PROGRESS REPORT SUBMITTED TO: Department of Electricity Development, DoED Nepal Electricity Authority, NEA NABIL Bank Limited as a LEAD Bank & Consortium Partners Hydro Consult Engineering Limited Gaurishankar Conservation Area Project, (GCAP) TPSC (India) Private Limited

Web Page: URL: www.himalurja.com

Relating to Upallo Khimti (12 MW) Hydro Power Project Progress Report No. 8 (Period: Bhadra 2074 – Kartik 2074)

Independent Power Producer, (IPP): HIMALAYA URJA BIKAS COMPANY LIMITED Subidha Nagar, Kathmandu - 32 20th November 2017 (4th Mangsir 2074)

Upallo Khimti (12 MW) Hydro Power Project

Progress Report No. 08

Project Name: 01

Upallo Khimti, 12MW Hydropower Project.

Report for:

Himalaya Urja Bikas Company Limited

Preparation Review and Authorization Date Prepared by Reviewed by 2017.08.15 Er. Rama Kant Gauro Eng. Saroj Kumar Upadhyay Er. Lav Kumar Shrestha Er. Susheel Sharma Er. Yam Lal Tharu Er. Ashish Amatya Er. Amit Singh

Approved for Issue by Hari Prasad Pandey Eng. Saroj Kumar Upadhyay Dr. Bhim Prasad Neupane

COMPANY DETAILS Himalaya Urja Bikas Company Ltd. Subhidhanagar, Tinkune, Kathmamdu-35, Nepal GPO Box: 8973 NPC868, Tel: + 977- 1-4111 853/ 1-4111 673/ 1-4111 674 Email: [email protected] Web Page: URL: www.himalurja.com

Authorized Person: Er. Saroj Kumar Upadhyay, M.Sc. in Civil Engineering (Hons.), M B A Director – Technical and Project Management Email: [email protected]

Address: Project Management Office Gokulganga Gaupalika - 1, Chuchure, Ramechhap, + 977 – 1 – 6206 742/6220 004

Head Office Subhidhanagar-32,Kathmamdu, Nepal +977-1-4111 853/ 4111 673

Upallo Khimti (12 MW) Hydro Power Project

Progress Report No. 08

Contents 1

Project Details ....................................................................................................................... 1 1.1 Description ............................................................................................................................... 1 1.1.1

Upallo Khimti Hydropower Project - 12 MW ................................................................... 1

1.1.2

Schematic Diagram of Upallo Khimti Hydro Project-12 MW ........................................... 2

1.2 The Parties ................................................................................................................................ 3 1.2.1

Employer .......................................................................................................................... 3

1.2.2

Design and Detailed Engineering Consultant ................................................................... 3

1.2.3

Bank Verification Consultant ............................................................................................ 3

1.2.4

Bank and Consortium ....................................................................................................... 3

1.2.5

Lot I Infrastructure Works ................................................................................................ 3

1.2.6

Lot II Civil Works ............................................................................................................... 4

1.2.7

Lot III Hydro Mechanical Works ....................................................................................... 4

1.2.8

Lot IV Electro Mechanical Works ..................................................................................... 4

1.2.9

Lot V 132 kV Transmission Line Works ............................................................................. 4

2

Key Dates .............................................................................................................................. 5

3

Site General Progress Executive.............................................................................................. 5 3.1 General ..................................................................................................................................... 5 3.2 Engineering Detailed Design Consultant .................................................................................. 6 3.3 Communication ........................................................................................................................ 7 3.4 Meetings................................................................................................................................... 7 3.4.1

Contract Administration and Planning Meeting (CAPM) ................................................. 7

3.4.2

Weekly Coordination Meeting (among Client and Contractor’s representative at site) . 7

3.5 Insurance .................................................................................................................................. 7 3.6 Engineering Safety.................................................................................................................... 7 4

LOT 1: Infrastructure Development........................................................................................ 8 4.1 Land Acquisition and Access Road Construction ..................................................................... 8 4.1.1

Land Acquisition ............................................................................................................... 8

4.1.2

Land Leasing ..................................................................................................................... 8

4.1.3

Access Road Construction ................................................................................................ 8

4.2 Camp House ............................................................................................................................. 8 4.2.1

Jifasa Camp: (Camp No 1) Project Management Office .................................................. 8

4.2.2

Argeli Ghari Camp: Camp No 2 ......................................................................................... 8

4.2.3

Garjyang Camp: Camp No 3 ............................................................................................. 8

4.2.4

Kharanitar Camp: Camp No: 4 .......................................................................................... 8

4.3 Construction Power.................................................................................................................. 9

i

Upallo Khimti (12 MW) Hydro Power Project

5

Progress Report No. 08

4.3.1

Study of Reliability and Power Available at Site............................................................... 9

4.3.2

Procurement of Material.................................................................................................. 9

4.3.3

Construction of Construction Power ................................................................................ 9

4.3.4

Load Approval for Construction Power ............................................................................ 9

Lot II Civil Works .................................................................................................................... 9 5.1 Summary of Progress ............................................................................................................... 9 5.2 Contractor Selection...............................................................................................................10 5.3 Construction Materials Survey ...............................................................................................10 5.4 Detailed Time Programme .....................................................................................................10 5.5 Camp of the Civil Contractor ..................................................................................................10 5.6 Key Personnel: ........................................................................................................................10 5.6.1

Manpower (Civil Contractor)..........................................................................................11

5.6.2

Equipment (Civil Contractor): .........................................................................................11

5.7 Material Stock at Site of Civil Contractor ...............................................................................12

6

5.7.1

Cement ...........................................................................................................................12

5.7.2

Rebar ..............................................................................................................................12

5.7.3

Sand washing and collection ..........................................................................................12

5.7.4

Diesel ..............................................................................................................................12

5.7.5

Stone Crusher .................................................................................................................12

Lot III Hydro Mechanical Works ............................................................................................ 12 6.1 Summary of Progress .............................................................................................................12 6.2 Contract Award ......................................................................................................................13 6.3 Camp ......................................................................................................................................13 6.4 Personnel (HM Contractor) ....................................................................................................13 6.5 Machine and materials ...........................................................................................................13 6.6 Summary of pipe fabrication and erection ............................................................................14 6.7 Summary of Bend ...................................................................................................................14 6.8 Gates and stoplog at Kharanitar Workshop ...........................................................................15 6.9 Other works ............................................................................................................................15

7

Lot IV Electro Mechanical Works .......................................................................................... 15 7.1 Summary of Progress .............................................................................................................15 7.2 Contract Award ......................................................................................................................16

8

LOT V (Ramechhap Garjyang Khimti 132 kV Transmission Line Project) ................................. 16 8.1 Introduction: ..........................................................................................................................16 8.2 Key Activities: .........................................................................................................................16 ii

Upallo Khimti (12 MW) Hydro Power Project

Progress Report No. 08

8.2.1

Office & Store Set Up: ....................................................................................................16

8.2.2

Substation works: ...........................................................................................................16

8.3 132 kV TL works:.....................................................................................................................16 9

Human Resources of HUBCL ................................................................................................. 17 9.1 Head Office, Kathmandu ........................................................................................................17 9.2 Project Management Office (PMO), Chuchure ......................................................................18 9.3 Ramechhap Garjyang Khimti 132 kV Transmission Line, Site Office, Rasnalu .......................18

10 Social Mitigation .................................................................................................................. 19 11 Financial Status.................................................................................................................... 19 APPENDIX 1: PHOTOGRAPHS ....................................................................................................... 20 APPENDIX 2: Civil Construction Schedules .................................................................................... 31 APPENDIX 3: Land Acquisition Details .......................................................................................... 34 APPENDIX 4: IPC .......................................................................................................................... 35 APPENDIX 5: Progress as per BoQ Quantity .................................................................................. 36

iii

Upallo Khimti (12 MW) Hydro Power Project

Progress Report No. 08

Acronyms AB AR BM BoQ CEC CEE DDC DoED EM DTP GCAP GWh HCE HM HUBCL HW IEE MR MSL MW NEA PA PH TPSC TR ToD UKHP-II UKHP VAT VDC

Anchor Block Access Road Bench Mark Bill of Quantities Clean Energy Consultants Pvt. Ltd Chief Executive Engineer District Development Committee Department of Electricity Development Electro Mechanical Detailed Time Programme Gaurishankar Conservation Area Project Giga Watt hour Hydro Consult Engineering Hydro Mechanical Himalaya Urja Bikas Company Limited Headworks Initial Environmental Examination Monthly Report Mean Sea Level Mega Watt Nepal Electricity Authority Penstock Alignment Power House TPSC (India) Private Limited Tailrace Time of Day Upper Khimti-II Hydroelectric Project, 7MW Upallo Khimti Hydroelectric Project, 12 MW Value Added Tax Village Development Committee

iv

Upallo Khimti Hydro Power Project, 12 MW

1

Progress Report No. 08

Project Details

1.1 Description 1.1.1 Upallo Khimti Hydropower Project - 12 MW Upallo Khimti Hydropower Project (UKHP) 12 MW is located mostly in Chuchure VDC of Ramechhap district, Janakpur Zone, Central Development Region of Nepal. The project area is located between longitudes 86o 19' 20" E to 86o 21' 40" E and latitudes 27o 39' 24" N to 27o 41' 54" N. The project components are located between elevations of 2003 m to 2303 m. UKHP is a peaking run-of-river hydropower project. Intake is located at near the confluence of Ghwang Khola and Khimti at altitude of 2300m form MSL, where water is taken from the Khimti River. The project will exploit a gross head of approx. 300 m on the Khimti river over a reach of about 3.5 km along the left bank of river to the tailrace outlet near Jifasa village of altitude of about 2000m form MSL. The surface powerhouse is located near Jifasa village and two horizontal axis Pelton turbine/generating units are to be installed, each of rated capacity 6.0 MW. At the installed capacity of 12 MW, it is estimated that the average annual energy production will be 73.61 GWh. The following table shows the basic feature of the project: Feature

UKHP HEP

Installed Capacity Gross Head Annual Sellable Energy Design Discharge Degree of Flow Exceedance

12 MW 300.0 m 73.61 GWh 5.61 m3/s 40%

The project site is linked to Jiri, Dolakha by all-weather gravelled road and distance is about 26 KM via Rasnalu Bridge. Route: 1 Kathmandu-Lamosanghu-Charikot-Jiri-Rasnalu-Khimti Site Route: 2 Kathmandu- Banepa –Khurkot –Manthali –Rasnalu -Khimti Site Among these alternatives, Route-2 is short but Route-1 shall be considered for the transportation of most of machine and materials for the construction work. The project comprises mainly Headworks, Penstock pipes, Powerhouse, Tailrace works.

1

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

1.1.2 Schematic Diagram of Upallo Khimti Hydro Project-12 MW

2

Upallo Khimti Hydro Power Project, 12 MW

1.2

Progress Report No. 08

The Parties

The project entities are listed below. 1.2.1 Employer Himalaya Urja Bikas Company Limited (HUBCL) Subhidhanagar, Tinkune-32, Kathmandu, Nepal 1.2.2 Design and Detailed Engineering Consultant Clean Energy Consultants Pvt. Ltd Anamanagar, Kathmandu, Nepal 1.2.3 Bank Verification Consultant Hydro-Consult Engineering Limited Ganga Devi Marg, Buddhanagar, Kathmandu, Nepal 1.2.4 Bank and Consortium Nabil Bank Limited (Lead Bank) Nepal Bank (Associated Bank) Everest Bank Limited (Associated Bank) ACE Development Bank Limited (Associated Bank) 1.2.5 Lot I Infrastructure Works Lot - 1 Contracts includes Infrastructure Development works such as Access Road Construction, Camp House Construction, 11kv/400 Construction Power and other related works. Himalaya Urja Bikas Company has undertaken the construction of these activities own its own engaging local contractors and youth. S.N

Description of the Work

Contractor

1

Landslide Treatment Works

Ramechhap Panch Pokhari Nirman Sewa

2

Causeway at Chake Khola

Ramechhap Panch Pokhari Nirman Sewa

3

Fencing with CGI sheet at Kharanitar

Ramechhap Panch Pokhari Nirman Sewa

4

Camp House (Jr Staff Block and Camp 2)

New Nepal Nirman Sewa

5

Camp House (Office Block and Officer’s Block)

New Nepal Nirman Sewa

6

Fencing with CGI sheet at JIFASA CAMP AREA

New Nepal Nirman Sewa

7

Raj Kulo at Gargang Khola

J & K Construction Private Limited

8

Director’s Block-1 and Outdoor Toilet -1

J & K Construction Private Limited

9

Garage -1 & Septic Tank-2

J & K Construction Private Limited

10

Garjang Crossing (Causeway)

Local Contractor

11

Camp No 2 at Argeli Gahari

New Nepal Nirman Sewa

3

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

1.2.6 Lot II Civil Works Lot II includes all the contracts related to Civil Construction Works. The bid for the work was given to the following Civil Engineering Contractors mainly A Class and experienced in Hydro Power Construction.The bid has been asked from the following Contractors: a) b) c) d)

Himal Hydro and General Construction Company Limited South Asian Infrastructure (P.) Ltd. High Himalaya Construction Company Limited B P Construction (P.) Ltd

Quality and Cost Based Evaluation, (QCBS) has been applied while evaluating the tender documents and a letter of Intent has been awarded to the highest-ranking scorer which is B.P Construction (P.) Ltd. The contract agreement has been signed with highest scorer B.P Construction (P.) Ltd (Registration Number of B P Construction (P.) Ltd is 15944/058/059 established dated 2050/05/26, License Number is 2363 A Class Contractor., VAT Registration number is 300011986 dated 2054/11/22). 1.2.7 Lot III Hydro Mechanical Works Lot III includes all the contracts related to Hydro Mechanical Works. We have already purchased Steel Plates from Steel Authority of India, (SAIL) that is confirming to IS-2062 BO/2011 E350 BO or equivalent. The bid was asked from the following contractors: a) Nepal Hydro & Electric Limited, (NHE), b) Cream Hydel (P.) Ltd and c) Machhapuchhre Metal and Machinery Works (P.) Ltd Quality and Cost Based Evaluation, (QCBS) has been applied while evaluating the tender document. The contract agreement has been signed with highest scorer Machhapuchhre Metal and Machinery Works (P.) Ltd from Industrial District Estate, Pokhara. 1.2.8 Lot IV Electro Mechanical Works Lot IV includes all the contracts related to Electro Mechanical Works Switchyard and Interconnection. And the bid has been asked from the following contractors: a) b) c) d) e) f)

Flovel Energy Private limited TPSC (India) Private Limited VOITH Hydro Pvt.Ltd Hunan Allon ward Hydro-Equiptment Co.ltd BFL Hydro Andritz Hydro Private Limited

Quality and Cost Based Evaluation, (QCBS) has been applied while evaluating the tender document. The contract agreement has been signed with highest scorer TPSC (India) Private Limited. 1.2.9 Lot V 132 kV Transmission Line Works Lot V includes all the works related to Ramechhap Garjyang Khimti 132 kV Double Circuit Transmission Line and Garjyang and New Khimti Substation which is being built by Nepal Electricity Authority. Agreement has been signed between NEA and Pinggao Group Co. Ltd. to execute above said works. Friendship Engineering Company (P.) Ltd is the sub-contractor of Pinggao Group Company Ltd for the

4

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

civil construction and erection and installation of 132 kV Double Circuit Transmission Line and 132 kV Garjyang sub-station and 132 kV Bay Extension at New Khimti sub-station.

