East Rockville Construction Projects – Public Works 2015 and 2016 September 10, 2015 Crabb Avenue Water Main Replacement Improvement (John Hollida) Project Goal / Expected Outcome - Replace aging infrastructure and improve fire flow in the water system. Construction Impacts - Excavation in the roadway. Access is maintained. Schedule – Construction - September 2015; Duration - 3 months. Budget – Construction - $1.0M Stonestreet Pedestrian Bridge Abutment Removal (John Hollida) Project Goal / Expected Outcome – Remove remnants of the former pedestrian bridge which are not needed; thereby eliminating future maintenance responsibility and liability. Construction Impacts – Minimal/No impact. Schedule – East abutment - removed Summer 2015. West abutment - September 2015; Duration - 2 weeks. Budget – Construction - $75,000 Howard Avenue Water Main Replacement (John Hollida) Project Goal / Expected Outcome - Replace aging infrastructure and improve fire flow in the water system. Construction Impacts – Excavation in the roadway. Access is maintained. Schedule – Construction - September, 2015; Duration - 2 months. Budget – Construction - $0.4M APS (Daniel Seo) Project Goal / Expected Outcome – Improve pedestrian safety; Provide countdown pedestrian signal heads and new push buttons.

Construction Impacts - Minimal/No impact (electrical work only). One location - intersection of S. Stonestreet Ave and Metro entrance. Schedule – February, 2016; Duration – 1 week. Budget - $15,000

Sharrows - North Horners (Kevin Belanger) Project Goal / Expected Outcome - Encourage bike riding. Increase the visibility and comfort of people riding bicycles on City streets. Construction Impacts – Sharrows are applied to the street. Traffic is maintained by flaggers. Applied during off peak hours. Schedule – Late October / early November, 2015; Duration – 1 day Budget - $30,000; 100% grant funded (MDOT). North Horners Force Main Replacement (Jim Woods) Project Goal / Expected Outcome - Replace aging infrastructure and increase sewer capacity. Construction Impacts – Trenchless construction; limited excavation. Schedule – Construction - Winter, 2016; Duration - 4 months. Community meeting planned – Sept 24. Budget – Construction - $0.6 M

Page 1 of 3

East Rockville Construction Projects – Public Works 2015 and 2016 September 10, 2015 Frog Run Storm Drain Improvement (Gabe Kosarek) Project Goal / Expected Outcome - Repair 1,900 LF of CMP storm drain (circa early 1960s). Line the invert with shotcrete, as well as approximately 1 dozen point repairs. Construction Impacts – Night work (9 pm - 7 am). Lane closures and access occurring at 3 manholes on Middle Lane @ Rt 355, Park Ln at Rt 355 under the bridge, and Park Ln at N. Stonestreet for 4 nights. There will also be access during the normal work hours (7 am to 5 pm) at the end of Grandin where it abuts Park Ln, and a lane closure at Reading Terrace and Grandin which will also span 4 days. Work is inside the pipe.

Schedule - Construction - November, 2015; Duration - 6 months. Budget - Construction - $0.4 M East Rockville Sanitary Sewer Capacity Improvements (Jim Woods) Project Goal / Expected Outcome – Infrastructure renewal, decrease risk of sewer overflows and increase sewer capacity. Construction Impacts - Lane and road closures, parking restrictions, excavation in roadways and on private property (within easements), park and playground closure in Maryvale Park (path / swings). Schedule – Construction - December, 2015; Duration - 12 months. Budget – Construction - $2.6 M ($1.3 M developer funded for the project) Edmonston Bridge Rehabilitation (John Hollida) Project Goal / Expected Outcome – Rehabilitate aging bridge and extend the structure’s useful life. Construction Impacts – Underside bridge repairs will be done at night which requires both WMATA and CSXT coordination. Top side repair will require a full time lane closure, one at a time, during construction. Intermittent sidewalk closures will also be used during construction. Schedule – Construction – Spring, 2016; Duration - 12 months. Budget – Construction - $1.3 M; WMATA is responsible for $0.5M per Master Agreement (MA-030) dated December 6, 1973 and Supplement No. 1 dated November 1, 1978. South Stonestreet Road Diet (Greg Lyons) Project Goal / Expected Outcome – Improve pedestrian safety and access to Metro. Provide bicycle lane. Install sidewalk on west side of S. Stronestreet Ave (Metro side). Narrow roadway (4 lanes to 3 lanes) to accommodate sidewalk without removing trees. Bike lane on east side added by a combination of sharrows and painted bike lane. Construction Impacts –Daytime lane closures outside of peak traffic hours. Schedule - Construction - Spring, 2016. Duration – 5 months. Budget – Construction - $0.4 M (80% grant funded by Complete Streets Near Metro Stations) Douglas Avenue Sewer Dig and Replace (Jim Woods) Project Goal / Expected Outcome - Replacement of aging infrastructure. Existing sewer has significant

