Republic of the Philippines REGIONAL DEVELOPMENT COUNCIL Eastern Visayas (Region VIII)

REGIONAL PROJECT MONITORING COMMITTEE VIII 1st Quarter CY 2015 Field Monitoring Report Monitoring Visit for Projects in the Provinces of Leyte and Southern Leyte 24 March 2015

The Regional Project Monitoring Committee (RPMC) VIII conducted field monitoring visits on March 24, 2015 on the following projects: 1. Rehabilitation/Repair/Improvement of Mahaplag River Flood Control 2. Japan Fund for Poverty Reduction (JFPR) for Emergency Assistance and Early Recovery for Poor Municipalities Affected by Typhoon Yolanda 3. Restoration along Daang Maharlika, Kahupian Road Slip Section, K1008+150-K1008+360 Boundary Mahaplag-Liloan, Sogod. Other Improvement Works (Slope Protection, Drainage, Sidewalks) 4. Construction/Rehabilitation of Flood Control Structures, Subang Daku Flood Control (Phase II) (Along Boundary Southern Leyte-Maasin-Macrohon Road) Sogod, Southern Leyte. The monitoring team that visited Leyte were Engr. Laurence Alonzo of Department of the Interior and Local Government (DILG) VIII, Mr. Marlon Dumagsa and Mr. Archie Niño Labordo of the National Economic and Development Authority (NEDA) VIII, and Ms. Nicole Orendain of the Asian Development Bank (ADB). Mr. Ramon C. Hidalgo of NEDA VIII Project Monitoring Evaluation Division (PMED) conducted the monitoring of Items 3 & 4 abovementioned on March 23, 2015 in Sogod, Southern Leyte. The other members of the monitoring team from DBM VIII and DILG VIII were not available on the said date.

The following information and observations were made during the field monitoring visit: 1. Rehabilitation/Repair/Improvement of Mahaplag River Flood Control, Kinawit, Poblacion, Mahaplag, Leyte Contract Cost Physical Accomplishment Slippage

PhP 17,120,000.00 65.00% (-) 4.00%

1

The river flood control (RFC) project is 50% completed. The contractor has constructed/posted 100m line Pelote extending the north end of the existing RFC. The construction is still ongoing with equipment and workers at the project site. The following photos were taken on site: Photo Documentation Rehabilitation/Repair/Improvement of Mahaplag River Flood Control Kinawit, Poblacion, Mahaplag, Leyte March 24, 2015

On-going construction at project site.

On-going construction of 100m Pelote stand along Mahaplag River connecting the existing RFC.

Equipment at project site

2

2. Japan Fund for Poverty Reduction (JFPR) for Emergency Assistance and Early Recovery for Poor Municipalities Affected by Typhoon Yolanda – (for Validation) Contract Cost

PhP 1,604,840.00 All projects validated are still under Physical Accomplishment procurement process. Slippage 0% The following photos were taken on site: PHOTO DOCUMENTATION

Area Validation of JFPR-Grant Funded Projects Mahaplag, Leyte March 24, 2015

Rehabilitation of 0.150 km. Farm to Market Road, San Juan, Mahaplag, Leyte

Improvement of the 49m River Flood Control Protection, Brgy. Mabunga, Mahaplag, Leyte

3

Improvement of the 12m Path Walk at Mabuhay, Mahaplag, Leyte

Rehabilitation of 0.85 km Farm to Market Road, Brgy. Mahayahay, Mahaplag, Leyte

Rehabilitation of 0.84 km Farm to Market Road, Brgy. San Isidro, Mahaplag, Leyte

4

Repair of 0.122 km PCCP Farm to Market Road, Brgy. Palaṅogan, Mahaplag, leyte

Repair of Palaṅogan Spillway Road Going to Malipoon, Mahaplag, Leyte

3. Restoration Works along Daang Maharlika, Kahupian Road Slip Section,

K1008+150-K1008+360 Boundary Mahaplag-Liloan, Sogod. Other Improvement Works (Slope Protection, Drainage, Sidewalks) Contract Cost Physical Accomplishment Slippage

PhP 43,295,140.59 40.00% 0% (on schedule)

The restoration works was 40% completed and on schedule. The project is ongoing. Though the road is under construction, it is open and limited only to light vehicles for the safety of the workers and commuters. The contractor should provide additional input to fast track the completion of the project to be able to open the road to all types of vehicle. The following photos were taken on site:

5

Photo Documentation

DPWH Standard Project Billboard

Boundary Mahaplag-Liloan-Sogod

Restoration of Road Slip along Kahupian Section K1008+1504+K1008+360 Boundary Mahaplag-Liloan Section (Daang Maharlika)

4. Construction/Rehabilitation of Flood Control Structures, Subang Daku Flood Control along Boundary Southern Leyte-Maasin-Macrohon Road, Sogod Contract Cost Physical Accomplishment Slippage

PhP 43,284,061.26 91.00% 6.00%

The project is substantially completed with 91% accomplishment. The contractor received an approved 30 Calendar Days time suspension and a 30 Calendar Days time extension due to Variation Order. The project is under correction of defects and deficiencies. The following photos were taken on site:

6

Photo Documentation

Flood Control Structure

Subang Daku Bridge 20T

Flood Control Structures of Subang Daku along boundary So. Leyte-Maasin-Macrohon Road, Sogod

7

PMC Form O-2 FINANCIAL AND PHYSICAL STATUS OF CAPITAL INVESTMENT PROGRAMS/PROJECTS As of March 31, 2015 a) Project Name/Title/Scope b) Implementing Agency c) Location

SCHEDULE

FINANCIAL (P'000)

a) Start Date

a) Prog. Amount

b) Completion Date

b) Contract Amount

c) Rev.Comp. Date

c) Revised (C.A.)

PHYSICAL (%) Target

Actual

Performance

Slippage

Employment Generated (Man-Days)

Remarks

RECONSTRUCTION/REHABILITATION OF SCHOOL BUILDINGS CY 2014 Reconstruction/Rehabilitation Program (RRP) - YOLANDA BATCH 1 Reconstruction/Rehabilitation of 73 classrooms in 28 school sites

a) 7/8/2014

a)

26,733,672.22

b) DepEd Regional Office VIII

b)

b)

26,374,305.72

c)

Leyte 1st District

c)

c)

a)

Reconstruction/Rehabilitation of 206 classrooms in 98 school sites

a) 7/8/2014

a)

82,006,447.71

b) DepEd Regional Office VIII

b)

b)

80,823,160.70

c)

a)

c)

c)

Reconstruction/Rehabilitation of 123 a) classrooms in 37 school sites

Leyte 2nd District

a)

a)

38,143,270.28

b) DepEd Regional Office VIII

b)

b)

37,664,241.89

c)

Leyte 4th District

c)

c)

a)

Reconstruction/Rehabilitation of 70 classrooms in 14 school sites

a)

a)

20,899,890.00

b) DepEd Regional Office VIII

b)

b)

20,837,099.86

c)

Ormoc City

c)

c)

a)

Reconstruction/Rehabilitation of 102 classrooms in 30 school sites

a)

a)

b) DepEd Regional Office VIII

b)

b)

c)

Samar 2nd District

c)

c)

a)

Reconstruction/Rehabilitation of 35 classrooms in 11 school sites

a)

a)

b) DepEd Regional Office VIII

b)

b)

c)

c)

c)

Catbalogan City

73

71

2

206

206

0

123

95

-28

58 classrooms repaired/ completed; 11 classrooms with ongoing repair; 1 for delisting; 1 with intervention and 1 in procurement process 154 classrooms repaired/ 100 completed; 28 classrooms with ongoing repair; 24 CL are for delisting (with intervention) 24 classrooms repaired/ 77.24 completed; 71 classrooms with ongoing repair; 24 CL for mobilization; 2 sites for delisting

97.26

Substantially completed

31,447.50

Procurement process ongoing

10,275.00

Procurement process ongoing

Page 1 of 9

a) Project Name/Title/Scope

SCHEDULE

FINANCIAL (P'000)

a) Start Date

a) Prog. Amount

b) Completion Date

b) Contract Amount

c) Rev.Comp. Date

c) Revised (C.A.)

a)

a)

b) DepEd Regional Office VIII

b)

b)

c)

Leyte 1st District

c)

c)

a)

Reconstruction/Rehabilitation of 197 classrooms in 29 school sites

a)

a)

b) DepEd Regional Office VIII

b)

b)

c)

b) Implementing Agency c) Location

PHYSICAL (%) Target

Actual

Performance

Slippage

Employment Generated (Man-Days)

Remarks

CY 2013 Quick Response Fund (QRF) a)

Reconstruction/Rehabilitation of 121 classrooms in 18 school sites

Leyte 2nd District

c)

c)

Reconstruction/Rehabilitation of a) ____classrooms in ___ school sites

a)

a)

b) DepEd Regional Office VIII

b)

b)

c)

Leyte 4th District

c)

c)

Reconstruction/Rehabilitation of 7 classrooms a) a) in 2 school sites

a)

b) DepEd Regional Office VIII

b)

b)

c)

Leyte 5h District

39,611.30

60,428.28

2,514.00

c)

c)

a)

a)

78,697,878.09

b) DepEd Regional Office VIII

b)

b)

76,299,698.95

c)

c)

c)

Reconstruction/Rehabilitation of 46 a) classrooms in 7 school sites

a)

a)

9,239,180.00

b) DepEd Regional Office VIII

b)

b)

8,986,273.63

c)

c)

c)

Tacloban City

Procurement process ongoing

Procurement process ongoing

Reconstruction/Rehabilitation of 336 a) classrooms in 34 school sites Ormoc City

Procurement process ongoing

Page 2 of 9

Procurement process ongoing

90

95

5

106

100

100

0

100

Procurement process ongoing

46 CL completed

a) Project Name/Title/Scope b) Implementing Agency c) Location

SCHEDULE

FINANCIAL (P'000)

a) Start Date

a) Prog. Amount

b) Completion Date

b) Contract Amount

c) Rev.Comp. Date

c) Revised (C.A.)