2

Key Dates

The following are the key dates. S. N 1 2 3 4 5 6 7 8 9 10 11 12 13

3 3.1

Development and Progress Details Capacity Upgrade and received new License from DoED IEE Approved PPA signed for the project with NEA Consulting Agreement has been signed with CEC Generation License Financial closure Track opening for Access Road Construction started Track opening upto Intake of 12 MW completed Contract for “Construction Power” line awarded Lot -2 Civil Contractor mobilised on Lot - 3 Hydro Mechanical Contractor mobilised on Lot - 4 Contract is awarded RCOD

Issued Dates-12 MW June 3, 2009 August 6, 2010 January 23, 2011 June 14, 2014 May 22, 2012 December 9, 2014 March 25, 2015 24 January, 2016 December, 2015 Feb 17, 2016 Mar 21, 2016 Sep 21, 2016 July 15, 2018

Site General Progress Executive General

Total Project work carried by HUBCL has been divided into 5 Packages. LOT I: Infrastructure Development  The Land Acquisition work for getting private land is complete for Access Road and Pipe Line and for all structure in both the projects. Land leasing work and obtaining forest clearance from Government Land has been completed.  Access Road Construction is completed and upgrading of the road is still continued.  11kV/400 v Constriction Power work is completed and the line is charged. ToD meters have been installed.  Four Camp house has been acquired at Site which are used for various purposes. Lot II: Civil Works  BP Construction Pvt. Ltd has been selected as the LOT II Contractor  Till date, approximately, 30% work has been completed on 12 MW Headworks.  Similarly, 25% work has been completed on 12 MW Pipe Alignment Works.  Excavation work & Superstructure works (upto Bottom Tie Beam) completed in Powerhouse. Lot III: Hydromechanical Works  Machhapuchhre Metal & Machinery works (p) Ltd has been selected as Lot III Contractor.  Till date, approximately 65% of M/S Plate has been fabricated for both the Projects and 20 % of Penstock Pipe has been erected for both the Projects.  Major Hydromechanical components like Undersluice Stop-log, Undersluice Gate, Intake Stoplog, Intake Gate and Orifice Stop-log have been installed. Other major equipments are stored at Site Workshop.

5

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Lot IV: Electromechanical Works  TPSC (India) Pvt. Ltd has been selected as the Lot IV Contractor.  Earthing materials required for switchyard and Power houses has been received at Site  Powerhouse drawing for has been issued by Lot IV contractor and approved by our design Consultant CEC.  Earthing Works by TPSC in completed.

Lot V: Ramechhap Garjyang Khimti 132 kV double circuit Transmission Line  An agreement has been signed between NEA and Pinggao Group Co. Ltd for construction of 31 KM 132 kV double circuit transmission line and construction of 132 kV sub-station at Garjyang and Fulasi.  Till date, detail survey, check survey, tower spotting, soil investigation and tree numbering works has been completed.  Detail requirement of land for 132 kV transmission line is under preparation stage and land acquisition is completed.  Excavation works for the Tower Foundation in progress.  19 labors are engaged in Transportation of the materials to selected Towers for Foundation concreting.  3.2 Engineering Detailed Design Consultant Clean Energy Consultant (P.) Ltd has been awarded as Detailed Design Engineering Consultant. The Consultant has issued so far: 01 Woking Drawings for Alignment Excavation 02 Working Drawing for Alignment / Excavation Details (Revision), River protection works on Headworks and Anchoring / Supporting Structures 03 Working Drawings for Retaining Structures on Headworks (Revision) and Anchor Blocks 04 Working Drawings – Deliverable 04 has been received on Jun 30, 2016  General Layout Plan Profile and Alignment Data Sheet  Headworks to Desander Planning and Structural Drawings  Anchor Block Detail Drawings 05 Working Drawings- Deliverable 05 has been received  Anchor Blocks 06 Working Drawings- Deliverable 06 has been received  Anchor Blocks 07 Working Drawings- Deliverable 07 has been received  Anchor Blocks 08 Working Drawings- Deliverable 08 has been received  General Layout Plan  General Profile  Anchoring  Anchor Blocks 09 Working Drawings- Deliverable 09 has been received  Excavation Drawing for Powerhouse & Switchyard 10 Working Drawing- Deliverable 10 has been received  Power House Layout Plan & Section  Power House Frame Structure Details Power House Machine Foundation Drawing will be received soon.

6

Upallo Khimti Hydro Power Project, 12 MW

3.3

Progress Report No. 08

Communication

All communication facility has been installed already at the Project Management Office, Chuchure to have fast, prompt, timely communication. Two lines of CDMA Telephone, 22 sets of Willkie Talkie are operational at site. Web Surfer Internet facility has been installed and operational without any problem.

3.4 3.4.1

Meetings Contract Administration and Planning Meeting (CAPM)

It takes place once in every two months at head office of HUBCL, Tinkune, Kathmandu among the client – HUBCL and Contractor - B.P. Construction P. Ltd., Machhapuchre Metal and Machinery Works Pvt Ltd and TPSC (India) Pvt. Ltd. The design Consultant Clean Energy Consultants is also present in the meeting if required. S.N 1 . 2 3 4 5 6 7 8 9 10 3.4.2

CAMP CAPM 1st CAPM 2nd CAPM 3rd CAPM 4th CAPM 5th CAPM 6th CAPM 7th CAPM 8th CAPM9th

Date May 8, 2016 June 27, 2016 August 3, 2016 September 5, 2016 November 7, 2016 January 21, 2017 March 14, 2017 June 5, 2017 August 29, 2017

Weekly Coordination Meeting (among Client and Contractor’s representative at site)

It takes place on Sundays in morning at site office, Chuchure, Ramechhap, among HUBCL, B.P. Construction P. Ltd. And Machhapuchre Metal and Machinery Works Pvt Ltd. 3.5

Insurance

All the activities related to development work carried out by HUBCL under different Packages are covered by various Insurance Company of Nepal. Item Lot 1 Lot 2 Lot 3 Others Staff

3.6

Description Office Block, Staff Block, Camp 2, Director’s Block, Garage Civil Works (Property Damage, Personal Insurance, Debris clearance) Hydro Mechanical (MS plate and Fabrication) Burglary of Equipment, Electronics Insurance for equipment, Fencing, Workshop, Vehicles, Heavy Equipment and Construction Power. Accidental Insurance of Staff (Head office and Project management Office)

Insurance Company NECO Insurance Limited NECO Insurance Limited NECO Insurance Limited NECO Insurance Limited Siddhartha Insurance Limited

Engineering Safety

Safety engineering is an engineering discipline which assures that engineered systems provide acceptable levels of safety which is complemented in our Projects. Also, Himalaya Urja Bikas Company had organised Training on Construction Site Safety Engineering on 14th and 15th Shrawan 2073 which was also participated by Contractor Members.

7

Upallo Khimti Hydro Power Project, 12 MW

4

Progress Report No. 08

LOT 1: Infrastructure Development

4.1

Land Acquisition and Access Road Construction

4.1.1

Land Acquisition

The land acquisition works has been nearly completed for pipe alignment and access road of UKHP. The total area of private land has already been acquired/purchased. The remaining public land is also acquired through lease agreement with Government of Nepal. Please refer to Annex – 3 for details. 4.1.2

Land Leasing

The land leasing and clearance for the forest already completed from the cabinet decision by Government of Nepal. 4.1.3

Access Road Construction

8.5 km Access Track from Kharanitar to Headworks is ready and operational. 3 waterlogged areas and water crossing are treated locally and access is open to 12MW Headworks. There are two Khola Crossing called Chake and Garjung. Chake crossing is complete and operational. Causeway in Garjang Khola is also completed and in use. Thus, all sites of the Projects are easily accessible. 4.2

Camp House

4.2.1

Jifasa Camp: (Camp No 1) Project Management Office

This is the central camp. We have about 24 Ropani of Land for our Jifasa Camp. This camp has been designed to be in operation even after Commercial Operation Date as our main camp. Protection Work of all blocks against lighting is completed. There are 4 blocks in this camp.     4.2.2

Director Block and Guest House – It is completed and occupied with air condition facility, attached bathroom, hot / cold showers. Officers’ Block (10 rooms and kitchen) – It is complete and occupied already by our Staff. Office Block – It is ready and in use. (Director Room, Technical Room, Meeting Room, Administration Room, Account Room are in this block.) Juniors’ Block – All ten rooms are occupied. Kitchen is used as temporary store. Argeli Ghari Camp: Camp No 2

This Camp is near to 12 MW Headworks in Argelighari and is complete. This will be occupied by Headworks staff in first week of Kartik, 2073. NEA line is connected. Only compound fence work is remaining. 4.2.3

Garjyang Camp: Camp No 3

We have lease agreement with Bhalepokhari School that will be used for 30 years. It is being used as a store. 4.2.4

Kharanitar Camp: Camp No: 4

We have rented one private house. The Petrol and diesel storage will be availed here. We have store facility with office and residence facility for a duration of Project Construction Phase merely.

8

Upallo Khimti Hydro Power Project, 12 MW

4.3

Progress Report No. 08

Construction Power

4.3.1

Study of Reliability and Power Available at Site

Power availability and reliability study has already been conducted for site. Study included condition of existing 11 kV Jiri –Those feeder, available power sources at Jiri 33/11 KV substation and at Charikot 33/11 KV substation. Study also included power availability at site for construction works during off peak time and peak time (5:30 PM -9:30 PM), frequency of occurrence of fault in existing 11 kV feeder from which we are planning to tap for our energy requirements. From overall, data collected at Jiri substation, it was seen that power is available for our requirement during off peak time and reliability is also seen satisfactory. Even though, some rectification works such as bush cutting, maintain of line to ground clearance, stay installation and other minor works has to carry out for making existing 11 kV line more reliable. 4.3.2

Procurement of Material

Procurement of Major materials such as Mechanical items, Electrical items, Conductor and ABC cable and for distribution transformers has been completed and transported to site. 4.3.3

Construction of Construction Power

Construction Power works (11 KV & 0.4 KV Line) has been completed for both Projects Upallo Khimti & Upper Khimti -II. Sunita & Kabita Construction (Pvt) Ltd, Dolkha, carried out the installation works of Construction Power which has been installed along the Headrace and Penstock pipe alignment of both the projects Upallo Khimti and Upper Khimti -II Hydro Power Projects. In total six transformers has been installed. Out of six, Five Transformers has been installed of Capacity 100 KVA and one Transformer has been installed of Capacity 250 KVA. Testing of Construction power is completed and line charged on 18 July 2016. 4.3.4

Load Approval for Construction Power

NEA’s Distribution and Consumer Services Ramechhap Branch has approved 600 KVA load for the construction power. Time of Day Energy Meter programming and installation completed and transported to site. Two ToD meters have been installed by NEA concerned people, one for stone crusher of Civil Contractor and another for workshop of Hydro Mechanical Contractor.

5

Lot II Civil Works

5.1

Summary of Progress             

Toe wall, U/S apron completed (upto 15m stretch). Weir Body RCC concreting completed (upto 15m out of 25 m stretch). Base concreting in Orifice with 1m Pier completed. Undersluice and Intake Base Concreting Completed with 2nd Lift of Shear Wall. Stone masonry works from Descender Intake to Bellmouth is completed. RCC base slab & Hunch part of Block 2, 3 and 4 Desander completed. Base slab & Shear Wall 1st lift RCC concreting on connecting canal completed (i.e. Block B & C) Gravel Trap (i.e. Block D) RCC concreting completed. Gravel Trap (i.e. Block E) Rebar works in progress. AB 14, 15, 16, 17, 17A, 17B,18, 19 & 21 M15 concreting completed. E/W in excavation is being carried out from AB 20 to AB 26 and AB 26 to 30. Reinforcement placing for Anchor Blocks and Saddles in-between AB 22 to 31 on going. Construction of 3 MW site camp near to our Argelighari camp is completed.

