ ~

g 0:

N

i

o !

2

345m

! ! ! !

PLAN - AS-BUILT Figure 8:

Plan of Shaft As-Built

.... .... '"

...J

• 162

St. Clair River Rail Tunnel, Sarnia Design and Construction of a Shaft for the TBM Cutterhead Retrieval

SETTLEMENT OF LT30 VS. PROXIMITY OF TBM & NEAREST CAISSON 0

~

r-------

20

~

0

-......

40

E

.s

-

60

0.2

--------

~

C

(])

E (])

80

~

~

(f)

100

(JJ ~

\

\

E <1l

\

Feb 1

(])

Feb3

Feb 2

TBM

-a--

--- LT30

C5 .f:

0.8

~\

120

Jan 31

1il

0.6

U C

<1l t)

C5

~\

140

(])

0.4

~ ~

1.2

1.4

Feb 4

--><-- CAISSONS

Figure 9: Surface Settlement related to Construction Proximity TBM RESCUE SHAFT Settlement History of Shaft 0

100

E

.s

-'" c:

I~

200

x

0

\

300

so

'i

\

100

1\

E E

'" '"

(f)

400

~ x

\

150

0

\

200

x Partia!~

T6M

I. 950lcnnes. E)(ca~ation ,

02 APR

1.

I,

x'I" !

x ~oo

04-AUG 04-JUL

SETILEMENT @ POINTS -

'"

I ._,_ ..,..,.. ".,"'._.".. 2SO

I

03 JUN 03-MAY

x

of

(J)

'0

1'kli!'IO~ :h~f

\ ""x

02·MAR

'0

.!!!

:;::

1\\\

500

600 3D-JAN

-

iii

04·SEP

# OF HOLES DRILLED

NOTE: Data based on Shaft monitoring points at Ho!e 12 Feb. 4 to Apr. 8 and Pile 4 Apr. 8 to Sept. 13.

Figure 10: Shaft Settlement History related to Caisson Installation

163

Brian Isherwood, Nadir Ansari, Peter McDonald

TBM RESCUE SHAFT Fence Settlement - March 26 to June 22

[

0

r=:::

100

--------

'-....... 1\

200

/,1

\

E

E
300

\

~

'" '"

400

E ~

'"

~

r--...

500

(f)

600

\

\

700

PT1

Vi

/ / /

/

f

E.;'st /{all

West Vall

7

/

\

I

\ ...

~ /j "'"

aDo

............... ..,

PT2

PTS

f

PT4

PTS

PT6

PT7

PTa

PT10

PT9

PT11

PT12

Fence Monitoring Points )'

May 17 ...

May 4

Figure 11:

May 24

June 22

Fence Settlement

TBM RESCUE SHAFT Settlement History near STATION 10+465 0 February
·100

·200

May 4

TBM drive to + 458

STA 10

·300

E

E-

E
·400 ·500 TBM Startup

·600

\

May 17

(fJ

·700 Drilling for Shaft ·600 ·900

May 24

TBM Drive to Shaft

·1000

o

20

40

60

80

100

120

140

160

Days from job start (January 31) NOTE: Dala based on monitorin

Figure 12:

oints LT30 and Fence PT4' linear inter elation March 3·26.

Settlement History of Monitoring Points near Station 10+465

>-'

..,. ~


1:1

~. ~

0-

~-l-=--'-'f---=

i~ "g. . 0

'o" .,

EYE REINFORCINe CAISSONS

.,'"":
-m::A--

E

--~--

",Ci "'"~

f5

_.

§,~ "., o~ >-i -

~

- '"

-'

~S

III

>-i~

ttl"

s::f{'

- .,e.

Q

~~

I Q2468!Om l

Figure 13:

------..

l

I

!

I

SECTION LOOK!Nc>

r:A~ I

Shaft Sections - Changed Soil Condition Scheme

"-------'---~::::.~---::::-:--~-~

••

''-'-'~,

~-~--~~.~~-

'--'r"

,_<~_d

~

§ FIXED

EYE REINFORCIN6

PIIIH--- MANNAY

C.AISSONS E

f15o

~

(5

~

~

j i

~

g

e:.

0.

4500 MIN.

AS -

PLUS CONGRElE

SECTION LOOKINt::> '~V"'"

Figure 14:

n

Shaft Sections - As Built

BUILT

0246t}IQrn L_

J

I

!