sag which increases risk of sewer backups and overflow Construction Impacts – Construction impacts are temporary lane closures and parking restrictions Schedule – Construction – Spring, 2016. Duration – 1 month. Budget – Construction - $150,000

Page 2 of 3

East Rockville Construction Projects – Public Works 2015 and 2016 September 10, 2015 First Street Culvert (Jim Woods) Project Goal / Expected Outcome – Replace aging infrastructure to mitigate structural deficiency (culvert corrosion). Increase waterway opening to reduce potential of the stream overtopping the roadway. Improve pedestrian safety with addition of a sidewalk on east side of First Street. Add 2 off-street parking spaces to serve Maryvale Park. Construction Impacts - First Street road closure during bridge replacement; detour routes; parking restrictions. Pedestrian access will be maintained to Maryvale Park during construction. Schedule – Construction – Spring, 2016; Duration – 6 months. Budget - Construction - $1.2 M Baltimore Road (Andrew Luetkemeier) Project Goal / Expected Outcome - Create a safer, standard roadway section that will benefit the users of multiple modes of transportation through the Baltimore Road corridor from Rt 355 to Rockville High School, and 2 bump outs on Baltimore Rd at S. Horners and Grandin. Construction Impacts – Full project: Full and partial roadway closures for construction; Roadway detours; Tree removal to accommodate roadway widening; and Temporary driveway closures. East Rockville impacts limited to partial road closures. Schedule – Construction – Fall, 2016. Duration – 18 months. Budget – Construction - $5.1 M; Grant - $3.6M Concrete and Asphalt Rehab (Mike Wilhelm) Roads Possibly Being Paved in FY ’16 in East Rockville Crabb Avenue – North Horners to First Street Virginia Avenue North Grandin Avenue Woodland Road England Terrace Ashley Manor Drive Coleman Park Lane

Reading Avenue Maple Avenue Joseph Street South Stone Street Avenue – dead end Grandin Avenue – Baltimore to Joseph

Roads Delayed by Rock Creek Sewer Reading Terrace Highland Avenue Croydon Avenue South Horners Lane

*Seth Place *Park Road Charles Street

*Also affected by water line work in the next 2 years

Uni-Directional Flushing (Steve Sokol) Project Goal / Expected Outcome – Improve water quality. Construction Impacts – None. Various locations throughout East Rockville. Schedule – Fall, 2015 and Spring, 2016 Budget – $0; City staff.

Page 3 of 3

East Rockville Projects - Overview Sept 8-2015.pdf

December 6, 1973 and Supplement No. 1 dated November 1, 1978. South Stonestreet Road Diet (Greg Lyons). Project Goal / Expected Outcome – Improve ...

296KB Sizes 3 Downloads 149 Views

Recommend Documents

Digital Circuit Projects- An Overview of Digital Circuits Through.pdf ...
Counter, 7400 Series, Digital Circuit Lab Manual, Electronic Circuits, Electronic Projects, Digital Circuit. Projects, Computer Science Online, Online Laboratory ...

Copy of East Wales Wentwood Woodlark Sept 14.pdf
Sunday, 7 September 2014, 11:00. Page 1 of 1. Copy of East Wales Wentwood Woodlark Sept 14.pdf. Copy of East Wales Wentwood Woodlark Sept 14.pdf.

sept hw
A train made up of 3 carriages is pulled along a level track by a force of 16 500 N. Each of the ... A cow has fallen over a cliff and cannot get back up to the field.

sept hw
a mass of 8 000 kg, and each experiences 1500 N of resistive forces. (a) Calculate the acceleration of the train. (b) Work out the tension in link B. 5. A cow has ...