9

Upallo Khimti Hydro Power Project, 12 MW

5.2

Progress Report No. 08

Contractor Selection

Tender had been floated on November 8, 2015. Bid received on December 10, 2015. B.P Construction Pvt. Ltd. has been awarded as a civil contractor for both of the Project on February 8, 2016. Contractor mobilised its personnel with equipment on February 17, 2016. 5.3

Construction Materials Survey

Technical team of Himalaya Urja Bikas Company Limited has visited the possible sources of construction materials especially for course and fine aggregate its quantity and quality. Basically, two sites, Mele and Olane, are selected. Both course (boulder from course aggregate) and fine aggregate are available at Mele, whereas only fine aggregate is available at Olane. Laboratory test results of all concerned materials satisfy the requirements of the relevant specifications and norms. 5.4

Detailed Time Programme

The preliminary Detailed Schedule is prepared for the civil works construction which is attached in Annex -2. The entire Civil Construction work will be completed by the end of December, 2017 followed by EM Installation, testing and commissioning by the end of June, 2018. 5.5 S.N. 1 2 3 4 5.6

Camp of the Civil Contractor Camp of Civil Contractor Camp 1 at Garjang Camp 2 near 12 MW PH Camp 3 near Argelighari Camp 4 near 7 MW PH

Purpose For site office, general store and Cement store For labours, and to store equipment and reinforcement For the accommodation of the worker of 12 MW headworks For the workers of stone crusher and 7MW Powerhouse

Key Personnel:

The Key Personnel of Civil Contractor: S.N. Staffs 1 Project Manager 2 Resident Engineer 3 Civil Engineer 4 Construction Engineer 5 Chartered Accountant 6 Accountant 7 Sub-Engineer 8 Equipment In-charge 9 Civil Sub-Overseer 10 Store Keeper 11 Social Mobilizer 12 Survey Helper 13 Supervisor 14 Mechanic 15 Pump operator 16 Excavator Operator

Nos 1 1 5 1 1 1 1 1 1 1 2 2 4 4 2 6

Location At Site At Site At Site Head Office Head Office At Site At Site At Site At Site At Site At Site At Site At Site At Site At Site At Site

Experience 15 Years 10 Years 10 Years 5 Years

10

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

5.6.1 Manpower (Civil Contractor) SN

Item

1. Front 1 (Headwork) 2. Front 2 (Pipe Alignment1) 3. Front 3 (Pipe Alignment2) 4. Front 4 (Powerhouse) Others 9. Stone crusher Total

Current (Skill/Unskilled Manpower) 20(10/10) 4(2/2) 0 25(10/15)

Remarks

Excavation ongoing

6 (2/4) 55(24/31)

5.6.2 Equipment (Civil Contractor): SN 1 2 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Item Excavator Backhoe loader Tripper Truck Tractor Crusher Machine Pump Set (4”) (7HP) Pump Set (3”) Concrete vibrator Concrete mixer Concrete pump Welding machine Batching plant Generators Bolero Monkey Jumper Total Station

17 18 19 a b c d e f g

Level Machine Rock drilling machine Lab equipment Compressive Strength Testing Machine Cube Mould Tamping Rod Sieve Apparatus set for aggregate Sieve Apparatus set for sand Heating Rod Oven

Qty. Remarks 3 1 4 4 For cement transportation 8 1 4 2 10 4 1 2 2 4 1 1 2 2 1 1 18 4 1 1 1 1

11

Upallo Khimti Hydro Power Project, 12 MW

5.7

Progress Report No. 08

Material Stock at Site of Civil Contractor

The following quantity of Materials are stocked at the Site by Civil Contractor. S.N. Item Qty. 1. Cement 870 bags 2. R-bar 123 tons 3. Diesel 1800 litres 4. Aggregate 1200 m3 5. Sand 400 m3 6. Silica 700 bags 7. Plasticizer 1160 litres 5.7.1   

5.7.2    5.7.3

Cement Maruti cement is approved by HUBCL. Different tests have been conducted and results satisfy the relevant codes and specifications. Mix design for M15, M25 and M20 has been completed. Concrete cubes are casted both for 40 down and 20 down. All tests satisfy the relevant codes and specifications. Rebar Total 115,000 kg of different sizes (10, 12, 16, 20 & 25 mm dia.) have been received. Different tests have been performed and results are positives. Rebar straightening and cutting for Anchor Blocks commenced and continued. Sand washing and collection

Sand washing is arranged in Khimti Khola near Olane which is about three kilometres south from 7 MW Powerhouse and tractors are used to transport washed sand from Khimti Khola to the yard in Kharanitar. 400 cum. of site is at site stock now. 5.7.4

Diesel

Diesel is stocked in the store of Garjang camp. Diesel is brought on required basis from the petrol station of Tamakoshi. However, the minimum stock of 700 litres is always maintained and it will be proportionately increased with volume of work to be carried out. Present stock of diesel at site is 1800 l. 5.7.5

Stone Crusher

It is in operation. 1200 cum. of Aggregate is at site stock now.

6

Lot III Hydro Mechanical Works

6.1

Summary of Progress     

Total Production of Pipe including Bends: 2514.482 m out of 3824.72 m is completed. Bends AB‐13, 14, 15, 16, 17, 17A, 17B, 18, 19, 20, 21, 22, 23,24, 25, 26, 27, 28 and 31 completed bends fabrication totals 21 numbers out of 44 numbers bends. Gate and Stop Log Frame required for concrete embedded parts have been 14 Sets Fabrication completed out of 16 required. Under Sluice Gate (Base & Vertical frame), Intake Gate (Base & Vertical frame) erection & Orifice Stoplog (Base & Vertical frame) completed in site. Erection of pipe from AB 12 to AB 21 completed.

12

Upallo Khimti Hydro Power Project, 12 MW

6.2

Progress Report No. 08

Contract Award

The Contract is awarded to Machhapuchhare Metal and Machinery Works. The contractor mobilised to site on March 21, 2017. 6.3

Camp

It is hired in Kharanitar. 6.4 SN 1 2 3 4 5 6 7 8 9 10 11 12

6.5

Personnel (HM Contractor) Personnel detail Project Engineer Site in-charge Welder Fitter/pug cutter Rolling m/c operator + Assistance Excavator operator Hydra crane operator Electrician Skilled manpower Semi-skilled manpower NDT Depart (QC) Store keeper Total manpower

Number Experience 1 8 Years 1 12 4 2 1 1 0 7 7 3 1 40

7 Years

Machine and materials

The following Machine and Materials are stocked at Hydromechanical Contractor Site: S.N. Machine and Materials Quantity 1. Escorts crane 1 2. Hydra Mobile Crane 1 3. Grinding Machine 4’, 7’ 1 4. Excavator 1 5. Generator a. 200 kVA 1 b. 40 kVA 1 c. 12 kVA 1 6. Rolling machine 1 Set 7. Overhead crane 1 Set 8. Welding machine 20 Pcs 9. Pug cutter machine 4 Pcs 10. Welding rod a. E 7018 4 mm 2 cases b. E 7018 - 3.15 mm 44 cases 11. Oxygen gas 38 cylinders 12. Paint 37 drum 13. Truck 1 14. Motorcycle 1

13

Upallo Khimti Hydro Power Project, 12 MW

6.6

Progress Report No. 08

Summary of pipe fabrication and erection

S/N 1 2 3 4 5 6 7 8 9 10 11 12

6.7

IP No AB-1 to AB-12 AB-12 to AB-15 AB-15 to AB-17 AB-17 to AB-21 AB-21 to AB-22 AB-22 to AB-28 AB-28 to AB-31 AB-31 to AB-33 AB-33 to AB-36 AB-36 to AB-41Y AB-41Y to BF-1 AB-41Y to BF-2 Total=>

Chainage Thickness (m) (mm) 0-816.82 8 816.82-1161.10 10 1161.10-1454.48 12 1454.48-1879.26 14 1879.26-1958.62 14 1958.62-2401.91 16 2401.91-2687.27 18 2687.27-3089.18 20 3089.18-3416.35 20 3416.35-3773.95 22 14 14

Diameter (mm) 1700 1700 1700 1700 1600 1600 1600 1600 1500 1500 1100 1100

Total length (m) 822.33 345.34 294.73 425.77 79.463 443.97 288.74 402.96 328.21 360.8 16.85 16.85 3826.013

Date-074/04/21 Rolling Erection completed completed (m) (m) 719.36 0 345.34 345.34 294.77 294.77 425.77 425.77 80 0 358 0 216 0 8 0 0 0 0 0 0 0 0 0 2447.24 1065.88

Summary of Bend

S/N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Total =>

Bend No Thickness (mm) 13 10 14 10 15 10 16 12 17 12 17A 14 17B 14 18 14 19 14 20 14 21 14 22 14 23 16 24 16 25 16 26 16 27 16 28 16 31 18

Diameter (mm) 1700 1700 1700 1700 1700 1700 1700 1700 1700 1700 1700 1600 1600 1600 1600 1600 1600 1600 1600

Length (m) 6.95 4.468 3.624 9.384 3.97 4.878 4.81 4.854 4.854 4.912 4.848 5.612 7.628 5.646 4.88 4.808 3.958 5.702 3.821 95.786

Weight Fabrication (Ton) 3.26929 2.15347 1.77056 5.13423 2.25416 3.18147 3.16075 3.15957 3.2146 3.21993 3.13471 3.4727 5.23883 3.96859 3.4119 3.35961 2.76466 3.98389

Date-074/04/21 Erection Remarks

59.85292

14

Upallo Khimti Hydro Power Project, 12 MW

6.8

Gates and stoplog at Kharanitar Workshop

S/n

Discription

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Embedded part installation Fabrication Erection

Date-074/04/21 Shutter installation Fabrication Erection

Undersluice gate Undersluice stoplog Intake gate Intake stoplog (3 set) Gravel flushing gate Desander inlet gate ( 2set ) Desander flushing gate ( 2set ) Intake orifice stoplog (3set) Intake trash rack(3 set) Bell mouth Manhole Anchor rings Purging duct Stiffeners at pipe crossing Y furcation Air release valve Mannul drive gate & Control box Eletric drive gear & control box

6.9

Other works 

7

Progress Report No. 08

Steel lining completed at Under sluice.

Lot IV Electro Mechanical Works

7.1

Summary of Progress 







 

Director Technical and Project Management (DTPM) attended Project Kick off meeting on 13th January 2017 in TPSCI Office Greater Noida. The meeting report has been circulated among executive teams and Project Managers Team as well. Net head and final data for Hydraulic Design parameter has been rechecked and reconfirmed by Clean Energy Consultant (P.) Ltd and has been forwarded to TPSCI as per the Kick off Meeting dated 13 January 2017. New Working Schedule has been enforced by the Civil Contractor and Hydro Mechanical Contractor. HUBCL will compile the new working schedule and will forward to TPSCI for final and consolidated harmonized work schedule. As a First Consignment from TPSCI, TPSCI has agreed to send Earth Mat design and then will supply the materials required for Earthing of Power House and Switch Yard of both the projects. HUBCL to inform about Custom Clearing Agent and will seek approval from DoED/Ministry of Energy to import electromechanical equipment with 1% custom facility. Second Consignment for the projects will be concrete embedded parts for the machine foundation of both the projects. Third Consignment from TPSCI will be EoT Crane of 25 Tonne. All the Superstructure works needs to be completed before receiving complete delivery of EM Equipment from TPSCI.

15

Upallo Khimti Hydro Power Project, 12 MW

     7.2

Progress Report No. 08

Turbine and Generator design data and selection meeting was held at head office of Client jointly with CEC and TPSCI on 3rd April 2017. Power House Excavation drawings issued to Client by TPSCI for both the Projects. Earthing design of Power houses and switchyards of both projects has been approved by Design Consultant submitted by TPSCI. First Consignment of Earthing material has reached at Site for both Projects on 14th June 2017. Earthing Works in Completed on 16th September 2017. Contract Award

The contract has been awarded to TPSC (India) Pvt. Ltd.

8

LOT V (Ramechhap Garjyang Khimti 132 kV Transmission Line Project)

8.1

Introduction:

Garjyang Ramechhap Khimti 132 kV Double Circuit Transmission line Project is being built by Nepal Electricity Authority. It consists of Construction of approximately 31 KM 132 kV TL from Garjyang Ramechhap to Fulasi VDC of Ramechhap and construction of new substation at Garjyang and bay extension works at New Khimti Substation of Fulasi VDC. NEA has signed the contract agreement with Pinggao Group Co. Ltd. Peoples’ Republic of China. On 10th May Sub Contract Agreement has been signed between Pinggao Group Company Limited & Friendship Engineering Company (P.) Ltd for the erection, installation and Civil Construction works of entire Transmission Line and Sub Station at Garjyang and Bay extension at New Khimti Sub Station. 8.2 8.2.1

Key Activities: Office & Store Set Up:

Pinggao office has been set up at Garjyang Village and at Burke village of Rasnalu of Gokulganga Gaupalika Ward No. 3. 8.2.2

Substation works:

Garjyang Substation: Following activities has been completed and ongoing for Garjyang substation. a) Soil bearing capacity and soil resistivity tests of Garjyang substation completed and provided to Pinggao Group Co. Ltd. for design process. b) Topographic survey data of Garjyang substation has been provided to Designer Pinggao Group) for design of Garjyang substation. c) Gabion Protection works of Garjyang Substation at the Left Bank of Khimti Khola has been completed. Please see photo attached below. d) Pinggao Group Co. Ltd. has prepared Plan and Layout, Single Line Diagram of Garjyang Substation is approved by NEA. e) Civil Design of Control building and Equipment foundation ongoing. f) Soil Investigation works for Garjyang Substation in progress. New Khimti Substation:

Due to unavailability of land for bay extension works, significant progress has not been made. 8.3

132 kV TL works:

132 kV TL works covers construction and installation of Double Circuit Transmission line from Garjyang substation to New Khimti substation. It is approximately 31 KM in length and consist of approximately

16

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

101 Towers. It covers Chuchure, Those, Rasnalu, Betali and Namadi VDC’s of Ramechhap district whereas Mali, Jiri and Sahare VDC’s of Dolakha District. Following activities are completed and ongoing under this scope. a) Soil bearing capacity test completed. b) Detailed Route Survey completed. c) Tree marking and numbering completed along the fixed route from Garjyang Substation to New Khimti Substation. d) Check survey of route has been completed including tower spotting works. e) Verification of Tower Spotting Works has been completed. f) Preliminary design of Different types of Towers has been completed. g) Foundation Excavation for various Towers has been started.