Reconstruction/Rehabilitation of 68 a) classrooms in 18 school sites

a)

26,330,040.00

b) DepEd Region VIII / E. Samar Division

b)

26,265,833.33

PHYSICAL (%) Target

Actual

Slippage

Performance

68

68

89

4

4

100

2

2

100

Sta. Cruz PS, General MacArthur

2

2

100

Canciledes ES, Hernani

1

1

100

3

3

100

2

2

100

7

7

100

2

2

65

5

5

70

3

3

75

Bucao PS, Guiuan North

1

1

100

Culasi ES, Guiuan South

4

4

95

2

2

95

2

2

95

5

5

60

3

3

50

c) Location:

a)

Prog. Amount

b)

Contract Amount

Aguinaldo ES, General MacArthur Alang-alang PS, General MacArthur

Hernani CS, Hernani

a)

a)

2,355,210.00

2,421,540.00

b)

b)

2,355,210.00

2,416,822.03

Karapdapan ES, Salcedo Bobon NHS, Mercedes Pagbabangnan ES, Guiuan South Cagusu-an ES, Guiuan South Canawayon ES, Guiuan South

Manicani NHS, Guiuan

a)

a)

a)

3,777,840.00

3,777,840.00

3,358,080.00

b)

b)

b)

3,765,430.69

3,775,213.10

3,355,544.00

Sulu-an IS, Guiuan South Casuguran ES, Guiuan South Inapulangan ES,Guiuan South Homonhon NHS - Sulangan Annex, Guiuan Gen. MacArthur CS, Gen. MacArthur

a)

3,358,080.00

b)

3,339,736.37

a)

1,259,280.00 b)

1,257,827.58

3

3

100

6,022,170.00

6,014,892.11

17

17

100

PAGCOR Funds

Page 3 of 9

Employment Generated (Man-Days)

Remarks

a) Project Name/Title/Scope b) Implementing Agency c) Location

Tacloban City

a) b) c) a) b) c) a) b) c) a) b) c)

PAGCOR DepEd Regional Office VIII Marasbaras NHS, Tacloban City a) PAGCOR DepEd Regional Office VIII Cabalawan ES, Tacloban City a) PAGCOR DepEd Regional Office VIII Anibong ES, Tacloban City a) PAGCOR DepEd Regional Office VIII Salvacion ES, Tacloban City

Ormoc City

SCHEDULE

FINANCIAL (P'000)

a) Start Date

a) Prog. Amount

b) Completion Date

b) Contract Amount

c) Rev.Comp. Date

c) Revised (C.A.)

a) b) c) a) b) c) a) b) c) a) b) c)

a) b) c) a) b) c) a) b) c) a) b) c)

3-Oct-14

3-Oct-14

3-Oct-14

3-Oct-14

a) PAGCOR b) DepEd Regional Office VIII

b)

b)

c)

c)

c)

Macabug ES, Ormoc City

a) 17-Sep-14

a) 17-Sep-14

a)

a) a) PAGCOR b) DepEd Regional Office VIII

b)

b)

a)

c)

Hugpa ES, Ormoc City a) a) PAGCOR b) DepEd Regional Office VIII

c)

c)

a) 17-Sep-14 b)

b)

c)

R.M. Tan ES, Ormoc City a) a) PAGCOR b) DepEd Regional Office VIII

c)

c)

a) 17-Sep-14 b)

a) b)

c)

c)

c)

Mas-in ES, Ormoc City

a)

Target

Actual

Performance

Slippage

Employment Generated (Man-Days)

Remarks

4,118,000.00 4,066,481.40

100

100

0

100

3 CL completed

4,098,000.00 4,047,674.05

100

100

0

100

3 CL completed

3,087,000.00 3,080,919.37

100

100

0

100

2 CL completed

10,322,000.00 10,300,358.48

100

100

0

100

7 CL completed

5,901,000.00 5,885,154.48 4,421,000.00 4,397,771.64 4,421,000.00 4,408,954.71 8,519,000.00 8,515,607.89

a) PAGCOR b) DepEd Regional Office VIII

b)

b)

c)

c)

c)

a) a) PAGCOR

a) 17-Sep-14

a)

5,291,000.00

b) DepEd Regional Office VIII

b)

b)

5,905,199.75

Dolores ES, Ormoc City

a) 17-Sep-14

a)

PHYSICAL (%)

3,077,000.00 3,074,343.38

Page 4 of 9

45

85

40

188.9

project ongoing

50

90

40

180.0

project ongoing

50

80

30

160.0

project ongoing

52

88

36

169.2

project ongoing

70

95

25

135.7

for punchlisting

50

80

30

160.0

project ongoing

a) Project Name/Title/Scope b) Implementing Agency c) Location c)

Nueva Vista ES, Ormoc City

SCHEDULE

FINANCIAL (P'000)

a) Start Date

a) Prog. Amount

b) Completion Date

b) Contract Amount

c) Rev.Comp. Date

c) Revised (C.A.)

c)

c)

a) a) PAGCOR

a) 17-Sep-14

a)

3,077,000.00

b) DepEd Regional Office VIII

b)

b)

3,074,455.45

c)

c)

c)

a) a) PAGCOR

a) 17-Sep-14

a)

5,422,000.00

b) DepEd Regional Office VIII

b)

b)

5,413,360.58

c)

Milagro ES, Ormoc City

c)

c)

a) PAGCOR

a) 17-Sep-14

a)

3,077,000.00

b) DepEd Regional Office VIII

b)

b)

3,051,361.81

c)

c)

c)

a) a) PAGCOR

a) 17-Sep-14

a)

3,087,000.00

b) DepEd Regional Office VIII

b)

b)

3,063,716.60

c)

c)

c)

Bagong ES, Ormoc City

Luna ES, Ormoc City

Sto Niño ES, Ormoc City

a) a) PAGCOR

a) 17-Sep-14

a)

7,238,000.00

b) DepEd Regional Office VIII

b)

b)

7,207,997.74

c)

c)

c)

Concepcion ES, Ormoc City

a) a) PAGCOR

a) 17-Sep-14

a)

3,087,000.00

b) DepEd Regional Office VIII

b)

b)

3,080,615.80

c)

c)

c)

a) PAGCOR

a) 17-Sep-14

a)

5,452,000.00

b) DepEd Regional Office VIII

b)

b)

5,421,283.09

c)

Cagbuhangin ES, Ormoc City

c)

c)

a) PAGCOR

a) 17-Sep-14

a)

7,508,000.00

b) DepEd Regional Office VIII

b)

b)

7,496,189.57

c)

c)

c)

a)

a)

Matica-a ES, Ormoc City

Sabang Bao ES, Ormoc City

Eastern Samar a) PAGCOR

7,662,000.00

Page 5 of 9

PHYSICAL (%) Slippage

Performance

Employment Generated (Man-Days)

Remarks

Target

Actual

45

85

40

188.9

project ongoing

60

90

30

150.0

project ongoing

45

80

35

177.8

project ongoing

45

95

50

211.1

project ongoing

65

85

20

130.8

project ongoing

55

85

30

154.5

project ongoing

80

95

15

118.8

3 projects ongoing; 1 project completed

48

80

32

166.7

project ongoing

a) Project Name/Title/Scope b) Implementing Agency c) Location

SCHEDULE

FINANCIAL (P'000)

a) Start Date

a) Prog. Amount

b) Completion Date

b) Contract Amount

c) Rev.Comp. Date

c) Revised (C.A.)

b) DepEd Regional Office VIII

b)

b)

c)

c)

c)

7,658,675.48

Campoyong ES, Guiuan East a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

7,652,000.00

b)

b)

7,646,439.48

c)

c)

c)

Guiuan East CS, Guiuan East a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

