Walnut Crossing Neighborhood Assoc

Milwood Neighborhood Assoc

 

  February 10, 2015      Dear Ms. Hensley,     We are writing to inform you of our extreme dissatisfaction with both the lack of progress  and irresponsible execution of the Walnut Creek Greenbelt Trail Project (Balcones Park to Walnut  Creek Parks) and to request action to complete this project without further delay.      As you know, the project was started sometime in 2010 but halted in 2011 due to multiple  problems  including  a  contract  dispute  and  problems  with  construction  plans.  One  section  of  trail  was completed east of Mopac, south of Cedar Bend. A bridge in Balcones Park has been left with  exposed rebar that is a safety hazard to park users and traps flood debris. The trail east of Mopac  was never properly backfilled and has been defaced with graffiti.       The  project  was  eventually  redesigned  and  rebid  with  a  contract  awarded  on  2/14/2013.  Shortly  after  construction  began,  Walnut  Crossing  and  Milwood  Neighborhood  Associations  negotiated  a  commitment  from  project  management  to  redesign  the  section  of  the  trail  through  Balcones Park to minimize effects on adjacent homeowners and to eliminate an elevated section of  trail that was completely out of scale with the park. As a result, a sidewalk was reconstructed to  provide ADA access from the Balcones Park Trailhead to a trail head on Scribe Drive. Meanwhile, a  section of the trail was completed in TXDOT’s ROW and was opened to the public approximately  1  year ago. Work then began in Walnut Creek Park with large sections of the park including the Log  Loops and the Tar Branch Trails closed off from public access. Two bridges over  the small creeks   and a parking lot have been completed with a short section of trail opened. The trail section by the  Log Loops and main bridge over Walnut Creek is still unfinished, yet now the contractor has begun  clearing  between  Metric  and  the  park  and  started  another  bridge  over  Walnut  Creek  east  of  Mopac.  The  slow  pace  of  this  project  defies  explanation  and  it  is  unfathomable  as  to  why  the  contractor was not required to complete the Walnut Creek Bridge and trail in Walnut Creek Park  before being allowed to move into new areas. We are concerned that if there is another contract  dispute,  an  even  larger  area  of  unfinished  construction  will  be  left  without  proper  safety  and  environmental protections (it took the neighborhood months of repeated requests to City staff to  maintain safety and environmental controls in 2011 when the previous contractor walked off the  job.)    Last  fall,  after  promised  status  updates  were  not  provided,  MNA  pressed  project  management  staff  and  were  then  told  that  the  redesign  and  construction  of  the  Balcones  Park  section  of  the  trail  would  be  delayed  due  to  Federal  Endangered  Species  Listing  of  the  Jollyville  Salamander and a wastewater project. We were told this section of the trail would be incorporated  into the wastewater project, for which the schedule and funding are both unsecured, to the best of  our knowledge.  The overlap in projects given as an excuse for delaying the trail; is a false pretense.  The  overlap  in  the  project  only  involves  access  for  construction  for  an  approximate  425  foot  section. In this area, there is an existing roller compacted concrete trail constructed in the 1980’s  Walnut Crossing Neighborhood Assoc 12105 Scribe Dr Austin, TX 78759 (512) 470-3123 www.wxna.org

Milwood Neighborhood Assoc PO Box 81224 Austin, TX 78708 (512) 636-9176 www.milwoodna.com

Walnut Crossing Neighborhood Assoc

Milwood Neighborhood Assoc

for sewer access and as a neighborhood amenity. To delay the approximately 1800 feet needed to  connect  the  trail  from  the  trailhead  at  Balcones  Park  is  a  disservice  to  the  community  who  have  been  waiting  for  this  project  to  be  completed  for  over  5  years  now.  Ironically,  a  sign  has  been  erected at the Balcones Park Trailhead giving the distance to Walnut Creek Park. Yes, you can get to  Walnut Creek from the trailhead, but not on the trail this project was intended to deliver, and from  the way things are going; not anytime soon.    We  believe  the  salamander  listing,  while  important,  is  not  a  significant  impact  to  project  completion.  The  watershed  from  the  proposed  trail  area  bypasses  the  spring  where  the  salamanders  are  found.  Curiously,  the  asphalt  accumulations  in  the  rock  berms  installed  in  a  tributary  that  does  drain  to  the  stream  above  the  salamander’s  habitat  have  not  been  removed,  despite notification to the City’s project staff.    The prospect of another year or more before the project completion and park restoration is  untenable to the neighborhoods. The park receives regular use by hikers, trail runners, cyclists and  is used as an outdoor classroom by Summitt Elementary. Additionally, the dam for Waters Park, an  important historical site, is nearby.       Quite  simply,  the  neighborhoods  want  the  project  completed  and  the  park  restored.  MNA  and  WXNA and members of the community volunteer every year to clean up litter and help maintain  the park. Over the past two years we have removed years of accumulated trash in the Mopac area  to  begin  reclaiming  the  trail  area  from  the  dumping  ground  it  had  become.  However,  the  never‐  ending construction remains an obstacle to this effort. Community members are concerned about  safety in the Greenbelt area due to the unfinished project. Construction sites are magnets for trash;  safety  fence,  silt  fence  remnants,  rebar  protective  caps  and  mulch  sock  netting  litter  the  creek  downstream  of  the  project  area.  We  all  know  that  neglect  breeds  more  neglect.  Impromptu  campsites  and  graffiti  along  the  trail  east  of  Mopac  are  evidence  of  this.  When  the  project  is  complete, regular use by hikers and bikers will deter illicit activity and result in less litter and graffiti  in the park and greenbelt.    Action requested by the Neighborhood Associations:     Instruct project management to take steps to accelerate completion of the entire project,  including the Balcones Park section. Require the contractor to furnish additional resources  such as extra crews or weekend work to complete paving without further delay.     Initiate  design  of  the  Balcones  Park  section  immediately,  present  the  design  to  the  neighborhoods for review, and proceed to complete construction without further delay. If  any overlap of the wastewater project is an issue, make a temporary repair of the existing  trail to enable use of the entire trail from Balcones Park to Walnut Creek Park.     Restore the eroded hillside on the abandoned trail in Balcones Park   