9

Human Resources of HUBCL

9.1

Head Office, Kathmandu

S.N. Name list Directors Head Office 1 Mr. Hari Prasad Pandey 2 Dr. Bhim Prasad Neupane Head Office Employees 1 Mr. Prakash Chandra Dulal 2 CA, Surya Prakash Pathak 3 Mr. Khagendra Pandey 4 Mr. Baburam Khanal 5 Mr. Manish Dhakal 6 Mr. Santosh Adhikari 7 Mrs. Kriti Timilsina 8 Mrs. Shobha Khatiwada 9 Mrs. Maina Kumari Adhikari 10 Mr. Tika Basnet 11 Mr. Chudamani Dahal 12 Mr. Krishna Bidari 13 Mr. Mohan Kumar Lamsal 14 Mrs. Parbati Karki Technical Staff at Head Office 1 Er. Susheel Sharma 2 Er. Yam Lal Tharu 3 Er. Ranjan Bhusal 5 CA, Narayan Poudyal 2 Mr. Rabindra Dhungana 3 Mr. Thakuri Singh Ghalan 4 Netra KC

Designation Executive Chairman Director-Head Office Manager-Administration Manager-Account & Finance Com. Secretary / Sr. Officer Asst. Manager-Account & Finance Officer-Administration Asst. Officer-Account Administration Assistant Administration Assistant Receptionist Driver Driver Guard Office Helper Office Helper Asst. Project Manager-Tech Sr. Electrical Engineer IT Engineer Financial Consultant Legal Consultant-Head office Computer Technician Security Provider

17

Upallo Khimti Hydro Power Project, 12 MW

9.2

Project Management Office (PMO), Chuchure

S.No. Name lists Director - PMO 1 Er. Saroj Kumar Upadhyay PMO Employees 1 Er. Rama Kant Gauro 2 Er. Lav Kumar Shrestha 3 Mr. Nabraj Bhandari 4 Er. Kapil Acharya 5 Er. Shyam Krishna Karki 6 Er. Ashish Amatya 7 Er. Amit Singh 8 Er. Hem Raj Guvaju 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

9.3

Progress Report No. 08

Mr. Hemanta Mani Nepal Mr. Aditya Basnet Mr. Rabin Bhattarai Mr. Lhatul Sherpa Mr. Tilak Kumari Khadka Mr. Rajesh Thakuri Mr. Pradip Kumar Khadka Mr. Naniram Basnet Mr. Prem Bahadur Khadka Mrs. Bina Khadka Mr. Khagendra Bahadur Karki Mr. Rudra Bahadur Karki Mr. Shivaram Karki Mr. Krishna Bahadur Basnet Mr. Ballav Basnet

Designation Director - Technical and Project Management (DTPM) Project Manager Resident Engineer Account Admin and Finance Manager Project Engineer Sr. Const. Engineer Headworks Engineer Electrical Engineer Site Engineer Sr. Overseer Store Keeper Sr. Asst. Sub Engineer Excavator Operator Office Assistant Driver Driver Office Assistant Senior Supervisor Admin Assistant Guard Guard Guard Guard Legal Consultant

Ramechhap Garjyang Khimti 132 kV Transmission Line, Site Office, Rasnalu

S.No. Name lists Director - PMO 1 Saroj Kumar Upadhyay 2 Dr. Bhim Prasad Neupane PMO Employees 1 Er. Binaya KC 2 Er. Yam Lal Tharu 3 Mr. Santosh Bhattarai 4 Rajesh Karki 5 Dhal Bahadur Khadka

Designation

Experience

Director Technical and Project Management (DTPM) Director-Head Office

28 Years

Project Manager Project Manager Admin Manager Surveyor Senior Supervisor

27 Years

10 Years 10 Years 1 Year 10 Years

18

Upallo Khimti Hydro Power Project, 12 MW

10

Progress Report No. 08

Social Mitigation

The company has allocated some budget in IEE for the social responsibility. Till date the company has asigned the MOU with the following institution for the intuitional support of those local institutions 11.1 11.2 11.3 11.4 11.5 11.6 11.7 11.8 11.9 11.10 11.11 11.12 11.13 11.14 11.15 11.16 11.17

11

Seti Devi Sec. School, Chuchure-8, Ramechhap Bhale Pokhari Basic School, Chuchure-1, Ramechhap Shiva Basic School, Chuchure-7, Ramechhap Mahadevshwori Basic School, Chuchure-5, Ramechhap Gupteswori Basic School, Those-7, Ramechhap Kali Devi Basic School, Chuchure-4, Ramechhap Jateswori Higher Sec. School, Chuchure-2, Ramechhap Panchpokhari Basic School, Chuchure-5, Ramechhap Seti Devi Basic School, Those -3, Ramechhap Jal Kali Basic School, Those – 1, Ramechhap Sharda Higher Sec. School, Those-5, Ramechhap Urgyen Shedrub Dargyeling Monastery, Shyama-1, Dolakha Pathibhara Bhumeshor Basic School, Shyama-1, Dolakha Shivalaya Yuba Club, Chuchure-1, Ramechhap Ramechhap District Sports Dev. Committee, Manthali,Ramechhap Health Post, Chuchure-1, Ramechhap Thokchan Choling Gumba, Chuchure-1, Ramechhap

Financial Status

The financial agreement was signed with consortium bank lead by Nabil Bank including Nepal Bank, Everest Bank and Ace Development Bank on December 9, 2014 for UKHP, 12 MW Project and on March 17, 2015 for UKHP-II, 7 MW Project. Based on the consortium agreement, details cost breakdown for individual particular is presented in table 12.1. Table 12.1: Summary of Budget Details S. N 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Particulars Pre-Operating/Development Cost Report Preparation and Field Investigation Infrastructure Development Camping Facilities Vehicle Land Purchase and Lease Office Equipment Civil Construction Metal Works Electro-mechanical Equipment Interconnection Equipment Transmission line Engineering & Management Social and Environment Cost Project Insurance during Construction Miscellaneous Interest During Construction Total with Financing

UKHP,12MW in Nrs '000 54,220.00 7,966.50 40,866.29 10,012.43 10,400.00 33,516.02 3,350.00 459,040.65 444,732.30 392,270.70 47,474.50 60,468.53 79,602.50 22,245.43 6,878.59 31,584.63 209,450.12 1,914,079.19 19

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

APPENDIX 1: PHOTOGRAPHS Progress Photographs – LOT I (Infrastructure Development)

Picture 1: Overall View of Jifasa Camp near 12 MW Powerhouse

Picture 2: Gabion works and Boulder riprap at downstream of Landslide area

20

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Picture 3: Overview of Construction Power

Picture 4: Causeway at Kharenetar

21

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Progress Photographs – Lot II (Civil Works) Upallo Khimti Hydropower Project, 12 MW:

Figure 1: 12 MW Weir

Figure 2: Intake gate of 12 MW

22

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Figure 3: Steel lining on Under sluice of 12 MW Completed and Shear wall formwork in progress

Figure 4: Gravel Trap Rebar of 12 MW in Progress.

23

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Figure 5: Track opening on 12 MW AB01 to AB-06

Figure 6: Concreting completed on 12 MW AB-21

24

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Figure 7: Backfilling works from AB-12-AB 18 Completed.

Figure 8: Excavation works from AB-26 to AB 29 in Progress

25

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Figure 9: Combine Footing of 12MW power House Completed.

Progress Photographs – LOT III (Hydro mechanical Works)

Figure 1: Welding & Rolling on Progress.

26

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Figure 2: Completed Rolling & Welding of Pipes.

Progress Photographs – LOT IV (Electro mechanical Works)

Figure 1: Placing of Earth Mat in 12 MW PH completed

27

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Progress Photographs – Lot V (Ramechhap Garjyang Khimti 132 kV Transmission Line Project)

Figure 1: Tree numbering and marking along the TL route

Figure 2: Check Survey at AP 21 – AP 22 on 05th June 2017

28

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Figure 3: Pinggao Site Office at Garjyang

Figure 45: Site Grading Work started at Garjyang Sub Station

29

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Figure 5: Gabion Works at the Left Bank of Khimti Khola Below the Garjyang Sub Station Completed

30

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

APPENDIX 2: Civil Construction Schedules Himalaya Urja Bikas Company Ltd Upallo Khimti Hydropower Project, 12 MW Upper Khimti -II Hydropower Project, 7 MW Prepared and maintained by Project Manager

SN 2.1.1 2.1.1.1 2.1.1.2 2.1.1.3 2.1.1.4 2.1.1.5 2.1.1.6 2.1.1.7 2.1.1.8

2.2.3 2.2.3.1 2.2.3.2 2.2.3.3 2.2.3.4 2.2.3.5 2.2.3.6 2.2.3.7 2.2.3.8 2.2.3.9 2.2.3.10 2.2.3.11 2.2.3.12 2.2.3.13 2.2.3.14

2.1.2 2.1.2.1 2.1.2.2 2.1.2.3 2.1.2.4 2.1.3 2.1.1 2.1.2 2.1.3 2.1.4 2.1.5 2.1.6 2.1.7 2.1.8 2.1.9 2.1.10 2.1.11 2.1.12 2.1.13 2.1.14 2.2 2.2.1 2.2.1.1 2.2.1.2 2.2.1.3 2.2.1.4 2.2.1.5 2.2.1.6 2.2.1.7 2.2.1.8 2.2.1.9 2.2.2 2.2.2.1 2.2.2.2

ACTIVITIES

Responsible

As of Jun 16, 2017 (Ashadh 02, 2074)

7MW: HEADWORKS River Diversion Sencond Stage Weir (25 m strech), Undersluice and Intake Undersluice and Intake Orifice Intake Block 1, 2, 3, 4 and Gravel Flushing Block 6, Desilting Basin, Spillway, Sand Flushing System Tailrace, Bell Mouth Left Side Protection Wall (only essential works before RCOD) Righ Side Protection Wall (only essential works before RCOD) 12 MW: POWER HOUSE, SWICHYARD AND TAILRACE Drawing for excavation Drawing for machine foundation (structural drawing) Excavation Filling and stone masonry side walls Design of Earthing Delivary of earthing materials Earthing of power house Power House Construction Delivery of EoT Installation of EoT EM Equipment Delivery Water filling in Headrace Pipe EM equipment installation Testing and Comissioning

45 BP

G1 15

BP

G2 15

BP

G3 15

2017 2018 2019 J A S O N D J F M A M J J A S O N D J F M A

2073

2074

2075

M F C B J A S B A K M P M F C B J A S B A K M P M F C 1

2

3

4

5

6

7

8

9 10 11 12 13 14 15 16 17 18 19

1

2

3

4

5

1

2

3

4

5

6

7

8

1

2

3

1

2

1 1

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

4

1

2

3

3

4

5

6

7

BP

1

2

3

4

BP

1

2

3

>

>

1

2 2

3

1

2

1

CEC

2

>

>

3

4

1

T PSC T PSC

1

BT BP

1

T PSC T PSC T PSC

1

3MW 1

T PSC

2

3

4

5

6

T PSC 42

1

2

3

4

5

6

7

8

9 10

BP

1

2

3

4

5

6

7

8

9 10

1

2

3

4

5

6

1

2

3

4

5

6

7

8

9 10 11

>

>

>

3

4

5

6

7

8

1

2

3

1

2

1

2

3

50

2

3

B

1

2

3

B

1 1

CEC

1 1

BP

7MW: POWER HOUSE, SWITCHYARD AND TAILRACE

Drawing for PH excavation Drawing for machine foundation (structural drawing) Excavation Filling and stone masonry side walls, PH fence Design of Earthing Delivary of earthing materials Earthing of power house Power House Construction Delivery of EoT Installation of EoT EM Equipment Delivery Water filling in Headrace Pipe EM equipment installation Testing and Comissioning 12 MW 12 MW: HEADWORKS River Diversion Sencond Stage Weir (10 m strech) Undersluice and Intake Orifice Intake Block A Left Side Protection Wall Righ Side Protection Wall U/P and D/N Stream Boulder Rip Rap Gravel Trap, Flushing and Spillway Desilting Basin and Sand flushing 12 MW: PENSTOCK PIPE Penstock pipe from Bell Mouth to AB 13. Penstock Pipe from AB 19 to Bifurcation

F M A M J

50

7 MW: PENSTOCK PIPE

Penstock pipe from Bell Mouth to AB 25 ( Including Garjang Penstock Pipe from AB 25 to AB 35 (Including Chake Crossing) Penstock Pipe from 35 to Bifurcation throught 39 T AB 39T to Surge Shaft

Group Worker No Excavator nos

ALL ACTIVIES OF LOT II, III, IV AND V

2

1

2

3

3

4

5

1

2

3

4

1

2

3

>

>

1

2 2

3

1

2

1

1

1

1 4

5

6

3 50 1

1

1

2

1

2

3

4

5

6

3

4

5

1

2

3

4

5

6

2

3

4

5

6

7

8

1

2

3

4

5

1

2

3

4

5

6

7

35 1

2

3

4

5

6

7

8

9 10 11 12

1

2

3

4

5

6

7

8

9 10 11 12

31

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Himalaya Urja Bikas Company Ltd Upallo Khimti Hydropower Project, 12 MW Upper Khimti -II Hydropower Project, 7 MW Prepared and maintained by Project Manager

