MS 3000 Holistic Transformer Monitoring Solution Faced with increasing pressure to continuously improve network availability and reliability, asset owners are now often looking for increased coverage on their important transformers. Continuously monitoring the transformer’s main components (active part, bushings, tap changer, cooling system) is key to maximizing transformer availability, reliability and performance while reducing the life-cycle cost. Asset owners are therefore expanding beyond Dissolved Gas Analysis (DGA) and connecting to or adding more sensors to extend their online monitoring reach. GE’s MS 3000 holistic and modular transformer monitoring system enables essential to comprehensive coverage of the most common causes of failure. It lets you combine the outputs of available sensors to form a homogeneous data flow coming from a single source. It uses analysis and sophisticated models to prevent data overload and deliver an aggregate view of the health of the transformer’s main components, providing intelligent alarms, diagnostics and suggested operational next steps. The MS 3000 is an “Expert System” which helps you confidently assess a transformer’s condition and optimize its operation and maintenance.

Key Benefits • Continuous supervision of the whole transformer, integrating data from available sensors • Modular: essential through to comprehensive coverage of transformer failure modes • All information available at a glance, even across several substation transformers • An “Expert System” to help you assess and manage your costly assets • Optimum operation efficiency with reduced life-cycle cost

Dissolved Gas Analysis • Combines with any GE or other DGA monitor and provides even more powerful diagnostics by correlating with load and temperature

Active Part Supervision • A transformer’s active part (e.g. core, winding, insulation, leads) has a finite design life • Extending it requires detecting stress situations causing premature degradation and correcting them

Bushing Monitoring • Bushing failures represent approximately 17% of sub-station transformer failures* • Many of these are "catastrophic" leading to total loss of the transformer with significant additional collateral damage

Cooling System • Common causes of overheating (like nonfunctioning fans) can easily be detected • Cooling efficiency can be improved

• Web server HMI, no need for software to access the data analysis

On Load Tap Changer

• Integration with GE's Perception software for centralised information and leveraging of fleet data**

• When present, OLTC, can account for up to 26% of sub-station transformer failures*

• Easy inter-operability of the transformer with the Smart Grid / Digital Substation

Applications While more specifically aimed at transformer assets where the loss of availability has severe consequences for the network, the MS 3000 benefits from a highly flexible and modular design enabling it to adapt to a wide range of customer demands and types of applications: • Suitable for most transformer types and ratings, independent of manufacturer • Applicable to new and existing transformers • Used in power generation, transmission and distribution

• The regular maintenance of frequently working OLTCs can also be optimized

Electrical Stress Detection • Partial discharge and transient over-voltages can erode/damage solid insulation if not detected and removed or attenuated

Decision Aids

• Special solutions for HVDC applications

• Transformer health status report can quickly and easily be produced using report generator

• Ideal for industries with process interruption risks

• Built-in simulator lets you understand the implications of external or internal events

A MODULAR AND FLEXIBLE SOLUTION Expert System Algorithms for analyzing the data acquired online are implemented in the software and reflect GE’s extensive experience with transformers. The expert system highlights issues through configurable alarms and provides clear correlated information as well as recommendations concerning the transformer continued operation, the suggested “next steps” and the need for service/maintenance.

Load • Load currents (A) • Over-currents (A) • Total number of over-currents (A) • Load factor (A) • Overload capacity (A) • Emergency overloading time (A) • Apparent power (A) • Active power • Reactive power • Transformer power factor (cos φ) • Transformer losses

COVERING THE KEY TRANSFORMER ELEMENTS

Insulation

Bushings

• Top oil temperature (A) • Bottom oil temperature • Calculated hot spot temperature (A) • Winding temperature • Moisture in insulation paper (A) • Bubbling temperature (A) • Bubbling safety margin (A) • Breakdown voltage (A) • Lifetime consumption (A) • Ageing rate (A)

• Operating voltages (C) • Transient lightening over-voltages (C) • Total number of over-voltages (C) • Change of C1 capacitance (C) • Power factor (tan δ) • Oil/SF6 pressure/density

• Detection of fast transient over- voltages (up to 5 MHz) caused by network switching • Capture of full waveform

Partial Discharge

• Gas in oil content (1 to 9 gases) (A) • Gas in oil rate of change (A) • Moisture in oil content (A) • DGA in OLTC

• Electrical PD • UHF PD

A modular and configurable system that can monitor the various key components of a power transformer listed here, depending on the asset owner's requirements.

