DIRECTROUTE (TUAM) LTD N17/N18 GORT TO TUAM PROJECT OFFICE CARTYMORE ATHENRY

DirectRoute (Tuam) Ltd Newsletter N17/N18 Gort to Tuam PPP Scheme Q 4

2 0 1 6

N17/N18 Project Update Welcome to our Q4 2016 Newsletter. Since our last issue, we have continued to make good progress on the Project and remain on the completion target of early 2018. There are over 700 people currently working on the Project and in excess of 2.6 million working hours have been clocked up to date. In addition to the bulk of the detailed design being complete the construction works continue to advance apace. The earthworks cut and fill operations are substantially complete at the time of writing. Pavement works up to binder course have progressed significantly in all areas. Work on the main structures along the project route also remains on schedule. All structures bar one have commenced construction at this stage with 41 substantially complete and another 8 are nearing completion. During the period some additional side roads have been opened to the public bringing to 21 the number of local roads open to traffic on their new alignments. These include the new alignments at the L-4501 Raheen Demesne, L-6142 Cloondarone Road, L–6141 Killeelaun Road, L-3103 Castlelambert Road, L-4501 Rinn Road and L–3105 Kilskeagh Road. Some of these roads will remain under temporary traffic management for a further period while certain works including final tie-in arrangements are completed. We request that all motorists be vigilant, familiarise themselves with the new layouts and obey all road signage and speed limits at these locations. We continue to update our website with relevant project information and are adding overhead photographs on a monthly basis to demonstrate the ongoing progress of the scheme. Please check the website regularly for these updates, including community engagement, and additions to the photo gallery.

Tuam Bypass at Kilmore Roundabout

M17 Ballynastaig

Tuam Bypass at Ballygaddy Road

1

THREE MONTH LOOK AHEAD The main works to be undertaken in the next three months are described in the table below.

Site Location

Work Period

Operation

Plant & Equipment

Entire Project

Ongoing

Main Earthworks—the cut & fill works across the project are almost complete. Rock blasting is compete in all areas except at Gortroe. Side road construction will continue.

Heavy construction plant, trucks, jeeps, drilling & explosive equipment

Entire Project

Ongoing

Utility Diversions—Utilities including, water, gas & electricity as well as phone & internet lines continue to be diverted as & where required ahead of major construction works.

Construction plant, jeeps

Entire Project

Ongoing

Drainage—Construction of mainline drainage networks shall continue across the project.

Construction plant, trucks, jeeps

Entire Project

Ongoing

Accommodation Works—Installation of or adjustment to private gates, entrances, boundaries or other features belonging to private individuals which are affected by the construction of the new road.

Construction plant, jeeps

Various Locations Across the Project

Ongoing

Structures—Works shall continue on the bridges. Construction of new underbridges, overbridges, culverts & underpasses across the project. Works shall include concrete works, installation of precast concrete beams, localised drainage & earthworks, surfacing works, barriers etc.

Construction plant, trucks, jeeps, cranes, concrete trucks & pumps

Entire Project

Ongoing

Landscaping—In sections where earthworks are substantially complete topsoil is being placed to allow planting and grass seeding to commence. Landscaping works themselves will proceed from October to March 2017.

Heavy construction plant, trucks, jeeps

Entire Project

Ongoing

Safety and Environmental Barriers—shall be installed in areas where earthworks are sufficiently progressed.

Heavy construction plant, trucks, jeeps

Entire Project

Ongoing

Pavement—the pavement works up to and includ- Heavy construction ing binder course level will continue in all sections plant, trucks, jeeps on mainline and side roads.

24 Hour Emergency Phone: 091-777000

Project Contact Details Email: [email protected]

Web: www.directroutegorttotuam.ie

We continue to update our website with relevant project information & are adding overhead photographs on a monthly basis to demonstrate the ongoing progress of the works. Please check the website regularly for these updates .