SN

ACTIVITIES

5.1 5.1.1 5.1.2 5.1.3 5.1.4 5.1.5 5.1.6 5.1.7 5.1.8 5.1.9 5.1.10 5.1.11 5.1.12 5.1.13 5.1.14 5.1.15 5.1.16 5.1.17 5.1.18 5.1.19 5.2 5.2.1 5.2.1.1 5.2.1.2 5.2.1.3 5.2.1.4 5.2.2 5.2.2.1 5.2.2.2 5.2.3 5.2.3.1 5.2.3.2 5.2.4 5.2.4.1 5.2.4.2 5.2.4.3 5.2.4.4 5.2.5 5.2.6 5.2.7 5.3 5.3.1 5.3.2 5.3.3 5.3.4 5.3.5 5.3.6 5.3.7 5.3.8 5.3.9 5.3.10 5.3.11 5.3.12

LOT - V: 132 kV TRANSMISSION LINE(31 km, 101 towers) Key Activities realated with 132 kV Transmission Line Check Survey of Transmision Line and Tower Spotting Cadastral Survey of Transmission Line Tree Numbering , Demarcation and cutting works Design and Drawing of Tower Foundation Construction Material procurement (external) Construction Material Arrangement (local) Excavation of Tower Foundation Civil work of Tower Foundation Stub supply by Pianggao Reinforcement and Formwork Stub installation RCC Concreting and Earthing of Tower Backfilling and Compaction of Tower Foundation Tower Erection Insulators Installation ACSR Bear Conductor Stringing OPGW Communication Wire Stringing Tower Protection works TRANSMISSION LIN E CH A RGIN G Garjyang 132 kV Sub Station Control Building / Equipment Foundation Works Design and Drawing of Control Building Design and Drawing of equipment foundation Construction of Control Building Construction of Equipment Foundation Fire Wall Design and Drawing of Fire Wall Construction of Fire Wall Cable Trench Design and Drawing of Cable Trench Construction of Cable Trench Mechanical & Electrical works Mechanical erection works Electrical euipment installation Cable Laying and Termination Control Panel Installation Dry testing Other miscellaneous works/Internal Road Charging of Garjyang 132 kV Substation New Khimti Sub Station ( 132 kV Bay extension works) Civil Works Design and Drawing of Civil Works Excavation, PCC, Form work, raft and pedestal concreting Cable Trench works Mechanical & Electrical works Erection of Mechanical structures Erection of Electrical Equipments Control Panel Installation Cable Laying and Termination works Dry testing Other miscellaneous works Charging of 132 kV Bay

5

Responsible

As of Jun 16, 2017 (Ashadh 02, 2074)

FE

Group Worker No Excavator nos

ALL ACTIVIES OF LOT II, III, IV AND V F M A M J

2017 2018 2019 J A S O N D J F M A M J J A S O N D J F M A

2073

2074

2075

M F C B J A S B A K M P M F C B J A S B A K M P M F C

1

1

2

3

4

5

6

7

8

9 10 11 12 13 14 15 16 17 18 19

5

6

7

8

9 10 11 12

2

FE

1

2

FE

1

2

3

4

PI

1

2

3

4

FE

1

2

3

4

5

6

7

8

9 10 11 12

FE

1

2

3

4

5

6

7

8

9 10 11 12 13 14

FE

1

2

3

4

5

6

7

8

9 10 11 12

FE

1

2

3

4

5

6

7

8

9 10 11 12 13

1

2

3

PI FE

2

3

4

5

6

7

8

9 10 11 12 13

FE

1

1

2

3

4

5

6

7

8

9 10 11 12

FE

1

2

3

4

5

6

7

8

9 10 11 12

FE

1

2

3

4

5

6

7

8

9 10 11 12

FE

1

2

3

4

5

6

7

8

9 10

FE

1

2

3

4

5

6

7

8

9 10

FE

1

2

3

4

5

6

7

8

FE

1

2

3

4

5

6

7

8

FE

1

2

3

4

5

6

7

8

PI

PI

1

2

FE

1

2

FE

1

2

3

4

5

6

9 10

1

2

3

4

5

6

7

8

1

2

3

4

5

6

7

2

3

4

5

6

7

FE

1

2

3

4

5

6

FE

1

2

3

4

5

6

1

2

3

4

5

1

2

3

4

1

2

3

1

2

3

FE

1

PI PI

1

FE

2

3

1

2

PI

FE

1

2

3

4

5 4

5

6

FE

1

2

3

FE

1

2

FE PI FE

1

2

3

4

5

6

1

2

1 1 3

PI FE

2

4

FE

PI

1

4

FE

PI

2

3

FE

PI

1

1 1

2

3

PI

4 1

32

3

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

Himalaya Urja Bikas Company Ltd Upallo Khimti Hydropower Project, 12 MW Upper Khimti -II Hydropower Project, 7 MW Prepared and maintained by Project Manager

SN

ACTIVITIES

5.1 5.1.1 5.1.2 5.1.3 5.1.4 5.1.5 5.1.6 5.1.7 5.1.8 5.1.9 5.1.10 5.1.11 5.1.12 5.1.13 5.1.14 5.1.15 5.1.16 5.1.17 5.1.18 5.1.19 5.2 5.2.1 5.2.1.1 5.2.1.2 5.2.1.3 5.2.1.4 5.2.2 5.2.2.1 5.2.2.2 5.2.3 5.2.3.1 5.2.3.2 5.2.4 5.2.4.1 5.2.4.2 5.2.4.3 5.2.4.4 5.2.5 5.2.6 5.2.7 5.3 5.3.1 5.3.2 5.3.3 5.3.4 5.3.5 5.3.6 5.3.7 5.3.8 5.3.9 5.3.10 5.3.11 5.3.12

LOT - V: 132 kV TRANSMISSION LINE(31 km, 101 towers) Key Activities realated with 132 kV Transmission Line Check Survey of Transmision Line and Tower Spotting Cadastral Survey of Transmission Line Tree Numbering , Demarcation and cutting works Design and Drawing of Tower Foundation Construction Material procurement (external) Construction Material Arrangement (local) Excavation of Tower Foundation Civil work of Tower Foundation Stub supply by Pianggao Reinforcement and Formwork Stub installation RCC Concreting and Earthing of Tower Backfilling and Compaction of Tower Foundation Tower Erection Insulators Installation ACSR Bear Conductor Stringing OPGW Communication Wire Stringing Tower Protection works TRANSMISSION LIN E CH A RGIN G Garjyang 132 kV Sub Station Control Building / Equipment Foundation Works Design and Drawing of Control Building Design and Drawing of equipment foundation Construction of Control Building Construction of Equipment Foundation Fire Wall Design and Drawing of Fire Wall Construction of Fire Wall Cable Trench Design and Drawing of Cable Trench Construction of Cable Trench Mechanical & Electrical works Mechanical erection works Electrical euipment installation Cable Laying and Termination Control Panel Installation Dry testing Other miscellaneous works/Internal Road Charging of Garjyang 132 kV Substation New Khimti Sub Station ( 132 kV Bay extension works) Civil Works Design and Drawing of Civil Works Excavation, PCC, Form work, raft and pedestal concreting Cable Trench works Mechanical & Electrical works Erection of Mechanical structures Erection of Electrical Equipments Control Panel Installation Cable Laying and Termination works Dry testing Other miscellaneous works Charging of 132 kV Bay

5

Responsible

As of Jun 16, 2017 (Ashadh 02, 2074)

FE

Group Worker No Excavator nos

ALL ACTIVIES OF LOT II, III, IV AND V F M A M J

2017 2018 2019 J A S O N D J F M A M J J A S O N D J F M A

2073

2074

2075

M F C B J A S B A K M P M F C B J A S B A K M P M F C

1

1

2

3

4

5

6

7

8

9 10 11 12 13 14 15 16 17 18 19

5

6

7

8

9 10 11 12

2

FE

1

2

FE

1

2

3

4

PI

1

2

3

4

FE

1

2

3

4

5

6

7

8

9 10 11 12

FE

1

2

3

4

5

6

7

8

9 10 11 12 13 14

FE

1

2

3

4

5

6

7

8

9 10 11 12

FE

1

2

3

4

5

6

7

8

9 10 11 12 13

1

2

3

PI FE

2

3

4

5

6

7

8

9 10 11 12 13

FE

1

1

2

3

4

5

6

7

8

9 10 11 12

FE

1

2

3

4

5

6

7

8

9 10 11 12

FE

1

2

3

4

5

6

7

8

9 10 11 12

FE

1

2

3

4

5

6

7

8

9 10

FE

1

2

3

4

5

6

7

8

9 10

FE

1

2

3

4

5

6

7

8

FE

1

2

3

4

5

6

7

8

FE

1

2

3

4

5

6

7

8

PI

PI

1

2

FE

1

2

FE

1

2

3

4

5

6

9 10

1

2

3

4

5

6

7

8

1

2

3

4

5

6

7

2

3

4

5

6

7

FE

1

2

3

4

5

6

FE

1

2

3

4

5

6

1

2

3

4

5

1

2

3

4

1

2

3

1

2

3

FE

1

PI PI

1

FE

2

3

1

2

PI

FE

1

2

3

4

5 4

5

6

FE

1

2

3

FE

1

2

FE PI FE

1

2

3

4

5

6

1

2

1 1 3

PI FE PI

2

4

FE

PI

1

3

4

FE

PI

2

3

FE

PI

1

1 1

2

3

4 1

33

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

APPENDIX 3: Land Acquisition Details

34

Himalaya Urja Bikash Company Limited UKHP 12MW &UKHP-II 7MW Hydropower Project Land Procurement Details Particulars Total Land Purchased Total Contract With Private Owener Total Contract With Public Institution Total Land

Area Ropani 79 5 3 88

Ana

Paisa 12 1 5 3

Dam 2 2 0 0

1 2 0 3

Himalaya Urja Bikash Company Limited UKHP-12Mw Hydropower Project Land Procurement Details Both Pipe & Road Alignment (12m Width) Map No.

Old New Parcel No. Parcel No

1 Kha 1 Kha 1 Kha 1 Kha 1 Kha 1 Kha

60 59 8 7 20 6

60 59 73 75 68 77

1 Kha

22

79

1 Kha 1 Kha 1 Kha 1 Gha 1 Gha 1 Gha 1 Gha 1 Gha 1 Gha 1 Gha 1 Gha 1 Gha 1 Gha 1 Gha 1 Gha 1 Gha 1 Gha 1 Gha 1 Gha

26 41 40 107 108 7 80 81 38 37 36 84 85 42 46 90 91 92 93

70 65 62 129 131 127 122 136

120 132 134 124 46 90 91 92 93

Area

Name of Owner Gomba Sherpa Ang Nima Sherpa Dawa Sherpa Dawa Sherpa Rinji/Palku Sherpa Nira kamar chiri/Lakpa geli Sherpa Nimlaki Sherpeni Ngima Doma Sherpa Wanchhu Sherpa Mohan Kumar Khadka Shree Bahadur Khadka Sher Kumari Khadka Ohm Bahadur Basnet Chatra Bahadur Basnet Bishnu Maiya Khadka Bishnu Maiya Khadka Dambar Kumari Khadka Chandra Bahadur Basnet Chatra Bahadur Basnet Yam Bahadur Khadka Nabaraj Khadka Nabaraj Khadka Dhal Bahadur Khadka Posh Bahadur Khadka Ram Kumar Khadka Tatal Purchased Contract

Location /Structure

Ropani 1 1 1 1 1 1

Ana 5 5 4 13 7 1

Paisa 2 2 0 0 0 2

Daam 2 3 0 0 0 0

Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road

0 1 1 1 0 0 0 0 0 0 0 1 0 0 0 4 4 4 4 1

14 6 0 0 3 3 6 2 2 2 2 0 1 12 12 0 8 8 8 8

0 1 0 0 0 0 2 0 1 2 2 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 2 0 0 0 0 0 0

Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Pipe Alignment With Road Camp House Camp House Camp House Camp House

35 33 1

7 15 8

3 3 0

3 3 0

Remarks

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

APPENDIX 4: IPC

35

Comparision Sheet of Lot 2, Civil Works Date: 2074/3/27 Project 12 MW IPC Nos IPC 1 IPC 2 IPC 3 Sub Total Total Claimed Amount (12 MW+7 MW) Total Certified Amount (12 MW+7 MW) Total WithHold Amount (12 MW+7 MW) Progress in 12 MW Progress in 7 MW

Claimed Amount By BP

Certified Amount By Hydro Consult

24,413,058.71 21,030,709.17 27,288,913.54 72,732,681.42

16,265,774.60 13,182,306.49 18,872,652.45 48,320,733.54

Withhold Amount

In % Certified

8,147,284.11 7,848,402.68 8,416,261.09 24,411,947.88

66.63 62.68 69.16

104,078,101.34 64,802,238.31 39,275,863.03 21.76% 12%

Contract Amount of 12 MW with VAT

334,243,359.00

Contract Amount of 7 MW with VAT Contract amount with VAT (12MW + 7MW):

263,815,815.00 598,059,174.00

as per claimed in IPC by BP as per claimed in IPC by BP

Project 7 MW Certified Claimed Amount Amount By Hydro By BP Consult 17,670,693.86 9,792,406.24 13,674,726.06 6,689,098.53 31,345,419.92

16,481,504.77

Withhold Amount 7,878,287.62 6,985,627.53 14,863,915.15

In % Certified 55.42 48.92

Comparision Sheet of Lot 3, Hydro Mechnaical Works Date: 2074/3/27

IPC Nos IPC 1 IPC 2 IPC 3 IPC 4 Sub Total Total Claimed Amount (12 MW+7 MW) Total Certified Amount (12 MW+7 MW) Total WithHold Amount (12 MW+7 MW) Progress in 12 MW Progress in 7 MW Contract Amount of 12 MW with VAT Contract Amount of 7 MW with VAT Total Contract Amount of (12MW+ 7 MW) with VAT

Claimed Amount By 3MW with VAT 7,511,118.95 23,365,728.14 15,761,270.42 6,823,329.01 53,461,446.52

Project 12 MW Certified Amount In % By Hydro Withhold Amount Certified Consult with VAT 6,257,072.29 1,254,046.66 83.30 17,843,666.40 5,522,061.74 76.37 8,503,542.16 7,257,728.26 53.95 5,200,093.00 1,623,236.01 76.21 37,804,373.85 15,657,072.67

69,222,022.35 48,821,023.48 20,400,998.87 30% as per claimed in IPC by 3MW 11% as per claimed in IPC by 3MW 177,533,767.15 137,447,424.93 314,981,192.08

Claimed Amount By 3MW with VAT 9,035,396.59 6,725,179.24

15,760,575.83

CertifiedProject 7 MW Amount Withhold By Hydro Amount Consult with VAT 7,459,990.02 1,575,406.57 3,556,659.61 3,168,519.63

11,016,649.63

4,743,926.20

In % Certified 82.56

82.56

Upallo Khimti Hydro Power Project, 12 MW

Progress Report No. 08

APPENDIX 5: Progress as per BoQ Quantity

36

Upallo Khimti Hydropower Project, 12 MW

Progress as per BoQ Quantity for Civil Works

Himalaya Urja Bikas Company Limited Upallo Khimti Hydropower Project,12 MW Contract no.: UKHP/12 MW/Lot 2.0 Civil Works Progress as per BoQ Quantity for Civil Works Date: August 7, 2017 Workdone till date

Bill Of Quantity S.N.