MATLAB Projects - IEEE Projects
... Human Action Recognition with Multimodal Feature Selection and Fusion. ... Medical Image Segmentation by Combining Graph Cuts and Oriented Active.

MATLAB Projects - IEEE Projects
(IEEE 2013). 2. Tracking Human with Multi-channel Interacting Multiple Models (IEEE 2013). ... MATLAB based INTELLIGIENT TRANSPORTATION. 1. CoSLAM: ...

Sept 2016facilites.pdf
Page 1 of 1. Stonington Public Schools. Board of Education Meeting. October 13, 2016. Bids\Purchase. I have a specification for the underground storage tank at WBS, but need one for. Central Office. Future – PMS lift to the music area and removal o

SEPT SERV_Food.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. SEPT ...

Overview - GitHub
This makes it impossible to update clones. When this happens, ... versions of the Yocto kernel (from the Yocto repository, or the Intel Github repositories on ...

pdf-1446\contemporary-world-cinema-europe-the-middle-east-east ...
Try one of the apps below to open or edit this item. pdf-1446\contemporary-world-cinema-europe-the-middle-east-east-asia-and-south-asia.pdf.

east river - GitHub
Page 1. EAST. RIVER. °

points-east-magazine-points-east-magazine-may-2015.pdf ...
We Make Custom Anchor Rodes! Choose Your Rope, Choose Your Chain. Add $20 Splicing Fee. $. 9999. STD-HX-150. Order# 748785. HX-150 VHF. Floating, submersible, 1030. mAh Li-Ion battery, 110 VAC. chargers with charging cradle. FLOATS! $79.99 )LQDO&RVW.

East Greenwich_Registration.pdf
Register today using the easy steps below! WHY REGISTER FOR SAFESTOP? AVAILABLE FEATURES. HOW TO REGISTER. SETTING UP YOUR ACCOUNT.

Overview - GitHub
Switch system is mobile Cashier backend sale system for merchants, which provides the following base features: Management of Partners, Merchants, Users, Cashiers, Cash registers, mPOS Terminals and Merchant's Product catalogues. Processing Sales with

notice - DC East - Delhi
Dec 27, 2013 - The candidate should report one hour before the time of interview. ... as Sr. Resident earlier on ad-hoc/ regular basis in any Govt. institution.

east river - GitHub
Page 1. °. EAST. RIVER.

notice - DC East - Delhi
Dec 27, 2013 - He will maintain a book to indicate the patients in his charge who would need attention after the night rounds and he will apprise the junior ...

MovingPlanetWaikiki-Sept 24.pdf - WordPress.com
Join Moving Planet Waikiki at the tail end of the Aloha Festival Floral. Parade on foot, on bikes, and on skateboards as we demand safer streets for bicycling and.

Sept-2.pdf
Page 1 of 9. Lindon. Elementary. Newsletter. September. 2017. -9/4: No School - Labor Day. -9/5 - 9/8: Green Ribbon Week. -9/5 - 9/8: Carnival pre-sales (Tues - Fri in the AM;. Tues - Thurs in the PM). -9/11: Carnival 5-8pm (see flier below). -9/12-9

Sept 9.pdf
Lesley University - Dr. Zrike invited Jack Gillette, Dean of the Lesley Graduate School. of Education, noting that to be aligned with Lesley University will elevate ...

Sept 2015 Forecast_Final.pdf
General Fund and State Education Fund Revenue Forecast..............28 ... lower income tax revenue from royalty payments. ... Sept 2015 Forecast_Final.pdf.

Sept 6.pdf
Peek at my week ... #4 Let's Take Turns (Kim Adsit) I'm going to leave this another ... Peek at my week-Math stations. Page 4 of 5. Sept 6.pdf. Sept 6.pdf. Open.

Sept 2015 Forecast_Final.pdf
Hickenlooper. Governor. Henry Sobanet. Director. Jason Schrock. Chief Economist. Greg Lestikow. Economist. Michael Yeadon. Economist. Page 2 of 60 ...

Sept 2015 Forecast_Final.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. Sept 2015 ...