2

TRAFFIC MANAGEMENT Some local road diversions remain in place across the scheme. These temporary diversions or road realignments allow two way traffic to be maintained as far as possible while works to construct bridges are progressed thereby minimising disruption to road users. DirectRoute requests that all road users be vigilant and observe all signage and reduced speed limits to help ensure the safety of all. Reduced speed limits have been implemented in specific sections of road following consultation with Galway County Council, An Garda Siochana and TII (formerly NRA) and have been implemented to ensure the safety of the public road users as well as construction personnel. Examples include the M6 at the location of the Rathmorrissy interchange (reduced locally to 80 kph), and the N18 at Kiltiernan (reduced locally to 60 kph). Traffic management signage to alert public road users has been and will continue to be erected throughout the scheme where construction works interact with the existing road network. Existing traffic management arrangements associated with the road closures to facilitate tie-in works taking place at R-348 Gortroe, R347 Owenbristy, L-4502 Turloughtrassa and L-3105 Sheeaunpark Road can be seen on the DirectRoute website. Traffic is now using the permanent alignment of the N18 at Kiltiernan under restricted temporary traffic management. Traffic lights will be used on a part time basis as required for completion of the tie-in works. The use of traffic lights will be restricted to between 09.30 and 16.00 hours and the tie-in works will take place during the 3-month period of September to November 2016. There is a reduced speed limit of 60kph in force for a 1 km length on both approaches to the new Kiltiernan junction on the N18 for the duration of the completion of the works. We would ask that all motorists familiarise themselves with the new layout and observe the speed limit. On the Tuam Bypass, works continue on the existing N17 in the vicinity of the new Burke Road roundabout and Kilmore roundabout. Traffic is being diverted through the northern section of the Kilmore roundabout and again we would ask motorists to familiarise themselves with the new layout and observe both the speed limit and traffic management by flagmen at this location. There are further road closures (full, partial or under traffic management) required to complete tie–in works for newly constructed overbridges. Roads affected include the R-446 Old Dublin Road, L-8591 Raheen Kilkelly, L-8565 Carnavoodaun, L-8581 Parknacappul, L-4506 Parkatleva, L-4518 Ballymaquiff and L-85312 Coole Demesne. Further information will be made available on the project website once these closures are confirmed and within upcoming newsletters. In all cases we request that you observe local signage and/or consult the project website for more information including traffic management updates and drawings of diversion routes where applicable.

M18 Gortroe

M18 Kilternan Interchange

Rathmorrissy Interchange with M6 3

DRILLING AND BLASTING SCHEDULE TO DECEMBER 2016 DirectRoute wishes to advise of the upcoming drilling and blasting operations schedule up to the end of December 2016. The dates are provisional depending upon site conditions and project scheduling so exact dates and times are subject to change and such notices are posted locally in advance of the works taking place. We will endeavour to post updates on the website when they are received and will do so for further updates beyond the end of December 2016. Blasting is provisionally scheduled for Tuesdays and Thursdays in the area of Gortroe.

COMMUNITY DEVELOPMENT DirectRoute was delighted to be able to make a small contribution to Western Alzheimers recently. Western Alzheimers is a charitable organisation that provides a complete service of care to families affected by Alzheimers/Dementia in the Western Region of Ireland. Supporting hundreds of families with a ‘home from home’ philosophy, Western Alzheimers ensures that people living with Alzheimers are cared for in a safe, comfortable and stimulating environment. Western Alzheimers offer the families support and facilities which include Long Stay Residential Care, Respite Care, Day Care and InHome Care in Galway, Mayo and Roscommon. Western Alzheimers are funded through state support from the HSE and DSP, fund raising activities and philanthropic contributions. Contact details are available on our website.

L-R at presentation: Paraic McCarthy (Roadbridge), Kathleen Gormally (Western Alzheimers), John Power (Roadbridge), Marcella Walsh (Nurse- Maryfield Nursing Home), Shane Foley (Roadbridge), Patricia Faulkner (HCA- Maryfield Nursing Home), Nadine Monaghan (DirectRoute)

SAFETY NOTICE The N17 N18 project is now approaching two years on site and DirectRoute thanks our neighbours and the general public for their ongoing co-operation in helping to ensure that the project is constructed as safely as possible for everyone. Construction activity by its very nature exposes people to a higher level of risk than many other activities and it is important that we all continue to be vigilant. DirectRoute have detailed arrangements in place to manage the risks for both those involved in building the project and for the general public. We have completed most of the side roads over and under the new motorway in recent months which has reduced significantly the number of points where public road and site traffic have to cross each other. We plan to complete many of the remaining side roads in the coming months and would request the public to take particular care at these points and comply with any restrictions or closures imposed under local temporary traffic management arrangements including any reduced speed limits and please bear in mind the increased braking distances that may be required in approaching wintry conditions. We would also ask that you keep clear of site even when there is no work being done. Parents & Guardians are partic4

N17 N18 Newsletter Q4 2016.pdf

N17 N18 Newsletter Q4 2016.pdf. N17 N18 Newsletter Q4 2016.pdf. Open. Extract. Open with. Sign In. Main menu. Displaying N17 N18 Newsletter Q4 2016.pdf.

2MB Sizes 3 Downloads 164 Views

Recommend Documents

N17 N18 Newsletter Q2.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. N17 N18 ...