Item No.

Unit

Description of Items

AA. PRELIMARIES AND GENERAL PROVISIONS Mobilization of Contractor's Office, camp, equipment, and 1 AA1 manpower as required by the Contract and as approved by the Employer De-mobilization of Contractor's office, camp, equipment, 2 AA2 manpower and reinstatement of site as required by the contract and as approved by the employer Maintenance of access road to all weather serviceable 3 AA3 condition to the satisfaction of the Employer Providing laboratory space 25 sqM, equipment, materials 4 AA4 required to make the laboratory operational for project period Providing laboratory testing services by developing a full time 5 AA5 laboratory technicians under the supervision of a Quality Control Employer Allow for Contractor's All Risk (CAR) insurance covering works, 6 AA6 equipment, materials and third party damage at site and in transit as per the contract Allow for insurance covering injury and damage to life of work 7 AA7 men and visitors at construction site Provide for safety management by developing a dedicated Safety Employer including supply of necessary equipment, first 8 AA8 aid by qualified first aider/s, and compliance of EHS requirements to the satisfaction of Employer Prepare and submit 2 hard copies and a soft copy of progress 9 AA9 photographs and record photographs as required by the employer Prepare and submit 2 hard copies and a soft copy of monthly 10 AA10 progress report in a format as approved by the employer Prepare and submit 2 hard copies and a soft copy of Project 11 AA11 completion report in a format approved by the employer Prepare and submit 2 hard copies and a soft copy of As Built 12 AA12 Drawings as approved by the Employer Prepare and submit 2 hard copies and a soft copy of Inspection 13 AA13 and maintenance Manual as approved by the Employer

Quantity

Unit Rate

Quantity

Amount (NRs.)

1

400,000.00

400,000.00

1.00

400,000.00

1

200,000.00

200,000.00

-

24

30,000.00

720,000.00

14.00

420,000.00

1

500,000.00

500,000.00

1.00

500,000.00

24

50,000.00

1,200,000.00

14.00

700,000.00

1

1,000,000.00

1,000,000.00

1.00

1,000,000.00

1

500,000.00

500,000.00

1.00

500,000.00

24

100,000.00

2,400,000.00

14.00

1,400,000.00

24

50,000.00

1,200,000.00

14.00

700,000.00

24

25,000.00

600,000.00

14.00

350,000.00

1

100,000.00

100,000.00

-

-

1

500,000.00

500,000.00

-

-

1

100,000.00

100,000.00

-

-

Sum -

Sum Month

Sum

Month

Sum Sum

Month

Month

Month

Sum Sum

Sum 9,420,000.00

Sub total of AA A. HEADWORKS AT KHIMTI KHOLA A1 Diversion Weir 1 1.0 River Diversion Work 2 1.1 Site Clearance Earthwork in Excavation and disposal of ordinary soil including 3 1.2 gravel/boulder mixed soil and soft rock (Excluding Hard Rock) by equipment all lead, all lifts Earth Work in excavation in hard rock without blasting 4 1.5 including disposal upto all lead and all lift.

Amount (NRs.)

LS LS

5,970,000.00

1.000 1.000

2,000,000.00 40.00

2,000,000.00 40.00

0.70 -

1,400,000.00 -

m3

1,484.550

140.00

207,837.00

46.71

6,539.40

m3

494.850

700.00

346,395.00

45.69

31,982.30

Earth Work in excavation for all types of soil and rock in sallow m3 water foundation including disposal upto all lead and all lift.

494.850

300.00

148,455.00

849.72

254,916.75

247.430

100.00

24,742.50

-

251.410

2,500.00

628,512.50

81.57

5

1.7

6

1.8

7

2.1

E/W in Backfilling by Ordinary Soil in 15cm thick layer and compaction with sprinkling of water, haulage distance and any m3 thickness. m3 Providing and laying Dry Stone Soling

8

2.4

Providing and laying Boulder Riprap (upto 1.2m Dia. Boulder)

m3

500.300

5,000.00

2,501,520.00

-

-

9

2.6

Providing and laying 20 cm thk.Hardstone Lining 1:3 Cement Sand Mortor

m3

249.260

2,200.00

548,372.00

-

-

10

3.1

Providing and Placing M10/40 Cement Concrete machine mixed for the foundation, footing etc, including upto all lead.

m3

125.240

9,000.00

1,127,137.50

38.59

347,314.50

11

3.2

Providing and Placing M15/40 Cement Concrete machine mixed for the foundation, footing etc, including upto all lead.

m3

464.710

10,500.00

4,879,502.25

242.33

2,544,444.00

12

3.3

m3

740.473

12,500.00

9,255,912.50

141.60

1,770,000.00

13

3.5

m3

6.160

15,500.00

95,480.00

145.29

2,251,964.00

Providing and Placing M20/40 Cement Concrete machine mixed for the wall etc, including upto all lead. Providing and Placing M25/20 Cement Concrete machine mixed for Super Structure, including upto all lead.

203,917.50

1

Upallo Khimti Hydropower Project, 12 MW

Progress as per BoQ Quantity for Civil Works

Himalaya Urja Bikas Company Limited Upallo Khimti Hydropower Project,12 MW Contract no.: UKHP/12 MW/Lot 2.0 Civil Works Progress as per BoQ Quantity for Civil Works Date: August 7, 2017 Workdone till date

Bill Of Quantity S.N.

Item No.

14

3.8

15

3.10 4.3 4.4 9.5

Unit

Description of Items Providing, fixing and removing formworks for Concreting Works. Providing, cutting, bending, binding and fixing Reinforcement for RCC Works Providing and Laying Random Rubble Masonry in 1:4 Cement and sand mortar, for all lead, all lift Providing and Laying Random Rubble Masonry in 1:6 Cement and sand mortar, for all lead, all lift Providing and Laying and fixing of Geo-Textile (Filter Fabrics), all lead,all lift

Quantity

Unit Rate

2 3 4

5 6 9 10 11 12 13 14 15

Intake/Under Sluice 1.1 Site Clearance Earthwork in Excavation and disposal of ordinary soil including 1.2 gravel/boulder mixed soil and soft rock (Excluding Hard Rock) by equipment all lead and all lifts Earth Work in excavation in hard rock without blasting 1.5 including disposal upto all lead and all lift. Earthwork in excavation for all types of soil including hard rock 1.7 in sallow water foundation including dispossal upto all lead and all lift. E/W in Backfilling by Ordinary Soil in 15cm thick layer and 1.8 compaction with sprinkling of water, haulage distance and any thickness. 2.1 Providing and laying Dry Stone Soling, all lead, all lift Providing and Laying 20 cm thk. Hard Stone Lining 1:3 Cement 2.6 mortar Providing and Placing M10/40 Cement Concrete machine 3.1 mixed for the foundation, footing etc, all lead, all lift Providing and Placing M15/40 Cement Concrete machine 3.2 mixed for the foundation, footing etc, all lead, all lift Providing and Placing M20/40 Cement Concrete machine 3.3 mixed for the wall etc, all lead, all lift Providing and Placing M25/20 Cement Concrete machine 3.5 mixed for Super Structure, all lead, all lift Providing, fixing and removing formworks for Concreting 3.8 Works. Providing, cutting, bending, binding and fixing Reinforcement 3.10 for RCC Works. Random Rubble Masonry in 1:4 Cement and Sand Mortar 4.30 including supply of all materials

2 3 4 5 6 7 8

9 10 11 12 13

Gravel Trap and Spillway 1.1 Site Clearance Earthwork in Excavation and disposal of ordinary soil including 1.2 gravel/boulder mixed soil and soft rock (Excluding Hard Rock) by equipment, all lead, all lifts Earth Work in excavation in hard rock without blasting 1.5 including disposal upto all lead and all lift. E/W in Backfilling by Ordinary Soil in 15cm thick layer and 1.8 compaction with sprinkling of water, haulage distance and any thickness. 2.1 Providing and laying Dry Stone Soling, all lead, all lift Providing and Placing M10/40 Cement Concrete machine 3.1 mixed for the foundation, footing etc, all lead, all lift Providing and Placing M15/40 Cement Concrete machine 3.2 mixed for the foundation, footing etc, all lead, all lift Providing and Placing M20/20 Cement Concrete machine 3.4 mixed for the wall, column, beam etc, all lead, all lift Providing and Placing M25/40 Cement Concrete machine 3.5 mixed for Super Structure, all lead, all lift Providing, fixing and removing formworks for Concreting 3.8 Works. Providing, cutting, bending, placing and fixing Reinforcement 3.10 for RCC works. Random Rubble Masonry in 1:4 Cement and Sand Mortar 4.30 including supply of all materials 9.10 Providing and Fixing 300 mm PVC Water Stopper Providing and fixing 25 mm thick Expansion Joint Board (Saltex 9.20 board)

Amount (NRs.)

2,200.520

750.00

1,650,387.00

543.51

407,634.75

MT

96.910

110,000.00

10,659,858.00

25.29

2,782,266.26

m3

440.000

7,500.00

3,300,018.75

-

m3

226.160

7,000.00

1,583,120.00

141.86

228.380

150.00

m2

2

34,256.25

-

38,991,546.25

993,048.00 12,994,027.46

1.000

40.00

40.00

m3

768.180

140.00

107,545.20

m3

256.060

700.00

179,242.00

m3

256.060

300.00

76,818.00

-

-

m3

128.030

100.00

12,803.00

-

-

m3

47.340

2,500.00

118,355.00

6.80

m2

21.250

2,200.00

46,750.00

-

m3

15.860

9,000.00

142,727.40

13.58

122,223.24

m3

44.130

10,500.00

463,359.75

58.91

618,565.50

m3

455.690

12,500.00

5,696,125.00

m3

2.400

15,500.00

37,200.00

56.43

874,680.50

m2

1,247.120

700.00

872,984.00

201.53

141,071.56

MT

44.980

110,000.00

4,947,800.00

12.34

1,357,129.57

LS (m )

m3

7,500.00 Sub total of A2

A3 1

Quantity

m2

Sub total of A1 A2 1

Amount (NRs.)

LS

180.68 1,751.90

-

100.83 12,701,749.35

7,227.28 1,226,331.40

17,006.80 -

-

756,195.00 5,120,430.85

1.000

40.00

40.00

139.58

5,583.12

m3

903.120

140.00

126,437.25

156.80

21,951.30

m3

225.780

700.00

158,046.56

20.11

14,079.10

m3

112.890

300.00

33,867.12

-

m3

42.750

2,500.00

106,875.00

23.26

58,147.50

m3

21.380

9,000.00

192,375.00

11.63

104,670.00

m3

11.850

10,500.00

124,383.00

-

-

m3

114.130

12,500.00

1,426,625.00

-

-

m3

15,500.00

-

46.15

715,387.00

m2

374.250

750.00

280,687.50

150.38

112,782.00

MT

12.600

110,000.00

1,386,000.00

3.73

409,750.00

m3

192.470

7,500.00

1,443,555.00

rm

30.000

600.00

18,000.00

19.77

11,860.80

m2

9.000

2,000.00

18,000.00

2.64

5,276.00

-

-

2

Upallo Khimti Hydropower Project, 12 MW

Progress as per BoQ Quantity for Civil Works

Himalaya Urja Bikas Company Limited Upallo Khimti Hydropower Project,12 MW Contract no.: UKHP/12 MW/Lot 2.0 Civil Works Progress as per BoQ Quantity for Civil Works Date: August 7, 2017 Workdone till date

Bill Of Quantity S.N.

Item No.