Letters (A), (B) or (C) indicate inclusion in the various standard configuration kits, see back page for details.

Cooling System

On Load Tap Changer

2

Both off-line and online data can be analysed. DGA using the most common diagnostic tools: Duval’s triangle, Rogers and Doernenburg ratios, Key Gas methods, etc… as per IEEE C57.104 and IEC 60599. Users can select the method most appropriate to their situation. They can also perform Furfural determination and oil condition evaluation according to IEC 60422:

Transient Over-Voltage

Dissolved Gas Analysis

• OLTC position (A) • Number of switching operations (A) • Number of operations until service (A) • Cum. switched load current (A) • Cum. current until service (A) • Power consumption of motor drive (B) • Motor drive current • Operation timing (B)

Oil Analysis

• Assessed mechanical condition (B) • Energy index (B) • Contact erosion • Gas in oil content • Moisture in oil content • Oil temperature • Oil temperature differences • Oil level in OLTC

Environment • Ambient temperature (A) • Ambient humidity • Cabinet temperature

Other measures • Oil level in main tank • Oil pressure • Humidity of air inside conservator • Gas quantity/gradient in Buchholz relay • Other digital and analogue inputs • Other parameters on request

• Operating condition of individual/group fans and pumps (A) • Operating time of individual/group fans and pumps (A) • Cooling efficiency (Rth) (A) • Cooling power • Inlet and outlet cooling system temperatures • Difference of inlet & outlet temperatures • Oil/water flow • Current consumption of individual/group fans and pumps • Intelligent cooling control for conventional and speed controlled fans

HMI

Sophisticated Modelling

Simulator

Report Generator

The Web server built into the MS 3000 provides web pages in several languages which can be accessed using a standard web browser. The key data overview screen will highlight any alarm and enable to drill down into more specific data. When part of a transformer fleet, integration with GE's Perception software** enables centralised information, leveraging of fleet data and fleet health ranking.

With a multitude of sensors constantly delivering refreshed online data, the MS 3000 uses sophisticated models to analyse all this data, correlate it when additional sources are available and convert the data into actionable information in order to enable the asset owner to get the most out of the transformer.

The built-in simulator module allows the user to simulate external events or internal transformer events and to study the corresponding effect on the transformer’s behavior. It can be invaluable for weighing up options when faced with a difficult decision but can also be used for training of personnel.

The configurable report generator quickly and easily creates a user-friendly report on the status of the transformer and of its main components. The report can be created on demand for selected monitored functions over a specified time frame.

GEGridSolutions.com

GEGridSolutions.com

3

Modular monitoring solution for power transformers The MS 3000 is a globally recognized online monitoring solution with well over 1,000 installations worldwide which benefits from extensive transformer manufacturing DNA. It is a powerful tool that concentrates most of the transformer data available and combines it with sophisticated models, diagnostic algorithms and practical experience to help the user evaluate the health of the transformer, monitor its current performance and optimize its operational efficiency. The MS 3000 is modular and highly configurable so that it can accommodate a wide range of specifications or customer requirements surrounding monitoring of the 6 main areas responsible for the failure of power transformers. Standard configurations are also available to cover typical requirements. Its wide range of communication options facilitates connection to SCADA systems, data historians and Asset Performance Management (APM) systems. All this is provided by a single vendor with extensive transformer manufacturing and monitoring experience, which supports the customer from conception to deployment, ensures that the solution meets expectations and stands by it for the long term.