I

I

SECTION LOOKINo

t;;M::;:> I

>-'

3:

~ ~

N 8H1

-@-

BARRIER FENcE

Of SHAFT iJ)

~~

tl

+

~

Q

c§"

~

---

~l'

!g 5 U)

trl-

--

''--,--

----------
. ---~

/

L4.4

~'

T-7\ A \~

Fi g

1 '

----------------~

PT4/

i~

o· ;:::-. n o o ::;"

""

_. ""''''' Vl~

"

""~

~~ S':=.: ~

~ TEST APPROX LOCATION HOLE.

>-l

5-" <1>

5

til,!!.

'1!

! ! !

X

s:::f;?

_."

(')8 "

lpm

~

i §:

~.

e:.

SITE PLAN Figure 1:

Site Plan

-'-'-"-'-

..

==t.....-

-_ .•, - - - - ,--

U)

~

~

5}

5}

z

G

+

~

~

"'

~

180

-f;

~

+

()

,

<--._"""-

~.-

R~

n

I 14TH

-l ,

LT30 180

z

()

I

~

1

()'

I

"-" "-"lj Illl j IIO

0.. r;

~~,

HI

irll!60

r

z()

1:; , E 1:;, ~IL'

G

z

F

E

-"'1 110 E

,1

I: IIO ~

~~!

2 I Iid' ~~I

II

IIV

110

Ii I-

~

1601

;rl

f

p.

z

~

::;'

~ w p. "

~ ~

150

150

~

[

0.

ST. CLAIR TILL

140

130

Figure 2:

>:;~>"%'0;:~~

LONGITUDINAL SECTION

-Tir-n--~

SEE FIG.1 FOR PLAN VIEW

KETTLE POINT SHALE

Longitudinal Section

9,!, I?

Ipm

....

':l

"" 00

",'"

.",.

INSTALLATION CHRONOLOGY

FACE TO FAGE OF PILE

]ANUARY31 ':FEBROARY3

• '?';;,/

~~

.JAN. 31

FEB. I FEB, 2 FEB. 3

:tu
HOLES HOLES HOLE 'HOLES

1-4 5-cJ 10 11,12

V

>!.'

6

£

t:J

'" ~.

I

I I \

r-

§

I \ l ) \ / " ~ .,-

i

I \

\

1

)

\ )

/

I

~-~

~

~~

;)S..) f

$ ci

ci

0.

Q ''"2C/l " ,.. ()

::to (j

gE o """:>0 C/l"' ","'I J:P~ " ~

~.

S"=:.: :~

irs @? ~g>

Q 2.

-" 1t ~

if J"

"0. '" Ei. "''"e:.

:>0

o

INDICATES LOCATION OF INCLINOMETERS (1 SHOHN)

1\1'

-@Figure 3:

PLAN -

Preliminary Shaft Design

PRELIMINARY SCHEME

o !

2 !

3

4

Sm

! !

0<'-

fA •

"

_

_,"-'

~

-

'

"

'

_

~

_

u

__

.

~

,

_

- ""---

-

---..-,-~--,,".

.

~~.~.--~.

__ ,.,

-

...:

-"-~

--->-~

S.Om FACE TO FACE OF PILE

~0·



,<-<0



JY-; ,,'0

J<

1\

I

I \

(

\

\

to

::l.

""

;;;<

1i

)

\ /

~

~

".

~


I \ I I \ ) \

\ )

/

~-

/

~

\:.~

f-

ciQ

0 0

P.

~ ~ ~

.,

'" p. .." to

"~ ~

~

""0:

N

-@-

OINDICATCs:.:LOGATJON OF INCLINOMETERS (7 SHOHN)

PLAN Figure 4:

Shaft Design

DESIGN ISSUE SCHEME

o

2

! !

3-

4

5m !

.....

$

I I \ X-++-+l I\ I \ \ I

ViHF42x212

IFF~~~~! IFIr~~~~~~!I - - - - iI - r \ !~ !

! \

HHF42x212

I

ROD HANeERS

I \ )

I \) : \

---------

i

\

i

I )

!

~

----~ --.--/

HP!2x,e.Q PILES (8 - REQUIRED)

b.5m

PLAN Figure 5:

Piled Underpinning Scheme

J UNDERPINNING SCHEME

o I

2 I

"

4 !

5m I

171

Brian Isherwood, Nadir Ansari, Peter McDonald

160

~D~~i

TIl 110

'\

,{ E

z

C>

~ 160

\

, f

ISO

-

~

BZ SHEETING

HZ 5HEETING

,W' 024681t.?m ~I

__-LI__~I__~I__~I__~I

1-40

,...