7,652,000.00

b)

b)

7,627,360.41

c)

c)

c)

Cogon ES, Guiuan North a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

8,372,000.00

b)

b)

8,360,285.24

c)

c)

c)

Nagaja ES, Hernani a) PAGCOR b) DepEd Regional Office VIII

a)

a)

11,848,000.00

b)

b)

11,841,771.45

c)

c)

c)

Homonhon NHS, Guiuan

a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

13,044,000.00

b)

b)

13,017,451.65

c)

Salcedo VHS, Salcedo a) a) PAGCOR b) DepEd Regional Office VIII

c)

c)

a)

a)

b)

b)

c)

c)

c)

a)

a)

b)

b)

So. Samar NCHS, Balangiga a) a) PAGCOR b) DepEd Regional Office VIII c)

c)

c)

a)

a)

10,746,000.00

b)

b)

10,734,846.31

c)

c)

c)

a)

a)

b)

b)

a) a) PAGCOR b) DepEd Regional Office VIII

Performance

Slippage

Page 6 of 9

Employment Generated (Man-Days)

Remarks

Target

Actual

5

5

0

100.0

project ongoing

5

5

0

100.0

project ongoing

5

5

0

100.0

project ongoing

6

6

0

100.0

project ongoing

8

8

0

100.0

for punchlisting

9

9

0

100.0

project ongoing

0

Maliwaliw ES, Salcedo II a) PAGCOR b) DepEd Regional Office VIII Tugop ES, General MacArthur

PHYSICAL (%)

#DIV/0!

project ongoing

3

3

0

100.0

project ongoing

4

4

0

100.0

project ongoing

3

3

0

100.0

project ongoing

SCHEDULE

a) Project Name/Title/Scope b) Implementing Agency c) Location c)

Cagdaja PS, Quinapondan

FINANCIAL (P'000)

a) Start Date

a) Prog. Amount

b) Completion Date

b) Contract Amount

c) Rev.Comp. Date c)

c) Revised (C.A.) c)

a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

San Vicente PS, Quinapondan a) a) PAGCOR b) DepEd Regional Office VIII

c)

c)

a)

a)

b)

b)

c)

c)

c)

Cambilla PS, Quinapondan

a) PAGCOR b) Q DepEdp Regional Office ( VIII g c) Quinapondan a) a) PAGCOR

a)

a)

b)

b)

c)

c)

a)

a)

b) DepEd Regional Office VIII

b)

b)

c)

c)

c)

Buenavista ES, Guiuan East

),

a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

Bobon ES, Mercedes a) a) PAGCOR b) DepEd Regional Office VIII

c)

c)

a)

a)

b)

b)

c)

c)

c)

Bungtod ES, Guiuan East a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

c)

c)

a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

c)

c)

Manicani NHS, Guiuan

San Jose ES, Guiuan East a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

c)

c)

a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

c)

c)

Gahoy ES, Guiuan East

Sapao ES, Guiuan East

8,352,000.00 8,347,630.53

8,674,000.00 8,648,573.35

13,172,000.00 13,161,291.14

10,534,000.00 10,518,856.50

11,808,000.00 11,805,985.60

Page 7 of 9

PHYSICAL (%) Performance

Slippage

Employment Generated (Man-Days)

Remarks

Target

Actual

3

3

0

100.0

project ongoing

4

4

0

100.0

project ongoing

2

2

0

100.0

3 projects ongoing; 1 project completed

6

6

0

100.0

project ongoing

3

3

0

100.0

project ongoing

3

3

0

100.0

project ongoing

4

4

0

100.0

for punchlisting

5

5

0

100.0

project ongoing

3

3

0

100.0

project ongoing

5

5

0

100.0

project ongoing

a) Project Name/Title/Scope b) Implementing Agency c) Location

a) PAGCOR b) DepEd Regional Office VIII c)

Trinidad ES, Guiuan North

SCHEDULE

FINANCIAL (P'000)

a) Start Date

a) Prog. Amount

b) Completion Date

b) Contract Amount

c) Rev.Comp. Date a)

c) Revised (C.A.) a) 12,160,000.00 b) 12,152,266.11

b) c) a)

a)

b)

b)

c)

c)

c)

San Pedro ES, Guiuan North a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

Alingarog, ES, Guiuan North a) a) PAGCOR b) DepEd Regional Office VIII

c)

c)

a)

a)

b)

b)

c)

c)

c)

a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c) Timala ES, Guiuan North a) a) PAGCOR b) DepEd Regional Office VIII

c)

c)

a)

a)

b)

b)

c)

c)

c)

Cagdara-o PS, Guiuan North

a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

Victory ES, Guiuan East a) a) PAGCOR b) DepEd Regional Office VIII

c)

c)

a)

a)

b)

b)

c)

c)

c)

Bitaugan ES, Guiuan South a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

c)

c)

a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

c)

c)

a)

a)

Mayana ES, Guiuan North

Banahao ES, Guiuan North a) a) PAGCOR

11,528,000.00 11,519,991.39

10,798,000.00 10,783,141.47

10,466,000.00 10,450,698.32

10,038,000.00 10,018,931.68

10,796,000.00

Page 8 of 9

Performance

Slippage

Employment Generated (Man-Days)

Remarks

Target

Actual

3

3

0

100.0

project ongoing

6

6

0

100.0

project ongoing

3

3

0

100.0

project ongoing

4

4

0

100.0

project ongoing

4

4

0

100.0

3 projects ongoing; 1 project completed

3

3

0

100.0

project ongoing

5

5

0

100.0

project ongoing

4

4

0

100.0

project ongoing

3

3

0

100.0

for punchlisting

4

4

0

100.0

project ongoing

c)

a) a) PAGCOR b) DepEd Regional Office VIII

Tubabao ES, Guiuan North

PHYSICAL (%)

a) Project Name/Title/Scope

SCHEDULE

FINANCIAL (P'000)

a) Start Date

a) Prog. Amount

b) Completion Date

b) Contract Amount

b) DepEd Regional Office VIII

c) Rev.Comp. Date b)

c)

c)

c) Revised (C.A.) b) 10,777,032.05 c)

a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

c)

c)

b) Implementing Agency c) Location

Habag ES, Guiuan South

Guinmaayohan ES, Balangiga a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

c)

c)

a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

c)

c)

Guinob-an ES, Lawaan

Parena ES, Giporlos a) a) PAGCOR b) DepEd Regional Office VIII

a)

a)

b)

b)

c)

c)

c)

Paya ES, Giporlos

8,704,000.00 8,696,334.19

11,538,000.00 11,523,693.26

Source: DepEd Region VIII

Page 9 of 9

PHYSICAL (%) Performance

Slippage

Employment Generated (Man-Days)

Remarks

Target

Actual

3

3

0

100.0

project ongoing

3

3

0

100.0

project ongoing

3

3

0

100.0

project ongoing

6

6

0

100.0

project ongoing

3

3

0

100.0

project ongoing

PMC Form O-2 FINANCIAL AND PHYSICAL STATUS OF CAPITAL INVESTMENT PROGRAMS/PROJECTS As of March 31, 2015 a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

a) Prog. Amount

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Revised (C.A.)

FINANCIAL (P'000)

AA Issued To Date

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

Target

Actual

Slippage

Performance

Employment Generated (Man-Days)

Remarks

Secondary National Roads Development Project (SNRDP) MCC-Assisted SNRD Project Contract Package 1: Road Rehabilitation, a) Sta. 827+144 to 843+500 (16.36 km), Buray a) Junction to Brgy. Tenani, Paranas, Samar b) MCC-PMO-DPWH c) Paranas, Samar 2nd District MCC-Assisted SNRDProject Contract Package 2: Road Rehabilitation, Sta. 843+500 to 907+281.82 Brgy. Tenani a) to Sulat/San Julian Mun. Boundary (63.78 km), Eastern Samar b) MCC-PMO-DPWH c) Paranas, Samar/Sulat, E. Samar MCC-Assisted SNRDProject Contract Package 3: Road Rehabilitation, Sta. 907+907 to Sta. 972+488 San a) Julian/Sulat Mun. Boundary to Balangkayan/Llorente Mun. Boundary (64.56 km), Eastern Samar b) MCC-PMO-DPWH c) Eastern Samar MCC-Assisted SNRDProject Contract Package 4: Road Rehabilitation,Sta. 979+488 to Sta. a) 1049+996 Balangkayan/Llorente Mun. Boundary to Guiuan (79.51 km), Eastern Samar b) MCC-PMO-DPWH c) Eastern Samar

05 Oct 2012 (550 Calendar Days)

a)

802,070.56 +US$140,182.68

08 Apr 2014 06 Jun 2014

b) c)

808,002.81 837,651.30

01 Jul 2013 (1,004 Calendar a) Days)

2,500,000.01

b) c)

a) b) c)

a)

31 Mar 2016

20 Sep 2012 (1,094 Calendar a) Days)

b) c)

a)

19 Sep 2015 23 Oct 2015

Eastern Samar 080514H00006

b) c)

100

100

98.24

98.24

project substantially completed.

