DRILLING AND BLASTING NOTICE DIRECTROUTE (TUAM) LTD N17/N18 GORT TO TUAM PROJECT OFFICE CARTYMORE ATHENRY
DirectRoute (Tuam) Ltd Newsletter N17/N18 Gort to Tuam PPP Scheme Q 2
N17/N18 Gort to Tuam PP Scheme
Press Release DirectRoute (Tuam) Construc on wish to advise local residents that Drilling and Blas ng opera ons will be taking place to construct the new N17/N18 Gort to Tuam PPP Scheme at various mes between April 2015 and June 2016.
The loca ons for this drilling and blas ng are;
Ballinphuil, Corofin
Annagh Hill Caherteemore Ballyglunin Kilskeeagh Gortroe/Rathmorrissy Greethill
N17/N18 Project Update Since the circula on of the Q1 2015 newsle er the gen‐ eral public will have seen growing evidence of site ac vity as the Contractors open up work on a number of fronts along the route of the scheme. The design and construc on works remain on programme and there have been 116,812 accident free hours worked on the Project up to the 31st March 2015. The Contractors have established their site com‐ pounds and mobilised their teams with in excess of 600 people having received Health & Safety induc ons to date. The bulk of the work carried out in Q1 2015 comprised the seasonal site clearance
Parknacappul/Roevehagh
works including demoli ons, removal of ditches, hedge‐ rows, trees and other vege‐ ta on. This is now complete and in addi on most of the 57km mainline has been
fenced. The establishment of the fencing has been aug‐ mented by surveying and preparatory work for site accesses and thus has al‐ lowed other ac vi es such as drainage works and some topsoil strip to commence. Some early plan ng of trees
2 0 1 5
and hedging at several loca‐ ons has taken place ahead of the main earthworks which will allow the early plan ng to become estab‐ lished prior to the comple‐ on of the Project. Discus‐ sions between DirectRoute and U lity providers is ongo‐ ing and some ESB diversion works have already taken place. Amongst other community ini a ves ins gated in the period safety officers from Lagan, Roadbridge and Sisk took part in a Keep Safe event in Gort a ended by 5th and 6th class pupils. The aim of the event was to help children to become more aware of personal and home safety, learn how to react to dangerous situa ons and to learn how to stay safe within the context of road safety.
Ballynastaig/Rinn
Residents in these areas will be contacted in advance of these works commencing to confirm the exact dates and mes of these works.
We would like to apologise in advance for any inconvenience that this may cause. We will endeavour to keep this disrup on to a minimum and every effort shall be made to minimise the dura on.
If you have any queries in rela on to this please contact DirectRoute (Tuam) Construc on at 091‐777000 or info@directroutegor otuam.ie
PROJECT CONTACT DETAILS 24 Hour Emergency Phone: 091 777000 Email:
[email protected] Web: www.diretroutegorttotuam.ie Roadworks on Tuam Bypass looking North from Ballygaddy Road
THREE MONTH LOOK AHEAD
TRAFFIC MANAGEMENT
The main works to be undertaken in the next three months are described in the table below. Following detailed consulta ons with An Garda Síochána and Galway County Council these works will include a contained programme for material removal which will involve drilling along with controlled blas ng in areas of rock which will commence shortly and con nue un l June 2016 with the controlled blas ng generally confined to weekdays between 10am and 4pm. No ces have been distributed to homes in the immediate vicinity of each affected loca on, published in local newspapers and displayed in public buildings along the route. The no ce including planned loca ons is incorporated into this newsle er.
Plant & Equipment
Site LocaƟon
Work Period
EnƟre Project
April Onwards
Topsoil Strip and Main Earthworks – Earthworks shall Heavy construc on commence with the stripping of topsoil along the foot‐ plant, trucks, jeeps print of the road. In areas of cut the ground below the topsoil shall be excavated to the required level. In areas of fill the ground below the topsoil shall be built up to the required level.
EnƟre Project
On‐going
U lity Diversions – U li es including water, gas and Construc on plant, electricity as well as phone and internet lines will be jeeps diverted as and where required ahead of major construc on works.