Technical Specifications CUSTOMIZED SOLUTION Flexible System • • • • •

Fully configurable system to meet wide set of specifications Scalable addition of sensors and functionalities Flexible architecture to meet site requirements Ability to integrate existing sensors and monitors Working with all transformer designs and makes

Implementation support • • • •

Detailed review of suitable options Advice on sensor requirement and positioning Optional planning site visit Solution project management

Successful delivery • • • •

Extensive testing of solution prior to shipping Commissioning on site Training of personnel Global service support

STANDARD CONFIGURATIONS Kit 1 – Base Module (A): • Dissolved Gas Analysis • Load • Insulation • Environment • Cooling System • Basic OLTC

GENERAL FEATURES Modular

Kit 2 – Base Module + Extended OLTC (A+B): • Features of "Base Module" • Extended OLTC monitoring Kit 3 – Base Module + Bushing (A+C): • Features of "Base Module" • Bushing monitoring Kit 4 – Base Module + Bushing + Extended OLTC (A+B+C): • Features of "Base Module" • Bushing monitoring • Extended OLTC monitoring Specific content indicated in centre page by letter coding

Sensors and monitoring capabilities as required.

Reliability

Fan-less, robust design for on-transformer installation.

Data

Lifetime data management and storage, using solid state disc (SSD).

HMI

Built-in Web server, available in several languages.

Communications Protocols

Wide range of communication interfaces. IEC® 60870-5-101/104, Modbus®, DNP3, IEC 61850

ENVIRONMENT Operating temperature

-40°c to +55°C -40°F to +131°F

Operating humidity 95% non condensing Enclosure rating IP 55 standard, IP 66 optional Power requirements 100 - 240 Vac 50/60 Hz 85 - 375 Vdc Dimensions

600 x 600 x 250 mm (23.6” x 23.6” x 9.8”) for small enclosure used in standard kits. Up to 600 x 1200 x 300 mm (23.6” x 47.2” x 11.8” for enclosure of large customized systems.

Weight

* Source: Cigré WG A2.37

From 30 to 100 Kg (66 to 220 lb) depending on configuration

** Coming soon in 2016

GE Grid Solutions Lissue Industrial Estate East Unit 1, 7 Lissue Walk Lisburn BT28 2LU United Kingdom Tel: +44 (0) 2892 622915

GEGridSolutions.com Modbus is a registered trademark of Schneider Automation Inc., IEC is a registered trademark of Commission Electrotechnique Internationale, IEEE is a registered trademark of the Institute of Electrical and Electronics Engineers Inc. Cigré is a registered trademark of Conseil International des Grands Réseaux Electriques. GE reserves the right to make changes to specifications of products described at any time without notice and without obligation to notify any person of such changes. GEA-31984 Copyright 2016, General Electric Company.

English 160614

03. MS 3000_Monitoreo Integral de Transformador.pdf

providing intelligent alarms, diagnostics and suggested operational next steps. The MS 3000 is an “Expert. System” which helps you confidently assess a ...

2MB Sizes 0 Downloads 112 Views

Recommend Documents

Descargar libro de calculo integral de larson pdf
Page 1 of 21. Descargar libro decalculo integral delarson pdf ... paracelular nokia n9.descargar navegador gps garmin paraandroid.como descargar videos de ...

GICUV-Sistema-de-Gestion-Integral-de-la-Calidad.pdf
There was a problem loading more pages. Retrying... GICUV-Sistema-de-Gestion-Integral-de-la-Calidad.pdf. GICUV-Sistema-de-Gestion-Integral-de-la-Calidad.Missing:

Integral trigonometri & integral tak tentu.pdf
Page 1. Whoops! There was a problem loading more pages. Retrying... Integral trigonometri & integral tak tentu.pdf. Integral trigonometri & integral tak tentu.pdf.

GO Ms 25 Dated 11-03-2016.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. GO Ms 25 Dated ...

Diagnóstico Integral del Centro de Medellín.pdf
3. Page 4 of 73. Diagnóstico Integral del Centro de Medellín.pdf. Diagnóstico Integral del Centro de Medellín.pdf. Open. Extract. Open with. Sign In. Main menu.

Cazadores-de-sombras-03-Ciudad-de-Cristal.pdf
mientras saltan las chispas. Job 5:7. Page 3 of 378. Cazadores-de-sombras-03-Ciudad-de-Cristal.pdf. Cazadores-de-sombras-03-Ciudad-de-Cristal.pdf. Open.