2,500,000.01

100

61.55

24.57

-36.98

39.92

project ongoing

2,455,881.55

100

83.49

74.13

-9.36

88.79

project ongoing

2,200,000.00

100

45.43

41.11

-4.32

100

10.00

7.00

100

85.00

80

2,500,000.01

2,455,881.55 2,455,881.55

2,200,000.00

4/14/2016 6/13/2016

b) c)

2,200,000.00

1/30/2013

a)

50,000.00

5/27/2013

b)

c)

Access Road to Borongan-Llorente Closed a) Canopy Forest Area, Maydolong-Borongan a) City, GRAVEL TO PAVED Eastern Samar District Engineering Office, b) b) Region VIII c) c) Maydolong, Eastern Samar

b) c)

16 Apr 2013 (1,095 Calendar a) Days)

Samar Pacific Coastal Road (EASTERN SAMAR) 080513H00001 Access Road to Borongan-Llorente Closed a) a) Canopy Forest Area, MaydolongBorongan City, GRAVEL TO PAVED Eastern Samar District Engineering Office, b) b) Region VIII c)

b) c)

802,070.56 +US$140,182.68

50,000.00

90.49

project ongoing

-3.00

70.00

project ongoing

-5.00

94.12

project ongoing

45,909.80

c)

4/28/2014

a)

11/5/2014

b)

5/3/2015

c)

50,000

50,000

Page 1 of 26

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

a) Prog. Amount

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Revised (C.A.)

FINANCIAL (P'000)

AA Issued To Date

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

Target

Actual

Slippage

Performance

Employment Generated (Man-Days)

Remarks

080514H00007 Road from Brgy. Ngolos-Brgy. Sulangan a) (Guiuan-Sulangan Road GRAVEL TO PAVED a) b) DPWH Region VIII/Eastern Samar DEO Guiuan, Eastern Samar

c)

080515H00009

Jct. Buenavista-Lawaan-Marabut Road a) K0984+000 - K0989+000 PAVED (CONCRETE) TO PAVED (CONCRETE) b) DPWH Region VIII/Eastern Samar DEO Eastern Samar

c)

a)

080513H00010 Arteche-Jipapad-Las Navas-Rawis Road, Chainage: 000 - Chainage 1200, GRAVEL TO PAVED

a)

1/2/2015

b)

c)

120,000.00

a)

3/17/2015

a)

b)

8/13/2015

b)

c)

50,000.00

b)

5/11/2013

b)

21,360.80

Road Opening/Construction of Arteche (Brgy. Catumsan)-Jipapad-Las Navasa) Catubig-Rawis Road (Including Bridges and ROW), ROAS OPENING (4km), CONCRETE

3/20/2014

a)

100,000.00

11/11/2014

b)

84,247.27

3/17/2015

a)

36,000.00

8/13/2015

b)

Arteche, Brgy. Calumsan-Jipapad-Las Navasa) Catubig-Rawis Road (Including Bridges and a) ROW) GRAVEL TO PAVED b) DPWH Region VIII/Eastern Samar DEO b) c) Eastern Samar c) 080515H00026 a) Jct. Taft-Oras-San Policarpo-Arteche Road K0894+000 -K0895+000, K0902+000 K0902+092, K0910+000 -K0910+710, K0924+000 -K0925+000, K0961+152 K0962+000 PAVED TO PAVED b) DPWH Region VIII/Eastern Samar DEO c) Eastern Samar

-3.72

96.27

50,000.00

100

1.55

4.00

2.45

258.06

25,200.00

100

-8.86

53.02

100,000.00

100

36,000.00

130,000.00

project's schedule expired

project's schedule expired

-

30,739.64

-

53,507.64

84,247.28

-

84.25

18.86

10.00

project's schedule expired

project's schedule expired

76.65

97.00

20.35

126.55

100

1.55

4.00

2.45

258.06

project ongoing

100

13.85

45.00

31.15

324.91

project ongoing

33,354.70

c)

2/24/2015

a)

11/10/2015

b)

130,000.00 111,676.70

c)

a)

3/3/2015

b)

8/14/2015

c)

96.00

47,381.30

25,200.00

Jct. Taft-Oras-San Policarpo-Arteche Road a) K0950+000 - K0955+000 PAVED a) (CONCRETE) TO PAVED (CONCRETE) b) DPWH Region VIII/Eastern Samar DEO b) c) Eastern Samar c) 080515H00025

99.72

c) a)

b) c)

100

108,083.10

30-Jan-13

b) DPWH-Regional Office VIII c) Eastern Samar 080515H00012

120,000.00

c)

a)

b) DPWH-Eastern Samar DEO c) Artheche, Eastern Samar 08514H00011 a)

b)

4/18/2014

a)

b)

40,631.00

40,631.00

100

3.14

37,010.20

c)

Page 2 of 26

15.00

11.86

477.71

project ongoing

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

080515H00029 a) Jct. Buenavista-Lawaan-Marabut Road K0952+(-828) - K0953+538, K0953+638 K0957+644, K0957+672 -K0958+291, K0958+315 -K0959+054, K0959+094 K0961+142, K0961+158 - K0969+428, a) K0969+554 -K0975+244, K0975+266 K0977+591, K0977+681 -K0977+733, K0977+779 -K0978+777, K0978+812 K0980+846 CONCRETE REBLOCKING RIGHT LANE b) DPWH Region VIII/Eastern Samar DEO b) c) Eastern Samar c) 080515H00031 Jct. Taft-Oras-San Policarpo-Arteche Road a) K0963+906 - K0964+347, K0969+016 a) K0969+970 GRAVEL TO PAVED b) DPWH Region VIII/Eastern Samar DEO b) c) Eastern Samar c) 080313H00033 Concreting/upgrading of gaps along Km a) Lapining-Arteche Road, 963+840 - Km 969+970 with exceptions, GRAVEL TO PAVED b) DPWH-Regional Office VIII c)

Eastern Samar

a) Prog. Amount

3/3/2015

6/15/2015

a)

b)

Revised (C.A.)

38,479.00

FINANCIAL (P'000)

AA Issued To Date

38,479.00

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE

Expenditure

Rate (%)

Total

Disbursement

Target

5.83

100

Actual

Slippage

15.00

9.17

Performance

257.29

Employment Generated (Man-Days)

Remarks

project ongoing

35,140.40

c)

3/16/2015

a)

39,880.00

7/13/2015

b)

38,150.00

39,880.00

100

85,000.00

100

project ongoing

2.76

15.00

12.24

543.48

8.16

53.73

45.57

658.46

project's schedule expired

c)

a)

2/7/2013

a)

b)

11/11/2014

b)

c)

85,000.00

26,778.50

26,779.50

31.51

84,247.27

c)

SAMAR 080415H00003 Dolongan-Basey Road -Chainage 2816 Chainage 2987, Chainage 3197 - Chainage a) 4412, Chainage 4820 - Chainage 5284 GRAVEL TO PAVED b) DPWH-Samar 2nd DEO c) Basey, Samar

a)

2/25/2015

a)

b) c)

8/22/2015

b) c)

a)

2/24/2014

a)

b)

8/22/2014

b)

40,204.00

40,204.00

100

-

-

-

15.00

30.00

15.00

200.00

project ongoing

31,860.00

100

-

-

-

100.00

95.00

-5.00

95.00

project ongoing

25,601.70

100

-

-

-

60.00

55

-5.00

91.67

project ongoing

36,077.00

080414H00017 a)

Malajog Br. Along Daang Maharlika (SM) (Sn Isidro-San Juanico Br.)

b) DPWH-Samar 1st DEO c) Samar 1st District 080414H00021 Tinambacan Br. Along Daang Maharlika (SM) (Sn Isidro San Juanico Br.) a) RETROFITTING/REHABILITATION/ STRENGTHENING b) DPWH-Samar 1st DEO c) Samar 1st District

c)

c)

a)

2/24/2014

a)

b)

8/22/2014

b)

c)

31,860.00 27,932.20

25,601.70 22,609.20

c)

Page 3 of 26

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

080413H00023 Road opening/concreting of Calbayog Diversion Road (including ROW) a) Km10+020 - Km11+40, with exception, Road OPENING, CONCRETE b) DPWH-Samar 1st DEO c) Calbayog City, Samar 1st District

SCHEDULE

a) Start Date

a) Prog. Amount

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

a)

2/6/2013

b)

8/1/2013

c)

a) b)

a)

3/20/2015

a)

b)

9/13/2015

b)

c)

c)