Walnut Crossing Neighborhood Assoc 12105 Scribe Dr Austin, TX 78759 (512) 470-3123 www.wxna.org

Milwood Neighborhood Assoc PO Box 81224 Austin, TX 78708 (512) 636-9176 www.milwoodna.com

Walnut Crossing Greenbelt Trail Letter 2-10-2015.pdf

Feb 10, 2015 - PO Box 81224 Austin, TX 78708. (512) 470-3123 www.wxna.org. (512) 636-9176 www.milwoodna.com. February 10, 2015. Dear Ms. Hensley,.

1MB Sizes 2 Downloads 157 Views

Recommend Documents

Walnut Crossing Greenbelt Trail Letter 2-10-2015.pdf
Feb 10, 2015 - and irresponsible execution of the Walnut Creek Greenbelt Trail Project (Balcones Park to Walnut. Creek Parks) and to request action to ...

The Balcones Neighborhood Pool is the 6 most uti - Walnut Crossing ...
May 28, 2015 - The P.A.R.D. Aquatics Division and the Open Space, Environment, and Sustainability Committee and ultimately the ... (29 total) from 2012-2013 Data at $2.30/participant. - District 7 ... City Map of Pools in the City. - Aquatics ...

The Balcones Neighborhood Pool is the 6 most uti - Walnut Crossing ...
May 28, 2015 - Last year the city cut several days and hours causing the pool to open later and lose ... (29 total) from 2012-2013 Data at $2.30/participant.

Old Trail School Letter from Educators' Collaborative (February 13 ...
Try one of the apps below to open or edit this item. Old Trail School Letter from Educators' Collaborative (February 13, 2016).pdf. Old Trail School Letter from ...

Old Trail School Letter from Educators' Collaborative (February 13 ...
Old Trail School Letter from Educators' Collaborative (February 13, 2016).pdf. Old Trail School Letter from Educators' Collaborative (February 13, 2016).pdf.

Strawberry Feta Walnut Summer Salad.pdf
1 Tbsp honey. 1 tsp chopped fresh thyme. Page 1 of 1. Strawberry Feta Walnut Summer Salad.pdf. Strawberry Feta Walnut Summer Salad.pdf. Open. Extract.

Clip #8—Greenbelt News Review Article—County Historical ...
Clip #8—Greenbelt News Review Article—County Historical Society Special Library Is Here (PAGE 7).pdf. Clip #8—Greenbelt News Review Article—County ...

2018 May Walnut Review.pdf
After a breakup, Elle becomes deter- mined to follow her ex-boyfriend Warner. (Jackson Coslit) to ... Spring DIY's ... 2018 May Walnut Review.pdf. 2018 May ...

News from Walnut Acres Elementary
Last day to submit Entry forms is today March 5th. Please ... If you would like to submit a last minute ... FIFTH GRADERS: WHO WANTS TO BE A GUY OR DOLL.

Clip #8—Greenbelt News Review Article—County Historical ...
Clip #8—Greenbelt News Review Article—County Historical Society Special Library Is Here (PAGE 1).pdf. Clip #8—Greenbelt News Review Article—County ...

Att B - I-5 East Duwamish Greenbelt Operational Plan.pdf ...
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. Att B - I-5 East ...

Trail Menucourt - Rev'7 Trail 2012.pdf
There was a problem loading this page. Retrying... Trail Menucourt - Rev'7 Trail 2012.pdf. Trail Menucourt - Rev'7 Trail 2012.pdf. Open. Extract. Open with.

SLG07.1 Trail 2016_06_18 Trail du mortier 22,2km.pdf
SLG07.1 Trail 2016_06_18 Trail du mortier 22,2km.pdf. SLG07.1 Trail 2016_06_18 Trail du mortier 22,2km.pdf. Open. Extract. Open with. Sign In. Main menu.

Tri-County Metro. Trans. Dist. v. Walnut Hill, LLC
Jun 20, 2018 - Tri-Met v. Walnut Hill, LLC single-family residence on a roughly half-acre lot. George and Marie Corti acquired the property in the 1950s and.

Clip #8—Greenbelt News Review Article—County Historical ...
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. Main menu.

Greenbelt Community Garden Club Garden Health Guide.pdf ...
Greenbelt Community Garden Club Garden Health Guide.pdf. Greenbelt Community Garden Club Garden Health Guide.pdf. Open. Extract. Open with. Sign In.

letter
Dec 9, 2002 - by neural-crest cells for proper development of neural-crest-derived structures. Neverthe- less, our data indicate a genetic requirement.

TRAIL - GENERAL.pdf
46 - CHIMAY - 12.03.2017 - 15,8 kms - TRAIL - GENERAL.pdf. 46 - CHIMAY - 12.03.2017 - 15,8 kms - TRAIL - GENERAL.pdf. Open. Extract. Open with. Sign In.

Pulau Ubin Tree Trail
Page 1 ... get a good insight of village life as you embark on this well-shaded trail. This trail, which starts in ... How to get to Pulau Ubin. Take a bumboat from ...