Cazadores-de-sombras-03-Ciudad-de-Cristal.pdf
Page 1 of 13. Exercices de révision- Oxydo-réduction et Piles électrochimiques, SMPC2, fsr. 2015. Prs . A. Eyahyaoui, A. Zrineh at M. Alaoui Elbelghiti. Université Mohammed V. Faculté des Sciences. Département de Chimie. Rabat. Année Universit

Cazadores-de-sombras-03-Ciudad-de-Cristal.pdf
Page 3 of 378. Traducido por Aurim. Pandoranium Página 3. PRIMERA PARTE. Saltan las Chispas. El hombre nace para el problema. mientras saltan las chispas. Job 5:7. Page 3 of 378. Cazadores-de-sombras-03-Ciudad-de-Cristal.pdf. Cazadores-de-sombras-03

Cazadores-de-sombras-03-Ciudad-de-Cristal.pdf
Page 2 of 378. Traducido por Aurim. Pandoranium Página 2. Índice. Parte Primera: Las Chispas Vuelan Hacia Arriba. 1. El Portal .

Cazadores-de-sombras-03-Ciudad-de-Cristal.pdf
mientras saltan las chispas. Job 5:7. Page 3 of 378. Cazadores-de-sombras-03-Ciudad-de-Cristal.pdf. Cazadores-de-sombras-03-Ciudad-de-Cristal.pdf. Open.

03. Carteles de ecoescuela.pdf
... la Higuera hemos hecho. unos carteles para recordarle a todos como hay que tratar al. planeta. (escribimos que cosas podemos tirar al contenedor amarillo).

03. El Ascenso De Nueve.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. 03. El Ascenso ...

03 - Caricias de Hielo.pdf
Page 2 of 318. 2. La Colmena. Flechas. Mercury era una secta. Eso era lo que todo el mundo decía al principio. Los psi se. rieron de Catherine y Arif Adelaja ...

Comprension de oraciones 03.pdf
Felipe lee un libro de cuentos. Felipe hace los deberes de mates. Felipe hace los deberes de lengua. Daniel se monta en una colchoneta. Daniel está sentado ...

03 Compactadora de Papel.pdf
REPORTE DE PROYECTO INTEGRADOR .... Salida de actuadores: Los pistones se activan uno a uno, de esta manera ... 03 Compactadora de Papel.pdf.

03 Brillante de Emma Green.pdf
Emma Green. Page 3 of 35. 03 ♥ Brillante de Emma Green.pdf. 03 ♥ Brillante de Emma Green.pdf. Open. Extract. Open with. Sign In. Main menu. Displaying 03 ...

Portaria MS n 3.432, de 12 de agosto de 1998.pdf
terço dos mesmos ser do tipo microprocessado;. Page 3 of 6. Portaria MS n 3.432, de 12 de agosto de 1998.pdf. Portaria MS n 3.432, de 12 de agosto de 1998.

La integral de Lebesgue un poco más de cien a˜nos ...
[37] D. Paunié, History of Measure Theory, Handbook of Measure Theory, Edi- ted by E. Pap., Elsevier, Amsterdam (2002), 3-28. [38] T. De Pauw, Autour Du ...

Integral-Leadership-The-Next-Half-Step-SUNY-Series-In-Integral ...
Using the insights of Integral Theory, particularly Ken Wilber's AQAL framework, the authors provide a simple yet elegant. outline that ... a total on-line electronic digital collection that offers entry to many PDF document catalog. You might find m

Integral Religion
the means by which it will progressively reveal itself here. It implies a growing ...... Then the cloud covered the Tent of Meeting, and the glory of the Lord filled the ...

Definite Integral
... kCga[lfcLucl[uLsm. Worksheet by Kuta Software LLC. -2-. 11) ∫1. 4. 5 x3 dx. 12) ∫0. 1. (−x5 + 3x3 + 1) dx. 13) ∫−3. 0. (x + 2) dx. 14) ∫0 π. 6. −sec xtan x dx.

56814989-Manual-Basico-de-Emulsiones-Asfalticas-MS-Nº-19.pdf ...
56814989-Manual-Basico-de-Emulsiones-Asfalticas-MS-Nº-19.pdf. 56814989-Manual-Basico-de-Emulsiones-Asfalticas-MS-Nº-19.pdf. Open. Extract. Open with.

Cronograma de atribuição 2018 - 22-03 e 23-03-2018.pdf ...
Whoops! There was a problem loading more pages. Whoops! There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. Cronograma de atribuição 2018 - 22-03 e 23-03-2018