080415H00054 Rehabilitation/Improvement of Access Road a) leading to Calbayog Airport - GRAVEL TO a) PAVED b) b) DPWH-Samar 1st DEO c) Calbayog City c) 089912H00001 Rehabilitation / Reconstruction of a) Catbalogan Diversion Road ROAD OPENING, CONCRETE b) DPWH-Samar 2nd DEO c) Catbalogan City 080413H00010 Road opening/concreting of a) Catbalogan City Diversion Road, Road OPENING, CONCRETE b) DPWH-Samar 2nd DEO c)

Samar 2nd District 080414F00015 Construction/Rehabilitation of Antiao River a) Control b) DPWH Region VIII c) Catbalogan, Samar 2nd District

49,400.00

Unpaid Obligation

Expenditure

Disbursement

Total

Rate (%)

-

-

-

Target

Actual

30.51

33

49,400.00

100

50,000.00

100

-

-

-

6.74

50,000.00

100

-

-

-

Slippage

Performance

Employment Generated (Man-Days)

Remarks

2.49

108.16

project ongoing

37

30.26

548.96

project ongoing

30.00

45

15.00

150.00

project ongoing

45,423.20

50,000.00 44,238.30

c)

3/5/2015

a)

7/2/2015

b)

50,000.00 45,105.60

c)

a)

3/5/2012

a)

100,000.00

b) c)

11/29/2012 4/28/2013

b) c)

95,459.00

a)

1/9/2013

a)

b)

5/9/2013

b)

a)

2/14/2014

a)

75,000.00

b)

9/11/2014

b)

59,670.15

c)

AA Issued To Date

PHYSICAL (%)

EXPENDITURE

c)

080415H00033 Construction/Rehabilitation of Calbayog a) Diversion Road, Sta. 11+667.5 - Sta. 16+ 551.45 GRAVEL TO PAVED b) DPWH-Samar 1st DEO Samar 1st District

Revised (C.A.)

FINANCIAL (P'000)

Funding Support (%)

c)

c)

25,360.00

100,000.00

100

18,908.61

76,550.55

3,804.00

95,459.16

95.46

100

95.00

-5.00

95.00

3,804.00

15

35.00

40

5.00

114.29

95,909.80

127.88

99.47

62.00

37.47

62.33

project's schedule expired

project's schedule expired

25,360.00

100

75,000.00

100

40,000.00

100

-

-

-

15.00

20.00

5.00

133.33

project ongoing

25,000.00

100

-

-

-

15.00

20.00

5.00

133.33

project ongoing

22,508.80

45,909.80

50,000.00

project's schedule expired

c)

080415F00017 Construction of Flood Control Structure, a) Silaga Bridge along Daang Maharlika, Brgy. a) Tulay, Sta. Rita, Samar - CONSTRUCTION

2/11/2015

a)

b) DPWH-Samar 2nd DEO

b)

7/31/2015

b)

c)

c)

Basey, Samar

080415F00018 Construction of Flood Control Structure, Balugo Bridge along Daang Maharlika, Brgy. a) a) Balugo, San Sebastian, Samar CONSTRUCTION b) DPWH-Samar 2nd DEO b) c)

San Sebastian, Samar

c)

40,000.00 35,699.50

c)

2/11/2015

a)

7/31/2015

b)

25,000.00 21,852.20

c)

080415F00019

Page 4 of 26

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

a) Prog. Amount

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

ConstructionRehabilitation of Flood Control a) Structure along Daang Maharlika, Poblacion a) Jiabong, Samar - CONSTRUCTION

2/11/2015

a)

b) DPWH-Samar 2nd DEO

b)

7/31/2015

b)

c)

c)

Jiabong, Samar

Revised (C.A.) 50,000.00

FINANCIAL (P'000)

AA Issued To Date

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE

Expenditure

Rate (%)

Total

Disbursement

Target

Actual

Slippage

Performance

Employment Generated (Man-Days)

Remarks

15.00

30.00

15.00

200.00

project ongoing

81.64

100.00

91.25

-8.75

91.25

project's schedule expired

99.05

100.00

98.80

-1.2

98.80

100

20.00

20.00

0

100.00

project ongoing

50,000.00

100

25.00

25.00

0

100.00

project ongoing

21,423.00

100

100.00

-15

85.00

project ongoing

50,000.00

100

-

-

-

80,000.00

100

54,815.05

10,493.27

65,308.32

200,000.00

100

119,064.10

79,035.30

198,099.40

21,443.40

45,773.20

c)

08414H00034 Construction/Improvement (Concreting) of Catbalogan City Diversion Road, Samar 2nd District Sta. 0+000 to Sta. 5+543.43 b) DPWH-Samar 2nd DEO c) Catbalogan City a)

a)

2/28/2014

a)

80,000.00

b) c)

10/15/2014

b) c)

65,308.32

a) Gaps along Lapinig-Arteche Road

a)

7/30/2012

a)

b) DPWH Region VIII c) Northern Samar

b)

6/6/2013

c)

7/17/2014

a)

1/12/2015

b)

6/30/2015

NORTHERN SAMAR

PAMANA Road Projects 089912H00002

080613F00010 a) Construction/rehabilitation of creitical sections of slope protection, Brgy. Nenita River along Bugko-Nenita Road, K0767+650, Brgy. Nenita, Mondragon CONSTRUCTION b) DPWH VIII/Northern Samar 1st DEO c) Mondragon, Northern Samar

200,000.00 193,998.30

a)

21,443.40

project's schedule expired

51,896.60

c)

080614H00010 a) Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure including Local Projects, Construction/Upgrading of San IsidroLope De Vega Road, Northern Samar GRAVEL TO PAVED b) Northern Samar 1st DEO c) Northern Samar

a)

12/17/2014

b)

6/13/2015

a)

50,000.00

43,059.60

c)

080613S00027 a)

Catarman NHS, Catarman (Capital), Northern Samar CONSTRUCTION

a)

9/16/2014

b) DPWH VIII/Northern Samar 1st DEO

b)

3/20/2015

c)

c)

c)

a)

a)

Catarman, Northern Samar 080614H0028

Eco-tourism Roads, Northern Samar, Capul a) Circumferential Roads, Capul GRAVEL TO PAVED

a) b)

b) Northern Samar 1st District

b)

b)

c)

c)

c)

Capul, Northern Samar

21,423.00

85.00

20,226.30

25,000.00

25,000.00

100

080614H00029

Page 5 of 26

0

#DIV/0!

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

a) Eco-tourism Roads, Northern Samar, Poblacion- Rock Formation Road, Biri GRAVEL TO PAVED b) DPWH VIII/Nothern Samar 1st DEO c)

Biri, Northern Samar

SCHEDULE

a) Start Date

a) Prog. Amount

b) Completion Date b) Contract Amount c) Rev.Comp. Date c) a)

10/28/2014

b)

4/25/2015

Revised (C.A.)

FINANCIAL (P'000)

AA Issued To Date

Funding Support (%)

a)

20,000.00

20,000.00

a)

30,000.00

30,000.00

100

100,000.00

100

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

100

Target

Actual

Slippage

Performance

Employment Generated (Man-Days)

Remarks

55.00

55.00

0

100.00

project ongoing

28.43

28.43

0

100.00

project ongoing

25.47

199.76

project ongoing

19.5

285.71

project ongoing

-33

67.00

40

900.00

-20

80.00

c)

080614H00030 a) Eco-tourism Roads, Northern Samar, San Vicente Roads, San Vicente GRAVEL TO a) PAVED b) DPWH VIII/Nothern Samar 1st DEO b) c) San Vicente, Northern Samar c)

12/30/2014 6/27/2015

26,918.20

080614H00045

a)

Road Opening/Construction of Arteche, Brgy. Catumsan-Jipapad- Las Navasa) Catubuig-Rawis Road Sta. 1+780Sta.7+0000

8/29/2014

a)

100,000.00

b) DPWH-Regional Office, Region VIII

b)

4/20/2015

b)

c)

c)

8/18/2015

c)

a)

1/23/2015

a)

56,889.00

b)

9/19/2015

b)

51,896.60

Northern Samar II DEO 080614H00046

Sn Antonio Circumferential Rd a) K0019+349 - K0023+805 GRAVEL TO PAVED Nothern Samar 1st District Engineering b) Office, Region VIII c) Northern Samar 080313H00047 Const/Repair/Rehab/Impvt of VILP's Construction of GandaraMatuguinao Road, Sta. 00+000 - Sta. 20+000, Samar 1st LD GRAVEL TO PAVED b) DPWH VIII/Nothern Samar 1st DEO c) Northern Samar a)

c)

71,587.34

12,633.06

84,220.40

84.22

25.53

51.00

84,220.40

56,889

100

10.5

100

30.00

c)

a)

2/24/2014

a)

b)

6/23/2014

b)

c)

20,000.00

20,000.00

100

30,000.00

100

67.00

project's schedule expired

c)

080515H00050 a) Mondragon-Bantayan 1341 -Chainage 2058 a) 2335 - Chainage 3047 GRAVEL TO PAVED

3/25/2015

a)