LOWER TILL

Figure 6:

Sheet Piling Alternative Scheme

,"

LINED HOLES !NTERLOGK HOLES

" SATELLITE" DRILL PATTERN

o !

PlAN Figure 7:

CHANGED SOIL CONDITIONS DESIGN SCHEME

Revised Design for Changed Soil Conditions

2 !

3 !

4 1

Bm !

_r"'''''_~O

~':'_';;:._;

e

REPAIR I GlUALtTY ASSURANCE HOLE

tll

::i.

§

~

lr

~

o F-

~ ~

5~. ;;0

g

t 0:

o

2:3 !

!

4 !

5m !

PLAN - AS-BUILT Figure 8:

Plan of Shaft As-Built

~

<:;l

174

St. Clair River Rail Tunnel, Sarnia Design and Construction of a Shaft for the TBM Cutterhead Retrieval

TBM RESCUE SHAFT Fence Settlement - March 26 to June 22 0

~

100

~

~

"'"

200

.sE

300

55

400

~

\

1/ V / /

/

\

E Q) 500

soo

I

\.

700

800

PT1

PT2

,

-"

.

East Nail

West 'Iall

l

1\

(f)

..

VI

i\

~

~

f---

II

~ /!

PT3

PT4

PTS

PTa

P17

PTS

PT9

PT10

PT11

PT12

Fence Monitoring Points

1Figure 11:

May 4

-

May 17 -

May 24 -

June 22

Fence Settlement

TBM RESCUE SHAFT Settlement History near STATION 10+465 0

February 4

100

= E

.s 'E Q)

E Q) EQ)

May 4

TBM driyeto STA 10 + 458

300 400 500 T8M Sta/tlJp

600

\

May 17

(/)

700 Drilling lex Shaft

800 900

'-, "-1lly24

TBM Drive to Shaft

1000

o

20

40

60

80

100

120

140

160

Days from job start (January 31) NOTE: Data based on monitorin

Figure 12:

oints l T30 and Fence PT4" linear inta

alalion March :3 . 26.

Settlement History of Monitoring Points near Station 10+465

Brian Isherwood, Nadir Ansari, Peter McDonald

175

SEITLEMENT OF LT3G VS, PROXIMITY OF TBM & NEAREST CAISSON 0

~

20

I

.1

I.

~

.s

CD

~

i' ,)

{).2

~

40

--------

~

E

c: CD E

;

0

~

6

g0

~

:!" CD

(f)

100

."

en

\

0.4

ell

0.6

\

Feb 1 -III-

Feb3

Feb 2

LT30

-e-

TBM

is .S

0.8

~\

120

Joo3t

CD CD

E

CD

()

C ell

en

~\

140

~

\

Feb 4

is

-~

1.2

1.4

-><- CAISSONS

Figure 9: Surface Settlement related to Construction Proximity TBM RESCUE SHAFT Settlement History of Shaft 0

100

i

I j, I

;--c

I:

II

E

.s E '" E'" CIl '"

C

~

50

x\

200

~

100

\

~

I'L

000

\

400

150

\

x

U1

200 TBMeg ss from shaft;

\~x


3O-JAN

xx

I 950 Exc8t°tlOn of I t nnes. OJ-MAY

x

04-AUG

03-JUN 04-JUL

SETTLEMENT @ POINTS -

04-SEP

# OF HOLES DRILLED

NOTE: Dala based on shaft monitoring points at Hole 12 Feb. 4 10 Apr. 8 lind Pile 4 Apr. 8 to Sept. 13,

Figure 10: Shaft Settlement History related to Caisson Installation ;(

I I

I

250

300

02-APR 02-MAR

'" (5

:c

Partial b ckfilling snd

I

~ =E

Cl

1\'><

500

:m

>-'

~


o ~ C§.

~

---

EYE RE1NFORC!NS CAISSONS E

6

i~ ".

p-. (')

o\::j -e.

o ~ "")0

"

--~

_.

tIl;; ,,-~

-.

;?;' ,.,., o -

~

,., _e

~

THICK

ill

"-0

"@.f!.° ::::g> oS e -.

-" 1>

[

~

[ SECTION LOOKIN<:;; NUl<. I H

Figure 13:

0246810rn I

_--.1

l

_

I

Shaft Sections - Changed Soil Condition Scheme

I

I

SECTION LOOKIN<:::>

1::"":;:01

.J


Il:l

S· FIXED

EYE REINFORCING GAISSON5

E5tIH-- HANy.,jAY

~

E

o o p.

