Bruce Monroe at Park View Update February 9, 2016
District of Columbia Public Schools
|
1200 First Street, NE | Washington, DC 20002 | T 202.442.4800 | F 202.442.5517 | www.k12.dc.us
DCPS | OCOO
Agenda SIT Coordinator Introduction Review of 2012 Kitchen/Cafeteria design Kitchen/Cafeteria Design Site Work Challenges & Limitations
Review of other potential projects Interior Projects to meet Ed Spec Exterior Projects
Next Steps
2
DCPS | OCOO
2012 Cafeteria Rendering
3
DCPS | OCOO
2012 Ground Floor Design
4
DCPS | OCOO
2012 Site Plan Existing Condition
Existing Condition
5
DCPS | OCOO
2012 Kitchen/Cafeteria Design Kitchen area would have to be excavated to bring kitchen and prep area to the same grade as dining. Serving would have to remain in the dining area. Parent Resource center would have to relocate.
6
DCPS | OCOO
Potential Challenges An architect will need to lay out the cafeteria to estimate the number of students can fit at one time.
Standard is to design for 3 lunch periods. Current space is smaller than the 2012 concept because the addition of an elevator and it will need to have the serving line.
An architect will need to lay out the kitchen to ensure there is enough space for the equipment and prep.
7
DCPS | OCOO
Other Potential Projects Note: price estimates are rough orders of magnitude and should be treated as estimates only.
Interior Work Modernize cafeteria – lights, ceiling, HVAC ($250,000) Fully Modernize the auditorium – finishes, HVAC, sound/lighting/video system. ($2,250,000) Enhance the art room with a kiln room. ($50,000) Modernize bathrooms on the ground floor ($350,000) Add HVAC to the gymnasium ($225,000) Security station – improve oversight of main entrance ($50,000) Add security system to exterior doors ($125,000) Replace exterior doors ($175,000) Replace steam heat in the building ($2,000,000) Site/Exterior Work
Parking lot – re-grade, improve, expand parking lot, improve loading ($750,000) Improve dumpster location/access ($150,000) Play equipment replacement ($200,000) Partial roof replacement ($675,000) Building façade improvements (repointing) ($650,000) Contribute additional funds to the RiverSmart project (FY17) ($200,000) Landscaping ($175,000)
8
DCPS | OCOO
Next Steps Next Steps DGS will procure an architect to design the kitchen, cafeteria, and associated site work. Based on information from DGS, the architect and feedback from the school leadership and the SIT, DCPS will determine the project scope.
9
Don’t forget to sign-in (please print)
Questions/Concerns Next Meeting: Late March/Early April
Contact:
[email protected]
District of Columbia Public Schools
|
1200 First Street, NE
|
Washington, DC
20002
|
T
202.442.5885
|
F
202.442.5026
|
dcps.dc.gov