30,000.00

b) DPWH VIII/Nothern Samar 1st DEO c) Northern Samar

7/22/2015

b)

26,742.90

080613H00054 Sn Antonio Circumferential Rd K0001+919-K0003+765, a) K0004+655-K0004+737, K0004+748-K0005+28 GRAVEL TO PAVED Nothern Samar 1st District Engineering b) Office, Region VIII c) Northern Samar

b) c)

45.00

project ongoing

c)

a)

2/7/2013

b)

11/3/2013

c)

5.00

a)

46,368.00

46,368.00

100

100

b) c)

080613H00057

Page 6 of 26

80

project's schedule expired

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Poblacion-Barangay Bonifacio Road, a) K0699+143-K0700+(-021), K0700+ (021) - a) K0700+379, GRAVEL TO PAVED

a)

29,425.00

6/4/2013

b)

27,459.90

a)

12/17/2014

b)

4/15/2015

c)

c)

Northern Samar Ist District 080614H00065

b) c)

b) DPWH-Regional Office, Region VIII

5/1/2015

c)

c)

Northern Samar Ist DEO 080614H00070 Poblacion-Barangay Bonifacio Road, a) K0700+379 - K0701+174 & K0701+728 - K0701+804 GRAVEL TO PAVED Northern Samar 1st District Engineering b) Office, Region VIII c) Northern Samar 080615H00005 LIP-Concrete Paving of Road Shoulder, Palapag-Mapanas-Gamay-Lapinig Road, a Tinampo-Palapag-Paysud Section, K0800+091 - K0800+256 and K0800+384a) K0800+774; b. Palapag-Paysud Section, K0803+076 -K0803+566: c. GamayCagamutan Section, K0843+000 K0844+000 (PAVED (CONCRETE) TO PAVED (CONCRETE) b) DPWH/Northern Samar 2nd DEO c) Palapag, Northern Samar

a) b)

a)

29,425.00

Unpaid Obligation

100

Expenditure

Total

Disbursement

-

Rate (%)

-

-

Target

Actual

Slippage

Performance

15.00

15.00

0

100.00

Employment Generated (Man-Days)

Remarks

project's schedule expired

25,990.00

25,990.00

100

50.00

55.00

5

110.00

project ongoing

34,612.00

100

60.00

50.00

-10

83.33

project ongoing

24,346.00

100

85.00

95.00

10

111.76

project ongoing

1.17

23.8

22.63

2034.19

project ongoing

22,902.50

b)

34,612.00 31,545.40

c)

11/6/2014 4/6/2015

a) b)

c)

c)

a)

a)

b)

b)

c)

c)

24,346.00 20,998.30

25,025.00

a)

3/12/2015

a)

40,000.00

b)

8/8/2015

b)

34,935.20

c)

AA Issued To Date

PHYSICAL (%)

EXPENDITURE

c)

11/3/2014

b)

FINANCIAL (P'000)

Funding Support (%)

c)

Daang Maharlika (SM) (Sn Isidro-Sn Juanico a) Br) - K0684+500 -K0685+345, K0685+421 - a) K0686+805 PAVED TO PAVED c) Northern Samar Ist DE 080614H00066 Catarman-Calbayog Road - K0769+000 a) K0770+300, K0772+700 -K0773+750 PAVED a) TO PAVED b) DPWH-Regional Office, Region VIII b)

Revised (C.A.)

2/5/2013

Northern Samar 1st District Engineering Office, Region VIII c) Northern Samar 080614H00062 Poblacion-Barangay Trujillo Road a) K0738+000 - K0738+990, K0738+990 K0739+117 GRAVEL TO PAVED b) DPWH-Regional Office, Region VIII b)

a) Prog. Amount

25,025.00

40,000.00

100

100

c)

089913H00006

Page 7 of 26

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Road opening/upgrading of Bugko-NenitaMirador-Cagpanit-an-De Maria-San Jose a) Road, (including Construction of De Maria a) Bridge approaches and slope protection), Chainage 12000 = Chainage 15659, GRAVEL TO PAVED b) DPWH-Regional Office VIII b) c)

Northern Samar, 2nd District

080615F00009 Construction of Palapag River Control. CONSTRUCTION b) DPWH/Northern Samar 2nd DEO c) Palapag, Northern Samar a)

080613H00024 Concreting/upgrading of gaps along a) Lapining-Arteche Road, K853+114.5 K854+210, GRAVEL TO PAVED b) DPWH-Northern Samar 2nd DEO c) Northern Samar, 2nd District

2/20/2013

a)

84,754.00

73,252.10

9/23/2013

b)

2/2/2014

c)

a)

2/25/2015

a)

31,000.00

b)

8/23/2015

b)

27,959.60

c)

2/6/2013

a)

b) c)

6/13/2013

b)

2/6/2013

a)

33,000.00

6/15/2013

b)

28,129.70

a)

3/11/2015

a)

31,479.00

b)

9/6/2015

b)

28,823.50

c)

b) DPWH/Northern Samar 2nd DEO

b)

c)

c)

30,000.00

AA Issued To Date

84,754.00

31,000.00

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

Target

Actual

Slippage

Performance

100

100

100

0

100

100

8.32

32.19

23.87

386.90

10.03

17.72

7.69

176.67

8.56

25.40

16.84

296.73

Employment Generated (Man-Days)

Remarks

project completed on 3/23/2014

project ongoing

30,000.00

100

3,834.90

4,219.50

3,834.90

4,219.50

12.78

12.79

project's schedule expired

project's schedule expired

33,000.00

100

31,479.00

100

4.02

32.2

28.18

801.00

project ongoing

33,500.00

100

7.1

38.09

30.99

536.48

project ongoing

100

100

100

0

100

project ongoing

c)

3/4/2015

a)

33,500.00

8/30/2015

b)

30,221.40

c)

a)

4/30/2012

a)

97,853.00

b)

5/12/2013

b)

19,456.90

c)

FINANCIAL (P'000)

Funding Support (%)

c)

a)

080615H00038 Rawis-Catubig Road - K0788+750 a) K0789+300 OTHER IMPVT. WORKS (SLOPE a) PROTECTION, DRAINAGE, SIDEWALKS)

Northern Samar 080613H00038 Pangpang-Palapag-MapanasGamay-Lapining Road, K0838+400, K0846+208a) K0847+440, K0848+200 K0849+820 &K0809+573 K0811+201, with exeptions GRAVEL TO PAVED b) DPWH-Northern Samar 2nd DEO c) Northern Samar, 2nd District

Revised (C.A.)

c)

080613H00025 Concreting/Upgrading of gaps along Lapining-Arteche Road , a) a) K858+764 - K860+000 GRAVEL TO PAVED b) DPWH-Northern Samar 2nd DEO b) c) Northern Samar, 2nd District c) 080615H00033 Sn Roque-Cababtoan Old Road a) K0774+892 - K0775+181, K0777+071 K0778+282 GRAVEL TO PAVED b) DPWH/Northern Samar 2nd DEO c) Northern Samar

a) Prog. Amount

97,853.00

c)

080615H00043

Page 8 of 26

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

a)

SCHEDULE

a) Start Date

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd - K0815+115 - K0816+884, K0837+526 a) K0838+000 GRAVEL TO PAVED/DistrictWide

b) DPWH-Northern Samar 2nd DEO

b)

c)

c)

Northern Samar, 2nd District

a) Prog. Amount

080615H00046 Local Instrastructure Program Repair/Rehab Bantayan - Malobagoa) Pagsang-an -Lawaan-Ginagdaan, Bantayan- a) Pagsang-an Section, San Roque, Northern Samar b) DPWH/Northern Samar 2nd DEO b) c) San Roque, Northern Samar c)

Revised (C.A.)