14

9.30

15

9.50

Unit

Description of Items Providing and fixing Joint Sealant as approved by the Project manager Providing laying and fixing of Geo-textile (Filter Fabrics) all lead,all lift

m2 m2

Quantity

Unit Rate

9.000

800.00

99.900

150.00

Sub total of A3 A4 1 2 3 4 5 6 7

Connecting Canal 1.1 Site Clearance Earthwork in Excavation and disposal of ordinary soil including 1.2 gravel/ boulder mixed soil and soft rock (Excluding Hard Rock) by equipment, all lead, all lift. Earth Work in excavation in hard rock without blasting 1.5 including disposal upto all lead and all lift. E/W in Backfilling by Ordinary Soil in 15cm thick layer and 1.8 compaction with sprinkling of water, haulage distance and any thickness. 2.1 Supplying and Placing Dry Stone Soling for all lift, all lead Providing and Placing M10/40 Cement Concrete, machine 3.1 mixed for the foundation, footing etc, for any lead, any lift

4.5 10

9.1

11

9.2

12

9.3

13

9.50

m3

95.280

140.00

13,338.86

1,428.58

200,001.62

m3

23.820

700.00

16,673.58

181.77

127,241.10

m3

11.910

100.00

1,190.97

-

m3

61.240

2,500.00

153,100.00

19.03

47,575.00

m3

30.620

9,000.00

275,580.00

9.22

82,980.00

98.450

12,500.00

1,230,609.38

15,500.00

2 3 4 5 6 7

8 9 10

11 12

-

-

-

59.40

920,700.00

m2

481.260

750.00

360,942.00

235.62

176,715.00

MT

9.840

110,000.00

1,082,936.25

9.34

1,027,197.93

m3

677.190

7,500.00

5,078,917.50

-

-

m3

150.600

4,000.00

602,400.00

-

-

Supply and fixing of 300 mm PVC Water Stopper, all lead all lift rm

30.000

600.00

18,000.00

9.61

5,764.80

m2

7.500

2,000.00

15,000.00

2.90

5,796.00

m2

7.500

800.00

6,000.00

-

-

m2

225.900

150.00

33,885.00

-

-

Supply and fixing of 25mm thick Expansion Joint Board (Saltax Board), all lead, all lift Providing and placing Joint Sealant all lead, all lift. Providing laying and fixing of Geo-textile (Filter Fabrics) all lead,all lift

Sub total of A4 A5 1

1,459,486.82 11,262.32

m3

4.3

-

281.56

Providing and Placing M25/40 Cement Concrete, machine mixed for the foundation, footing etc, for any lead, any lift.

3.10

14,985.00 5,337,076.43

-

40.00

(3.5)

9

-

40.00

m3

Providing, fixing and removing formworks for Concreting Works. Providing, cutting, bending, binding and placing Reinforcement for RCC works, all lead, all lift. Random Rubble Masonry in 1:4 Cement and Sand Mortar including supply of all materials Gabion Works including supply and placeing of gaion boxes and boulders as per the design and specification all complete for all lead, all lift

7,200.00

Amount (NRs.)

1.000

Providing and Placing M20/20 Cement Concrete, machine mixed for the foundation, footing etc, for any lead, any lift.

3.8

Quantity

LS

3.4

8

Amount (NRs.)

DESANDER AND SPILLWAY 1.1 Site Clearance Earthwork in Excavation and disposal of ordinary soil including 1.2 gravel/ boulder mixed soil and soft rock (Excluding Hard Rock) by equipment, all lead, all lift. Earth Work in excavation in hard rock without blasting 1.5 including disposal upto all lead and all lift. E/W in Backfilling by Ordinary Soil in 15cm thick layer and 1.8 compaction with sprinkling of water, haulage distance and any deapth. 2.1 Providing and Placing Dry Stone Soling Providing and Placing M10/40 Cement Concrete machine 3.1 mixed for the foundation, footing etc, for all lead, all lift Providing and Placing M15/40 Cement Concrete machine 3.2 mixed for the foundation, footing etc, for all lead, all lift Providing and Placing M20/20 Cement Concrete, machine 3.4 mixed for Super Structure, for all lead, all lift Providing and Placing M25/40 Cement Concrete, machine 3.5 mixed for Super Structure, for all lead, all lift Providing, fixing and removing formworks for Concreting 3.8 Works. Providing, cutting, bending, placing and fixing/ binding 3.10 Reinforcement for RCC works. Random Rubble Masonry in 1:4 Cement and Sand Mortar 4.3 including supply of all materials Gabion Works including supply of Gabion boxes, boulders and 4.5 filling of the boxes all complete Providing and fixing 300 mm PVC Water Stopper for all lead, all 9.1 lift

LS

8,888,613.54

2,605,233.77

1.000

40.00

40.00

1,386.41

55,456.50

m3

6,892.320

140.00

964,924.80

2,531.23

354,372.29

m3

1,723.080

700.00

1,206,156.00

925.15

647,606.40

m3

861.540

100.00

86,154.00

-

m3

359.340

2,500.00

898,357.50

223.21

558,027.50

m3

179.670

9,000.00

1,617,043.50

207.17

1,864,557.00

m3

104.810

10,500.00

1,100,473.50

49.20

516,600.00

m3

49.820

12,500.00

622,775.00

m3

1,342.520

15,500.00

20,808,984.05

348.48

5,401,440.00

m2

3,510.500

750.00

2,632,874.25

396.17

297,128.25

MT

149.710

110,000.00

16,468,585.10

41.82

4,599,760.00

m3

1,335.930

7,500.00

10,019,475.00

2,167.59

16,256,887.50

m3

195.000

4,000.00

780,000.00

-

rm

240.000

600.00

144,000.00

111.88

-

-

-

67,127.40

3

Upallo Khimti Hydropower Project, 12 MW

Progress as per BoQ Quantity for Civil Works

Himalaya Urja Bikas Company Limited Upallo Khimti Hydropower Project,12 MW Contract no.: UKHP/12 MW/Lot 2.0 Civil Works Progress as per BoQ Quantity for Civil Works Date: August 7, 2017 Workdone till date

Bill Of Quantity S.N.

Item No.

13

9.2

14

9.3

15

9.50

Unit

Description of Items Providing and fixing 25mm thick Expansion Joint Board (Saltax Board) for all lead and all lift,. Providing and fixing Joint Sealant Providing laying and fixing of Geo-textile (Filter Fabrics) all lead,all lift

Quantity

Unit Rate

72.000

2,000.00

144,000.00

13.30

m2

72.000

800.00

57,600.00

-

m2

629.700

150.00

94,455.00

-

LS

57,645,897.70 123,564,883.27

1 2 3 4 5 6 7

Anchor Block Earthwork in Excavation of ordinary soil including gravel/ 1.3 boulder mixed soil and soft rock (Excluding Hard Rock) including disposal upto all lead and all lift. Earth Work in excavation in hard rock without blasting 1.5 including disposal upto all lead and all lift. 2.1 Providing and Placing Dry Stone Soling for all lead, all lift. Providing and Placing M10/40 Cement Concrete, machine 3.1 mixed for the foundation, footing etc, for all lead, all lift. Providing and Placing M15/40 Concrete, machine mixed for 3.6 the foundation, footing etc, for all lead, all lift. Providing, fixing and removing formworks for Concreting 3.8 Works. Providing, cutting, bending, placing and binding Reinforcement 3.10 for RCC works.

1 2 3 4 5 6

Simple Support Earthwork in Excavation of ordinary soil including gravel/ 1.3 boulder mixed soil and soft rock including disposal upto 30 m lead and 2.0 m lift. 2.1 Providing and placing Dry Stone Soling Providing and Placing M10/40 Cement Concrete, machine 3.1 mixed for the foundation, footing etc, for all lead, all lift. Providing and Placing M15/40 Cement Concrete, machine 3.2 mixed for the foundation, footing etc, for all lead, all lift. Providing, fixing and removing formworks for Concreting 3.8 Works. Providing, cutting, bending, placing and binding Reinforcement 3.10 for RCC works.

1 2 3 4 5 6 7

Saddle Support Earthwork in Excavation of ordinary soil including gravel/ 1.3 boulder mixed soil and soft rock including disposal upto all lead and all lift. 2.1 Providing and Laying Dry Stone Soling Providing and Placing M10/40 Cement Concrete, machine 3.1 mixed for the foundation, footing etc, for all lead, all lift. Providing and Placing M15/40 Cement Concrete, machine 3.2 mixed for the foundation, footing etc, for all lead, all lift. Providing, fixing and removing formworks for Concreting 3.8 Works. Providing, cutting, bending, Placing and binding Reinforcement 3.1 for RCC works Providing and Laying Random Rubble Masonry in 1:4 Cement 4.3 sand mortar, for all lead, all lift.

30,645,562.84 52,824,741.73

40.00

5,546.08

221,843.37

m3

69,794.900

140.00

9,771,286.00

7,472.19

1,046,106.88

m3

3,021.810

700.00

2,115,267.00

6,396.09

4,477,260.20

m3

63,094.580

100.00

6,309,458.00

-

m3

392.390

7,500.00

2,942,925.00

2.81

m3

535.080

4,000.00

2,140,320.00

-

-

356.720

150.00

53,508.00

-

-

m2

m3

1,446.940

m3

142.770

m3

329.730

m3

164.860

m3

23,332,804.00

140.00

21,060.00

5,766,270.45

202,571.60

1,605.40

224,755.80

700.00

99,939.00

49.78

34,842.50

2,500.00

824,325.00

36.14

90,360.91

9,000.00

1,483,740.00

16.78

151,017.14

3,969.710

10,500.00

41,681,955.00

49.01

514,605.00

m2

4,293.110

750.00

3,219,832.50

137.38

103,033.50

MT

172.650

110,000.00

18,991,500.00

6.44

708,620.00

66,503,863.10

1,827,234.85

m3

402.780

140.00

56,389.20

-

m3

126.280

2,500.00

315,700.00

27.54

68,850.00

m3

63.140

9,000.00

568,260.00

14.00

125,973.00

m3

183.420

10,500.00

1,925,910.00

21.52

225,907.50

m2

335.640

750.00

251,730.00

117.36

88,017.75

9.840

110,000.00

1,082,400.00

0.96

105,186.95

MT

Sub total of B3 B4

26,600.00

40.00

Sub total of B2 B3

Amount (NRs.)

1.000

Sub total of B1 B2

Quantity

m2

Sub total of A5 Total of A B. HEADRACE ALIGNMENT B1 Alignment E/W Excavation, Backfilling and Structure 1 1.1 Site Clearance Earthwork in Excavation and disposal of ordinary soil including 2 1.2 gravel/ boulder mixed soil and soft rock (Excluding Hard Rock) by equipment, all lead, all lift. Earth Work in excavation in hard rock without blasting 3 1.5 including disposal upto all lead and all lift. E/W in Backfilling by Ordinary Soil in 15cm thick layer and 4 1.8 compaction with sprinkling of water, all lead, all lift and all deapth. Providing and Laying Random Rubble Masonry in 1:4 Cement 5 4.3 and sand mortar, for all lead, all lift Gabion Works including supply of Gabion boxes and boulders 6 4.5 and placing in position for all lead and all lift. Providng, Laying and fixing of Geo-textile (Filter Fabrics), all 7 9.5 lead, all lift.

Amount (NRs.)

4,200,389.20

-

613,935.20

m3

360.400

140.00

50,456.00

109.98

15,396.50

m3

87.600

2,500.00

219,000.00

7.90

19,740.00

m3

43.800

9,000.00

394,200.00

4.27

38,448.00

m3

73.870

10,500.00

775,635.00

2.62

27,468.00

m2

158.320

750.00

118,740.00

17.15

12,864.00

MT

4.120

110,000.00

453,200.00

0.26

28,820.00

m3

633.600

7,500.00

4,752,000.00

40.47

303,555.00

4

Upallo Khimti Hydropower Project, 12 MW

Progress as per BoQ Quantity for Civil Works

Himalaya Urja Bikas Company Limited Upallo Khimti Hydropower Project,12 MW Contract no.: UKHP/12 MW/Lot 2.0 Civil Works Progress as per BoQ Quantity for Civil Works Date: August 7, 2017 Workdone till date

Bill Of Quantity S.N.

Item No.

Unit

Description of Items

Quantity

Unit Rate

Sub total of B4 Total of B C. POWERHOUSE, TAILRACE & PROTECTION WORKS C1 Powerhouse 1 1.1 Site Clearance Earthwork in Excavation and disposal of ordinary soil including 2 1.2 gravel/ boulder mixed soil and soft rock (Excluding Hard Rock) by equipment, all lead, all lift. Earth Work in excavation in hard rock without blasting 3 1.5 including disposal upto all lead and all lift. E/W in Backfilling by Ordinary Soil in 15cm thick layer and 4 1.8 compaction with sprinkling of water, any haulage distance and any thickness. 5 2.1 Providing and Laying Dry Stone Soling, all lead, all lift. Providing and Placing M10/40 Cement Concrete, machine 6 3.1 mixed for the foundation, footing etc, for all lead, all lift. Providing and Placing M15/40 Cement Concrete, machine 7 3.2 mixed for the foundation, footing etc, for all lead, all lift. Providing and Placing M20/40 Cement Concrete machine 8 3.3 mixed for the wall etc, for all lead, all lift. Providing and Placing M20/20 Cement Concrete, machine 9 3.4 mixed for the wall, column, beam etc, for all lead, all lift. Providing and Placing M25/20 Cement Concrete, machine 10 3.5 mixed for the II Stage Concrete etc, for all lead, all lift. Providing and Laying 25mm thick 1:1 1/2:3 Cement Concrete 11 3.7 Flooring with 20mm down stone aggregrates Providing, fixing and removing formworks for Concreting 12 3.8 Works. Providing, fixing and removing formworks for Beam and 13 3.9 Column Providing, cutting, bending, placing and binding Reinforcement 14 3.1 for RCC works. Providing and laying Random Rubble Masonry in 1:4 Cement 15 4.3 and sand mortar for all lead, all lift. Providing and Laying Random Rubble Masonry in 1:6 Cement 16 4.4 and sand mortar, for all lead, all lift. Providing and laying Brick Masonry Work in 1:4 cement and 17 4.6 sand mortar for all lead, all lift. Providing and Laing 12mm thick Cement Plaster in 1:4 cement 18 5.1 and sand mortar for all lead, all lift. Providing and Laying 3mm thick neat cement punning for all 5.3 lead,all lift Providing, Fabricating and fixing in place Wood works in 19 6.1 Chaukhat of Door/Window. Providing, Fabricating and fixing 1.5" thick Saalwood Door 20 6.2 Shutter. Providing, Fabricating and fixing in place Glass Shutter for 21 6.3 Windows. Providing, Fabricating and fixing in place with False Ceiling and 22 6.4 3 mm plywood Two Coat Water Proof Cement Painting on plastered surface 23 7.1 including supply of materials, all lead, all lift. One Coat Enamel Painting over One Coat Priming including 24 7.2 supply of materials. 25

LS

Amount (NRs.)