EnƟre Project
On‐going
Drainage – The construc on of pre‐earthworks drain‐ Construc on plant, age is ongoing throughout the scheme. Construc on of trucks, jeeps the majority of the main drainage works shall run con‐ currently or just following comple on of earthworks in each area of the scheme.
EnƟre Project
On‐going
Accommoda on Works – Installa on of or adjustment Construc on plant, to private gates, entrances, boundaries or other jeeps features belonging to private individuals which are affected by the construc on of the new road.
Various locaƟons (as noted in the Drilling and BlasƟng Press Release)
April 2015 – June 2016
R446 (Old Road) Clarinbridge River (Ballinillaun) Private Lands (Ballinillaun) Dunkellin River (Dunkellin) Private Lands (Glenmore, Cartymore) Private Lands (Annagh) Private Lands (Annagh) Abbert River (Annagh) Galway – Dublin Railway Line (Gortroe) R338 (Gortroe) M6 (Rathmorrissy Interchange) L31030 (Tobernavean) L2105 (Weir Road, Tuam) River Nanny (Tuam) Tuam – Claremorris Railway Line (Tuam) Private Lands (Annagh) L6143 (Mahanagh) Grange River (Mahanagh)
April – October 2015 May 2015 – June 2016 June – September 2015 May 2015 – June 2016 May – July 2015 May – July 2015 July – October 2015 May 2015 – April 2016 April 2015 – May 2016 June 2015 – April 2016 April 2014 – August 2017 June 2015 – April 2016 May – December 2015 July 2015 – January 2016 April 2015 – May 2016 May – September 2015 July 2015 – May 2016 June 2015 – April 2016
Page 2
OperaƟon
As the work on the project gathers pace the public will encounter increased levels of traffic management established for the safety of construc on workers and the general public. DirectRoute would ask that road users observe all signage and re‐ duced speed limits to help ensure the safety of all. Traffic management signage to alert public road users has been and will con nue to be erected throughout the scheme, where the construc on works interact with the exis ng road network. Temporary road diversions are being constructed adjacent to exis ng roads at the loca ons of new bridges traversing the new road. These temporary diversions will allow two‐way traffic to be maintained while works to construct bridges are pro‐ gressed thereby minimising disrup on to road users. Examples include the R446 (old N6), the R347 at Owenbristy, the R338 at Gortroe, the L31030 at Tobernavean and the L6143 at Mahanagh. Reduced speed limits are being implemented through specific sec ons of road fol‐ lowing consulta on with Galway County Council, An Garda Síochána and the Na‐ onal Roads Authority. Examples include the N63 (reduced locally to 60kph), the R348 (reduced locally to 60kph), the M6 (reduced locally at the loca on of the Rathmorrissey Interchange to 80kph, from May 2015), the R339 (reduced locally to 60kph) and the N17 north of Tuam (reduced locally to 60kph). The exis ng M6 will see the hard shoulder being cordoned off on both sides of the road at the proposed Rathmorrissey Interchange. This will facilitate construc on works while ensuring two way traffic is being maintained on the M6. Temporary vehicle safety barriers shall be installed to close the hard shoulder, ensuring the safety of road users and construc on personnel.
Drilling and Blas ng – Drilling and blas ng of rock in Construc on plant, these areas shall be carried out to allow the rock to be drilling and explosive excavated to the required level for the new road. equipment, trucks, jeeps Structures – Construc on of new under bridges, over bridges and underpasses across the project. The new structures will span exis ng rivers and roads or provide access for local landowners to their property. Works shall include piling works, concrete works, installa on of precast concrete beams, localised drainage and earthworks, surfacing works, etc.
Construc on plant, trucks, jeeps, cranes, concrete trucks and pumps, piling equip‐ ment
SAFETY NOTICE Construction activity by its nature exposes people to a higher level of risk than many other activities. DirectRoute have detailed arrangements in place to manage the risks for both those involved in building the project and for the general public. We would ask you to co-operate with us in ensuring the project is delivered as safely as possible. You can help us by:1. 2.
Taking care at the various locations where the project crosses the existing road network and complying with any restrictions imposed under local temporary traffic management arrangements including any reduced speed limits. Keep clear of site. This applies particularly to children for whom construction sites can pose a particular attraction.