2/17/2015

a)

57,000.00

9/24/2015

b)

52,282.80

3/15/2015

a)

30,000.00

8/5/2015

b)

27,137.30

FINANCIAL (P'000)

AA Issued To Date

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

Target

Actual

Slippage

Performance

Employment Generated (Man-Days)

Remarks

57,000.00

100

19.55

50.28

30.73

257.19

project ongoing

30,000.00

100

1.93

20.93

19

1084.46

project ongoing

23,000.00

100

5.9

35.49

29.59

601.53

project ongoing

44.98

996.02

c)

080615H00048 Pangpang-Palapag-Mapanas-Gamay-Lapinig Rd - K0815+225 - K0815+325, K0822+650 a) K0832+850, K0839+200 - K0839+400 a) OTHER IMPVT. WORKS (SLOPE PROTECTION, DRAINAGE, SIDEWALKS) b) DPWH-Northern Samar 2nd DEO

b)

c)

c)

Northern Samar

3/2/2015

a)

23,000.00

7/29/2015

b)

20,672.20

c)

080613H00051 Pangpang-Palapag-Mapanas-GamayLapining Road, K0807+060 - K0807+400, a) K0808+135 - K0809+000, GRAVEL TO PAVED b) DPWH-Northern Samar 2nd DEO

a)

3/1/2012

a)

28,691.00

b)

6/6/2013

b)

191,563.00

c)

c)

Northern Samar, 2nd District

a)

2/6/2013

b)

5/3/2013

c)

c)

080613H00059 Pangpang-Palapag-Mapanas- GamayLapining Road, K0823+641 - K0824+000, a) K0833+569 - K0834+159, GRAVEL TO PAVED b) DPWH-Northern Samar 2nd DEO c) Northern Samar, 2nd District

100

13,224.60

13,224.60

30,700

30,700.00

100

18,420.00

18,420.00

23,284.00

100

46.09

5.02

50.00

project's schedule expired

c)

080613H00053 Pangpang-Palapag-Mapanas-GamayLapining Road, a) K0822+(-366) - K0822+(-029), K0823+(-172) - K0823+000, GRAVEL TO PAVED b) DPWH-Northern Samar 2nd DEO Northern Samar, 2nd District

28,691.00

a)

60.00

57.26

71.83

14.57

125.45

43.12

28.75

62.05

33.3

215.83

project's schedule expired

b) c)

a)

3/1/2013

a)

23,284.00

b)

5/23/2013

b)

21,728.90

10,039.60

c)

080615H00075

Page 9 of 26

10,039.60

project's schedule expired

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Laoang-Calomotan Road - K0974+700 a) K0796+500 (PAVED (CONCRETE) TO PAVED a) (CONCRETE) b) DPWH/Northern Samar 2nd DEO b) c) Palapag, Northern Samar c) 080515H00077 Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure a) a) including Local Projects - Construction of San Isidro-Lope De Vega Road, GRAVEL TO PAVED b) DPWH/Northern Samar 2nd DEO c) Northern Samar

a) Prog. Amount

b)

Revised (C.A.)

3/11/2015

a)

35,247.00

8/7/2015

b)

31,274.40

FINANCIAL (P'000)

AA Issued To Date

Funding Support (%)

35,247.00

100

50,000.00

100

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE

Expenditure

Rate (%)

Total

Disbursement

Target 3.79

Actual

Slippage

16.33

Performance

Employment Generated (Man-Days)

Remarks

12.54

430.87

project ongoing

45

1000.00

project ongoing

-11.67

88.33

0.92

102.70

project ongoing

c)

3/25/2015

a)

50,000.00

9/19/2015

b)

46,257.30

c)

5.00

50.00

c)

Leyte Circumferential Road(s) a. Babatngon-San Miguel-Barugo-Carigara Road 080214H0016 Road Opening of San Miguel - BabatngonTacloban City Road along Bagahupia) Babatngon-Sta. Cruz-Caraycaray Section Leyte 1st District ROAD OPENING, CONCRETE b) DPWH-Leyte 1st DEO

a)

1/17/2014

b)

7/16/2014

c)

c)

Leyte 1st District

a)

50,000

50,000

100

100

49,679.00

49,679.00

100

34.08

88.33

project's schedule expired

b) c)

080215H00028 Mainit-Sn Miguel-Santol Rd. - K0945+865, a) K0945+933 - K0978+097, K0950+399 K0951+ 199 GRAVEL TO PAVED

a)

1/30/2015

a)

b) DPWH Region VIII

b)

7/27/2015

b)

c)

c)

Leyte 1st District

080215H00044 a) Leyte-Samar Inter-Provl Rd - K0909+363 k0910+270, K0910+421 -K0911+243, K0911+243 - K0911+400 GRAVEL TO PAVED b) DPWH Region VIII/Leyte 1st DEO c)

DistrictWide-Leyte 1st District 080215H00045

Bagahupi-Babatngon-Sta Cruz - BarugoCarigara Rd. - Chainage 2167-Chainage 2782, Chainage 8361 - Chainage 9389, GRAVEL TO PAVED b) DPWH-Leyte 1st DEO a)

c)

Leyte 1st District

46,249.90

c)

a)

1/30/2015

a)

49,574.00

b)

7/27/2015

b)

46,155.10

c)

49,574.00

34.08

35.30

1.22

103.58

project ongoing

34.08

45

10.92

132.04

project ongoing

c)

a)

1/30/2015

a)

b)

7/27/2015

b)

c)

35.00

37,789.00

37,789.00

100

34,775.70

c)

080213H00066

Page 10 of 26

-

-

-

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

a) Prog. Amount

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Road Opening, San Miguel Babatngon-Tacloban Road, along a) a) Babatngon-Sta. Cruz-Caraycaray Section, ROAAD OPENING, CONCRETE

1/14/2013

a)

40,000.00 39,500.00

b) DPWH-Leyte 1st DEO

b)

6/22/2013

a)

c)

c)

8/21/2013

c)

a)

1/17/2014

b)

 6/13/2014

c)

  

Leyte 1st District

080214H00108 a) Widening of Pawing-Campetic Road, K0917+(-334) - K0917+986, Leyte 1st LD WIDENING PAVED/DistrictWide,Leyte 1st District Engineering Office,Region VIII b) Leyte 1st DEO, DPWH VIII c) Palo, Leyte

a)

080215H00128 Tigbao-Sta. Fe-Sn. Miguel Road a) K0911+224 - K0913+000, K0913+828 K0913+876 GRAVEL TO PAVED b) DPWH Region VIII

a)

2/5/2015

a)

b)

9/22/2015

b)

c)

c)

Leyte 1st District 080215H00152 San Miguel-Babatngon-Tacloban City Road a) along Bagahupi-Sta. Cruz-Caraycaray Section (GRAVEL TO PAVED) b) DPWH Region VIII c) Leyte 1st District 080215H00185

a) Daang Maharlika (LT) - K0948+000 -

K0949+000, K0950+000 - K0953+620 WIDENING - PAVED/DistrictWide,Leyte 1st District Engineering Office,Region VIII b) DPWH Region VIII c)

DistrictWide-Leyte 1st District

080215H00199 a) Daang Maharlika (LT)-K0898+(-178)K0898+462,K0900+862K0900+883,K0900+892K0900+910,K0900+932K0901+046,K0901+375K0901+393,K0901+594K0901+632,K0901+677K0901+735,K0901+789K0901+799,K0902+334K0902+397,K0902+790K0902+850,K0902+950-K0902+980 PAVED (CONCRETE) TO PAVED (CONCRETE) b) DPWH Region VIII c) DistrictWide-Leyte 1st District

Revised (C.A.)

100

 24,000

 24,001

60,745.00

60,745.00

Expenditure

Total

Disbursement

-

Rate (%)

-

-

Target

Actual

Slippage

Performance

Employment Generated (Man-Days)

Remarks

project's schedule expired

100

92

-8

92.00

100

100

77.00

-23

77.00

100

2.94

5.67

2.73

192.86

project ongoing

40,375.00

100

35.67

30.00

-5.67

84.10

project ongoing

129,590.00

100

58,930.00

100

project's schedule expired

55,728.10

a)

40,375.00

b)

7/19/2015

b)

38,883.90

c)

c) 2/13/2015

11/11/2015

c)

a)

b)

129,590.00

3.54

5.43

1.89

153.39

project ongoing

118,929.30

c)

a)

2/17/2015

b)

9/14/2015

c)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE

c)

1/30/2015

b)

AA Issued To Date

40,000.00

a)

a)

FINANCIAL (P'000)

Funding Support (%)

a)

b)

58,929.00

54,076.70

c)

080214H00210

Page 11 of 26

12.86

17.20

4.34

133.75

project ongoing

a)

SCHEDULE

Project Name/Title/Scope

a) Start Date

Implementing Agency c) Location

b)

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

a) Widening of Daang Maharlika (LT), Leyte 1st LD, K0915+411 a) K0916+911,K0919+754 K0920+300.15 WIDENING - PAVED b) DPWH Region VIII/Leyte 1st DEO b) c) Districtwide c)

080214H00213 Mainit-Sn Miguel-Santol Rd K0947+558K0947+944,K0948+000 a) K0948+846,K0950+362 K0950+399,K0949+758 K095+042 GRAVEL TO PAVED 1st District Engineering b) Office, Region VIII c)

 1/17/2014

a)

Revised (C.A.)  37,413

FINANCIAL (P'000)

AA Issued To Date  37,414

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE

Expenditure

Rate (%)

Total

Disbursement

100

Target

100

Actual

Slippage

89.8%

-99.102

Performance

0.90

 7/31/2014

Employment Generated (Man-Days)

Remarks

project's schedule expired

  

a)

4/23/2014

a)

b)

8/21/2014

b)

39,210.00

39,210.00

100

100

53

-47

53.00

28,221.00

100

100

95.40

-4.6

95.40

49,000.00

49,000.00

100

100

80.00

-20

80.00

43,712.00

100

31.77

30.00

-1.77

94.43

100

100

0

100

2.00

15

13

750.00

project's schedule expired

Leyte

Leyte 1st District

080214H00214 a) Leyte-Samar Inter-Provl Rd - K0907+368 k0908+528, K0908+642 -K0908+773, K0908+816 - K0909+363 GRAVEL TO PAVED b) DPWH Region VIII c) Leyte Ist District Engineering

c)

c)

a)