Quantity

6,763,231.00 100,800,287.30

446,291.50 8,653,732.00

1.00

40.00

40.00

1,200.00

48,000.00

m3

8,252.130

140.00

1,155,298.20

3,000.00

420,000.00

m3

401.150

700.00

280,801.67

290.00

203,000.00

m3

802.290

100.00

80,229.05

-

m3

85.870

2,500.00

214,675.00

-

m3

55.270

9,000.00

497,394.00

-

m3

445.120

10,500.00

4,673,783.10

-

m3

313.670

12,500.00

3,920,927.13

-

m3

154.170

12,500.00

1,927,150.31

-

m3

16.450

15,500.00

255,006.00

-

m2

173.280

850.00

147,288.00

-

m2

2,916.590

750.00

2,187,443.25

-

m2

481.540

1,400.00

674,150.40

-

MT

136.950

110,000.00

15,063,978.52

-

m3

45.540

7,500.00

341,550.00

-

m3

149.880

7,000.00

1,049,151.60

-

m3

135.060

16,000.00

2,160,943.84

-

m2

877.470

400.00

350,988.80

-

m2

173.280

200.00

34,656.00

-

m3

3.320

180,000.00

596,700.00

-

m2

6.720

6,000.00

40,320.00

-

m2

76.680

5,000.00

383,400.00

-

m2

95.200

5,000.00

476,000.00

-

m2

877.470

150.00

131,620.80

-

m2

82.350

300.00

24,705.00

-

436.020

800.00

348,816.00

-

2,070.360

200.00

414,072.00

-

8.1

CGI Sheet Roofing works with supply of Materials complete.

m2

9.7

Providing and Fiing Flat iron grill in windows with red oxide paint

Kg

27

Providing, fabrication and fixing Powerhouse Entrance Gate

L.S.

1.000

100,000.00

100,000.00

-

28

L.S. Providing, fixing and removing Scaffolding Providing and fixing/ installing Sanitary, Plumbing and Electrical L.S Works, 3% of Total from Sn. 1 to 28 Providing and applying Bioengineering and Slope Protection LS Works

1.000

1,000,000.00

1,000,000.00

-

1.000

1,000,000.00

1,000,000.00

-

1.000

150,000.00

26

29 30

Sub total of C1 C2 1

Amount (NRs.)

Tailrace and Protection Works Earthwork in Excavation and disposal of ordinary soil including 1.2 gravel/ boulder mixed soil and soft rock (Excluding Hard Rock) m3 by equipment for all lead, all lift.

300.240

140.00

150,000.00

-

39,681,088.67

-

42,033.60

-

671,000.00

5

Upallo Khimti Hydropower Project, 12 MW

Progress as per BoQ Quantity for Civil Works

Himalaya Urja Bikas Company Limited Upallo Khimti Hydropower Project,12 MW Contract no.: UKHP/12 MW/Lot 2.0 Civil Works Progress as per BoQ Quantity for Civil Works Date: August 7, 2017 Workdone till date

Bill Of Quantity S.N.

Item No.

2

1.5

3

1.8

4

2.1

5

3.1

6

3.2

8

3.8

9

3.1

10

4.3

11

9.4

12

9.5

Unit

Description of Items Earth Work in excavation in hard rock without blasting including disposal upto all lead and all lift. E/W in Backfilling by Ordinary Soil in 15cm thick layer and compaction with sprinkling of water, any haulage distance and any thickness. Providing and laying Dry Stone Soling for all lead, all lift. Providing and Placing M10/40 Cement Concrete, machine mixed for the foundation, footing etc, for all lead, all lift. Providing and Placing M15/40 Cement Concrete, machine mixed for the foundation, footing etc, for all lead, all lift. Providing, fixing and removing formworks for Concreting Works. Providing, cutting, bending, placing and binding Reinforcement for RCC works. Providing and Laying Random Rubble Masonry in 1:4 Cement and sand mortar, for all lead, all lift Supply and fixing Barbed Wire Fencing Providing Laying and fixing of Geo-textile (Filter Fabrics), for all lead, all lift.

Quantity

Unit Rate

Quantity

m3

33.360

700.00

23,352.00

-

m3

33.360

100.00

3,336.00

-

m3

260.140

2,500.00

650,339.00

-

m3

130.070

9,000.00

1,170,610.20

-

m3

113.540

10,500.00

1,192,196.25

-

m2

397.250

750.00

297,937.50

-

MT

3.610

110,000.00

397,584.00

-

m3

1,669.230

8,000.00

13,353,800.00

-

406.250

700.00

284,375.00

-

1,436.180

150.00

215,426.25

-

17,630,989.80

-

m m2

Sub total of C2 C3. SUBSTATION CIVIL WORKS (PH and Interconnection) Earthwork in Excavation in ordinary soil including gravel/ 1 1.3 boulder mixed soil and soft rock including disposal upto all lead and all lift. E/W in Backfilling by Ordinary Soil in 15cm thick layer and 2 1.8 compaction with sprinkling of water, any haulage distance and any filling deapth. 3 2.1 Providing and laying Dry Stone Soling for all lead, all lift. Providing and Laying 15cmm thick stone aggregates for all lead, 4 2.2 all lift. Providing and Placing M10/40 Cement Concrete, machine 5 3.1 mixed for the foundation, footing etc, for all lead, all lift. Providing and Placing M15/40 Cement Concrete machine 6 3.2 mixed for the foundation, footing etc, for all lead, all lift Providing, fixing and removing formworks for Concreting 7 3.8 Works. Providing, cutting, bending, placing and binding Reinforcement 8 3.1 for RCC works. Providing and laying Random Rubble Masonry in 1:4 Cement 9 4.3 and sand mortar for all lead, all lift. 10 Providing and installing Chainlink Fencing 11 Providing, fabrication and installation of Entrance Gate

Amount (NRs.)

m3

1,321.680

140.00

185,035.71

-

m3

132.170

100.00

13,216.84

-

m3

65.200

2,500.00

163,000.19

-

m2

758.144

600.00

454,886.40

-

m3

28.475

9,000.00

256,275.34

-

m3

142.772

10,500.00

1,499,106.00

-

m2

554.485

750.00

415,863.75

-

MT

7.145

110,000.00

785,950.00

-

m3

96.000

7,500.00

720,000.00

-

100,000.00 100,000.00

100,000.00 100,000.00 4,693,334.23 62,005,412.69 286,370,583.26 295,790,583.26

-

LS 1.000 LS 1.000 Sub total of C3 Total of C Total A+B+C Total ( A+B+C+AA) VAT @13 % Total Amount Including VAT

334,243,359.09

Amount (NRs.)

671,000.00 62,149,473.74 68,119,473.74 76,975,005.32

6

EMPLOYER : M/S. HIMALAYA URJA BIKAS COMPANY LIMITED CONTRACTOR : M/S. MACHHAPUCHHRE METAL AND MACHINERY WORKS P. LTD PROJECT : UPALLO KHIMTI HYDROPOWER PROJECT, 12 MW SUMMARY OF WORK DONE (12MW) BOQ Item No 1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9 10 11 12

Description Part No-I Headrace, Penstock Pipe Fabrication and Erection Base Plate as specified in specification or directed by PM HDPE Sheet of thickness: 6mm Stiffeners at Pipe & Crossing Anchor Rings Bellmouth Y Furcation Air Release valve Manhole

UNIT TON Ton Ton Sq ft Ton Ton Ton Ton Ton Ton

Part No-II Gates Stoplog Trashrack and Frames Tranquilizers Purging Ducts HeadWorks Lining and Scour Protections Manual Drive Gate Operating Gear Box Electric Drive, Gear and Control Box Backup Power of HW DG, 75kVA HeadWorks Railing and Projection Works Power House Truss, Gates, Shutters Expansion Joints

Ton Ton Ton Ton Ton Ton Nos Nos Nos Ton Ton Ton

As per BOQ Qty 2,254.00 7 2,257.70 10 11 2.9 11.3 1 1.7

13.27 2.73 9.22 4.61 5.88 10.06 1 6 1 2 9.5 29.3

Previous period Fab.Qty Ere.Qty 1,018.54 110.70

This period Fab. Qty Ere.Qty 205.21 436.22

1.79

8.22 5.22 0.00

Comulative of this period Fab. Qty Ere.Qty 1,223.75 546.92

1.79

1.61 1.64 0

2.03 6.17 0.54

1.40 3.58 0

10.25 11.39 0.54

3.01 5.22 0

DATE:074/04/21 Completion % Remarks Fab % Ere % 54% 24%

PR 8-12 MW Final.pdf

Page 1 of 53. PROGRESS REPORT SUBMITTED TO: Department of Electricity Development, DoED. Nepal Electricity Authority, NEA. NABIL Bank Limited as a ...

8MB Sizes 5 Downloads 175 Views

Recommend Documents

PR 8-7 MW Final.pdf
Page 1 of 52. PROGRESS REPORT SUBMITTED TO: Department of Electricity Development, DoED. Nepal Electricity Authority, NEA. NABIL Bank Limited as a ...

MW flyer.pub
Who: Eligible Middle School Students. (Rising 6th -Rising 8th). When: June 25-28, 2012. Cost: $350 per course. Host: The College of William & Mary, Williamsburg, VA. Where: Maggie Walker Governor's School, Richmond, VA. Popular Class Offerings : The

Mw. Hirsch
hyperbolicity going beyond the Birkoff center. See our (2. 17). A. Gottlieb ... In this paper we push Hadamard's idea, which we call the graph transform [22]. How-.

. Z4 aémw?iil'li
automatic manner as they are advanced upon a conveyor after having been baked .... and, for purposes of illustration, is made up to impress the same design.

Nba 2K17 Vc Code Generator 812 - PDFKUL.COM
Code Generator Nba 2K12 Generator No Survey Code Generator Nba2k17 Codes ... Generator Codes on Apple TV, Free Game Generator Codes Nba 2K17 ...

Catalogo MW 2017.pdf
Page 5 of 132. Catalogo MW 2017.pdf. Catalogo MW 2017.pdf. Open. Extract. Open with. Sign In. Main menu. Displaying Catalogo MW 2017.pdf. Page 1 of 132.

OC & MW Lab manual.pdf
12 Impedance Measurement by Slotted Line Method. 59. 13 Measurement of Numerical Aperture of Optical Fiber 63. 14 Measurement of Losses in the FIBER 67.

Boggs Field - MW Winter Season.pdf
6:00 - 7:00 Evans BU10. RED. 7:00 - 8:00 Evans GU12. RED. 6:00 - 7:00 Kermis GU10. RED. 7:00 - 8:00 Hayes BU14. RED. *** FIELD 2 ***. 6:00 - 7:00 Girls GU10. BLUE. 7:00 - 8:00 Burga BU12. RED. FIELD 5. 6pm Winter Season. 7pm Winter Season. 8pm Winter

H¶mw ]mZhmАjnI aqey H¶mw ]mZhmАjnI aqey ...
∴PS = QR (kАЖka{XntImW§fnse Xpeyamb hi§Д). OR. ∆PAS В. PA = PS BbXn\mВ ˂A = ˂APS F¶v ]dbmw. PQRS Hcp N{Iob NXpА`pPambXn\mВ. ˂ Q = ˂ PSA ...

Subway Surfers Cheats For Android 2017 812
Huawei E5577C 4G Mobile Hotspot Review 4G LTE Mall. Being able to play Subway Surfers depends mostly on the hardware of the device you want to use it on ...

SP @MW Dual 010418.pdf
Junior Varsity "B" Team Score Junior Varisty "B" All-Around. Event Madison West Sun Prairie Place Athlete School Score. Vault 6.500 0.000 1 #N/A 0.000. Bars 6.600 0.000 2 #N/A 0.000. Beam 3.250 0.000 3 #N/A 0.000. Floor 0.000 0.000 4 #N/A 0.000. Tota

Pr Guigonis.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. Pr Guigonis.pdf.

pr-msritep.pdf
ltnvflla n qvd'oltfrnrvrruuhirioun'jrioaav uo TprurirllrirrYlornri'd16'nvuuu:rilalana1flllrnh.Jrar#ounr: uYd,u, ojnt'rrovttluhjmuriroYunvltuufiaortfi'frfifiruanr:il:yrfiunrui.

pr-msritep.pdf
ltnvflla n qvd'oltfrnrvrruuhirioun'jrioaav uo TprurirllrirrYlornri'd16'nvuuu:rilalana1flllrnh.Jrar#ounr: uYd,u ... pr-msritep.pdf. pr-msritep.pdf. Open. Extract. Open with.

PR Intern.pdf
Proficiency with AP Style for news releases. ○ Proficiency with graphic design software such as Microsoft. Publisher, Adobe Photoshop and/or Adobe InDesign. ○ Familiarity with social media platforms. ○ Personal computer proficiency with Office

PR&Branding_Scale.pdf
vs. Page 4 of 51. PR&Branding_Scale.pdf. PR&Branding_Scale.pdf. Open. Extract. Open with. Sign In. Main menu. Displaying PR&Branding_Scale.pdf.

HIT-MW Dataset for Offline Chinese Handwritten Text ...
HIT-MW Dataset for Offline Chinese Handwritten Text Recognition. Tonghua Su. Tianwen ... large number of training and testing data, resulting in high model fit and reliable ..... project report", Pattern Recognition, Vol. 5, No. 3, pp. 213-228 ...

*AMENDED-PR-R405ChallengerDeep.pdf
May 2, 2012 - The resolution's adoption shows strong bi-partisan support of its intent. "You can't explore ... approval of Resolution 405 is a smart business decision for Guam and the region. The ... *AMENDED-PR-R405ChallengerDeep.pdf.

PR ADVANCE grant.pdf
Sep 7, 2015 - to host websites for the networks in each of the various research areas. A social science component of the. grant will study the efficacy of this ...

Holiday Buyer's Guide PR - Libsyn
limiting their “Best of the Best” awards to only the top five sex products tested in 2008. Download .... without anywhere near the same degree of desensitization.