[::;.

(5

~

i *~

T.B.M.

~

g

MAT

4500 MIN.

=--,:---

PLUG CONCRETE

SECTION LOOKINoB I~Vr"o'"

J
~

;j

Shaft Sections - As Built

e?o.

AS - BUILT 0246E>!Om ~

l

__ ---1

I

I

SECTION LOOK1NC'

t:;J'""'h:> I

>-'

:::l

St Clair River Rail Tunnel Case Study.pdf

The planning, design and construction of the new St Clair River Tunnel has been described in. several previous papers with some mention of the unplanned ...

1018KB Sizes 1 Downloads 147 Views

Recommend Documents

2015 2016 St Clair Chrome Book Start Guide.pdf
lens cleaning tissues to clean the screen. These are very convenient. and relatively inexpensive. Page 4 of 4. 2015 2016 St Clair Chrome Book Start Guide.pdf.

Band Calendar St. Clair High School 2018-2019
Band Room. September 12, 2018. Evening Rehearsal. 6-8pm. SCHS Field. September 14, 2018. Varsity Home Football. 6pm. EC Stadium ...

Anacostia River Tunnel Excavation Complete - The Lane Construction ...
Nov 7, 2016 - Company, in a joint venture with Salini Impregilo and Parsons (IHP JV) ... tunnel component of the Combined Sewer Overflow (CSO) program ...

Anacostia River Tunnel Excavation Complete - The Lane Construction ...
Nov 7, 2016 - It is the final major tunnel component of the Combined Sewer Overflow (CSO) ... latest major work to be completed in the United States by S.A. Healy, a leader in ... strategic areas including energy and mobility, helping to drive ...

2016 03 25 Rail River Link Route-100 Timetable Leaflet.pdf ...
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. 2016 03 25 Rail ...

A case study from the Mackenzie River
(b) The difference between autumn and summer freshwater change (i.e., November–December minus .... MISRA, V. M.; K. YAU and N. BADRINATH. 2000.

pdf-1448\pirates-guide-to-lake-st-clair-surrounding-waters-by-bill ...
pdf-1448\pirates-guide-to-lake-st-clair-surrounding-waters-by-bill-bradley.pdf. pdf-1448\pirates-guide-to-lake-st-clair-surrounding-waters-by-bill-bradley.pdf.

Tunnel vision - Nature
Apr 5, 2007 - on the delay between the X-ray burst and the laser pulse. The number of field maxima that can contribute to the Ne2+ signal, and so the. Ne2+ yield, changes in steps as the delay is var- ied. The steepness of the steps indicates the dur

St. Columba Anglican School Case Study.pdf
Android: A variety of affordable tablets that. are easy for schools to set up and manage,. and designed for students to share. Google Play for Education: A content ...

Dutch Rail - Eclipse
source code for open source Eclipse projects all helped them get developers up to speed. NS will go live with Donna in stages, starting in the autumn of 2007.

Dutch Rail - Eclipse
and familiar, NS set out to replace it in an effort to keep up with growing demand while keeping costs down. With such a long lifecycle for their planning software, they wanted to be sure the new version would meet their growing needs for the next fi

Tunnel Tent PDF.pdf
facilitate both storage and logistics when there are several people in the tent. Page 2 of 2. Tunnel Tent PDF.pdf. Tunnel Tent PDF.pdf. Open. Extract. Open with.

Order Order Rail-Se-Rail route.PDF
Member. 2.TheTermsofreferenceoftheCommitteewi||beasunder:-ffi. "R- 'P. "To ey'olve a mutually beneficialrail-sea-rail (RSR) policy., eru rery. 3. The committee should submit its report by 2ThFebruary 20S W. N S. 4. The Headquafters of the committee w

SOT-23 Micropower, Rail-to-Rail Op Amps ... - Linear Technology
Above the Positive Supply – Design Note 221. Raj Ramchandani. 01/00/ ... applications, where the inputs are required to operate at or above the supply.

Rail Budget.PDF
There was a problem previewing this document. Retrying... Download. Connect more apps... Rail Budget.PDF. Rail Budget.PDF. Open. Extract. Open with.

Dutch Rail - Eclipse
applications via J2EE-based server components. ... interface supporting multi monitor capabilities ... activity. Since upward of 400 users will be working in the system, preventing update conflicts ... of the Windows Clipboard to move data locally.