N17 N18 Newsletter Q2.pdf
Page 1 of 2. DRILLING AND BLASTING NOTICE. PROJECT CONTACT DETAILS. 24 Hour Emergency Phone: 091 777000. Email: [email protected]. Web: www.diretroutegorttotuam.ie. N17/N18 Gort to Tuam PP Scheme. Press Release. DirectRoute (Tuam) Constru

N17 N18 Newsletter Q3 2016.pdf
... during the 3-month period of Septem- ber to November 2016. There is a reduced speed limit of 60kph in force for a 1 km length on both approaches to the new.

N17 N18 Newsletter Q3 2016.pdf
D I R E C T R O U T E ( T U A M ) L T D. N 1 7 / N 1 8 G O R T T O T U A M. P R O J E C T O F F I C E. C A R T Y M O R E. A T H E N R Y DirectRoute (Tuam) Ltd ...

N17 N18 Newsletter Q3 2017.pdf
Jacobs to undertake the monitoring and ... Entire Project Pavement – wearing course application is ongoing - installation ... on the Dunmore Road in Tuam, provides a range of services for cancer patients. ... N17 N18 Newsletter Q3 2017.pdf.

N17 N18 Newsletter Q2 2017.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. N17 N18 ...

N17 N18 Newsletter Q1 2016.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. N17 N18 ...

TMAD Newsletter Q4 2014.pdf
During Q4 of 2014, TMAD supported him for monthly expenses of Rs 4,000. Expenses: Rs 4,000. Donor: TMAD Group Fund. Volunteer: Kishore Kumar Javvaji.

TMAD Newsletter Q4 2013.pdf
Sai Krishna Someneni. Education. Case 1: Support for Sravani ... Spoorthi Jyothi home 2 years ago while she was doing her intermediate. TMAD supported that home 2 years ago for ... Puspha is studying B.Tech 2nd year Computer Science, first semester,

TMAD NEWSLETTER Q4 2010.pdf
Volunteers: Dr. Hemanth, Sujatha, Lakshman, Anilkumar BVN. http://tmad.org/index.php?option=com_content&view=article&id=128:sravani-mbbs-support-.

RMGPA Newsletter Q4 2015.pdf
marketing plan, submittal requirements, qualifi- cations and experience, commodity codes and. contracts. All in all we had a great deal of information to.

N17 Sault - Plateau d'Albion.pdf
N17 Sault - Plateau d'Albion.pdf. N17 Sault - Plateau d'Albion.pdf. Open. Extract. Open with. Sign In. Main menu. Displaying N17 Sault - Plateau d'Albion.pdf.

Q4 2015 QRES_revised.pdf
8 Business Name Registration. MSMEs. Mineral Production. Prices and Inflation. 9 Purchasing Power. Labor and Employment. Revenue Collection. 10 Customs ...

PE Q4.pdf
If you were to think of Asian countries that would closely relate to the given. pictures, what ... What are your proofs to say so? 5. Can you .... Displaying PE Q4.pdf.

Halliburton Announces Q4 2012 Earnings
Jan 25, 2013 - addition, you may participate in the call by telephone at (703) 639-1306. ... A replay of the conference call will be available on Halliburton's Web ...

History Q4 Bench.pdf
The Apple logo is recognized world wide and has influenced a great part of the way we look at technology in. today's world. Through this company, we are able ...

Krishanth_UG-Q4.pdf
Page 1 of 22. UG-Q4: Compare and contrast the following methods for finding roots of. equation: the method of false position, Newton's method, and fixed point. iteration. K. Krishanth. Supervisor: Dr. T. Kirubarajan. July 28, 2014. Page 1 of 22 ...

FAR1-Q4 FY2014 FINAL.pdf
45,635,000.00. 9,496,000.00. 36,139,000.00 ./·::.c:. . .- ~~ 1~ q~ abo D~~ io· .,:·. Page 4 of 15. FAR1-Q4 FY2014 FINAL.pdf. FAR1-Q4 FY2014 FINAL.pdf. Open.

Workshop flyer Q4 1112.pdf
IT skills are required to use this simple but powerful website building tool. Improve Your Search Engine Ranking. Find out how search engine optimisation ...

VOLTAS Q4 FY17 - India Notes.pdf
... apps below to open or edit this item. VOLTAS Q4 FY17 - India Notes.pdf. VOLTAS Q4 FY17 - India Notes.pdf. Open. Extract. Open with. Sign In. Main menu.

La Lettre de la CNCEIP N18 - Formation professisonnelle continue.pdf
Actions concourant à l'acquisition d'une qualification reconnue dans la classification de la CCN* figurant sur la liste établie par la. CEFI *. ✓ Déontologie 2h ...

2017.Q4-NSoC-Calendar-Web.pdf
(and the diference between the two), and how to choose the right. cutting board for each and every job. Ready to be better? MENU. • Korean Beef Rice Bowl.