4/23/2014

a)

28,221.00

b)

7/22/2014

b)

26,002.50

c)

project's schedule expired

c)

08214H00025 Burauen-Mahagnao Rd a) K0984+241 - K0985+1064 GRAVEL TO PAVED b) DPWH/Leyte 2nd DEO

a)

1/24/2014

b)

7/15/2014

c)

Leyte 2nd District 080215H00079 Bernard Reed Bridge (B00032LT) along a) Daang Maharlika (LT) b) DPWH Region VIII/Leyte 2nd DEO c) Leyte 2nd District 080213H00081 Balagnon Bridge along Burauen-Albuera a) Road CONSTRUCTION OF NEW BRIDGE b) DPWH-Leyte 2nd DEO c) Leyte 2nd District 080215H00103 Daguitan Bridge (B00067LT) along Daang Maharlika (LT) a) RETROFITTING/REHABILITATION/ STRENGTHENING b) DPWH-Leyte 2nd DEO

c)

c)

c)

2nd District

a) Prog. Amount

a) b)

project's schedule expired

c)

a)

2/9/2015

a)

43,712.00

b)

8/9/2015

b)

41,060.00

c)

project ongoing

c)

a)

2/28/2013

a)

b) c)

11/7/2013

b) c)

a)

3/13/2015

a)

b)

9/18/2015

b)

18,000.00

18,000.00

100

40,000.00

40,000.00

100

36,840.90

c)

080214H00104

Page 12 of 26

18,000.00

-

18,000.00

-

100.00

-

project substantially completed

project ongoing

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Bagahupi-Babatngon-Sta Cruz- BarugoCarigara Rd - K0930+420 - K0932+244 a) GRAVEL TO PAVED Leyte 2nd District Engineering b) Office, Region VIII c) Leyte 2nd District 080214H00113 Road Opening/Upgrading of Burauen-Albuera Road, including bridges, a) Burauen Side, Matagara Bridge, ROAD OPENING, CONCRETE b) DPWH-Leyte 2nd DEO

a)

5/20/2014

b)

2/13/2015

c)

c)

Buraeun, Leyte 2nd District 080214H00121 a) Road Opening/Upgrading of BurauenAlbuera Road, including Bridges, Burauen Side, Bridges, ROAD OPENING, CONCRETE

a) Prog. Amount

a)

3/28/2014

a)

b)

8/4/2014

b)

c)

a)

Revised (C.A.) 21,000.00

a)

100,000.00

b)

81,787.34

9/5/2014

a)

50,000.00

b)

3/2/2015

b)

c)

5/1/2015

c)

a)

1/30/2015

a)

27,287.00

b)

7/15/2015

b)

25,409.50

080213H00138 Bagahupi-Babatngon-Sta Cruz-Barugoa) Carigara Rd - K0934+049 - K0935+267.60, K0930+639 - K0931+420 GRAVEL TO PAVED b) DPWH-Leyte 2nd DEO c) Leyte 2nd District

c)

Rate (%)

Total

Disbursement

100

Target

Actual

Slippage

Performance

100

45.00

-55

45.00

100

51.26

-48.74

51.26

Employment Generated (Man-Days)

Remarks

project's schedule expired

100,000.00

100

69,519.24

12,268.10

81,787.34

81.79

50,000.00

100

80.00

83.33

3.33

104.16

27,287.00

100

35.67

36.04

0.37

101.04

20.00

15.00

-5

75.00

100

70.00

-30

70.00

10.00

30.00

20

300.00

project's schedule expired

project ongoing

45,109.40

project ongoing

c)

a)

1/28/2013

a)

25,90.00

b)

7/7/2013

b)

23,481.40

c)

080213H00139 Construction of Libas Bridge along Burauen Albuera Road, Burauen CONSTRUCTION OF a) a) NEW BRIDGE/Burauen,Leyte 2nd Disrict Engineering office, Region VIII b) b) DPWH-Leyte 2nd DEO c) Buraeun, Leyte 2nd District c)

100,000.00

Unpaid Obligation

Expenditure

c)

b) DPWH-Leyte 2nd DEO 080215H00134 Bagahupi-Babatngon-Sta CruzBarugo-Carigara Rd - K0925+060 a) K0925+720, K0925+845 - K0925+1280 OTHER IMPVT. WORKS (SLOPE PROTECTION, DRAINAGE SIDEWALKS) b) DPWH Region VIII c) Leyte 2nd District

AA Issued To Date

PHYSICAL (%)

EXPENDITURE

c)

c)

Burauen, Leyte 2nd District

FINANCIAL (P'000)

Funding Support (%)

25,90.00

100

21,000

100

-

-

-

project's schedule expired

c)

2/28/2013

a)

12/14/2013

b)

21,000

21,000

21,000.00

100

project's schedule expired

c)

080215H00150 a)

Dulag-Julita-Burauen Road - K0944+214 K0947+000 PAVED TO PAVED

b) DPWH Region VIII/Lete 2nd DEO c) Leyte 2nd District

a)

3/10/2015

a)

40,000.00

b)

8/1/2015

b)

34,607.00

c)

40,000.00

100

c)

080215H00151

Page 13 of 26

project ongoing

a)

Project Name/Title/Scope

Implementing Agency c) Location

b) a)

Jaro-Dagami-Burauen-La Paz Road K0969+500-K0973+400 PAVED TO PAVED

SCHEDULE

a) Start Date

a) Prog. Amount

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Revised (C.A.)

a)

2/23/2015

a)

40,000.00

b) DPWH Region VIII/Lete 2nd DEO

b)

7/17/2015

b)

35,819.10

c)

c)

Leyte 2nd District

080215H00169 Palo-Carigara-Ormoc Road - K0945+000, K0950+000 - K0951+969, K0954+320 a) a) K0956+780 PAVED (CONCRETE) TO PAVED (CONCRETE) b) DPWH Region VIII/Lete 2nd DEO b) c) Leyte 2nd District c)

2/24/2015

a)

116,207.00

7/13/2015

b)

103,630.50

2/3/2015

a)

130,000.00

b)

10/20/2015

b)

120,196.40

c)

c)

a)

2/18/2015

a)

102,203.00

b)

10/25/2015

b)

898,705.80

c)

c)

c)

a)

Total

Target

Actual

Slippage

Performance

Employment Generated (Man-Days)

Remarks

40,000.00

100

15.00

35.00

20

233.33

project ongoing

116,207.00

100

15.00

12.00

-3

80.00

project ongoing

130,000.00

100

21.92

45.98

24.06

209.76

project ongoing

102,203.00

100

1.05

1.10

0.05

104.76

project ongoing

c)

3/27/2012

a)

110,852.57

b)

7/25/2013

b)

46,540.00

c)

11/18/2013

c)

a)

Leyte 2nd District 080212H00378 Road Opening Burauen-Albuera Road Including Bridges, Burauen Side, a) Leyte 2nd Dist. ROAD OPENING, CONCRETE Leyte 2nd District Engineering b) Office, Region VIII

a)

3/19/2013

b)

3/7/2014

c)

c)

Buraeun, Leyte 2nd District

Disbursement

Rate (%)

c)

080215H00188 Palo-Carigara-Ormoc Road - K0946+755 K0947+000, K0959+435 - K0960+000, a) K0960+440 - K0961+798, K0962+000 K0963+1000 WIDENING - PAVED b) DPWH Region VIII Leyte 2nd District 080211H00243 Reconstruction of Carigara Bridge along a) Palo-Carigara-Ormoc Road, Carigara REPLACEMENT OF DAMAGED BRIDGE b) DPWH Region VIII

Unpaid Obligation

Expenditure

c)

a)

Leyte 2nd District

AA Issued To Date

PHYSICAL (%)

EXPENDITURE

c)

080215H00187 Daang Maharlika (LT) - K0955+589 K0958+804 WIDENING - PAVED b) DPWH Region VIII a)

FINANCIAL (P'000)

Funding Support (%)

b)

50,000

110,852.57

100

50,000

100

48,000.00

100

50,383.30

47,490.10

50,383.30

0.05

100

90

-10

90.00

47,490.10

94.98

46.75

35.00

-11.75

74.87

13,825.20

28.8

36.94

44.44

7.5

120.30

35.94

40.93

4.99

113.88

project's schedule expired

project's schedule expired

47,490.10

c)

b. Jct Sambolawan (Leyte)-Calubian-San Isidro-Tabango-Villaba Road

080213H00016 Tabing-Kawayan - Sta Rosa - Lawisa) Tabango Rd - K1033+222 K1035+222 GRAVEL TO PAVED b) DPWH Region VIII/Leyte 3rd DEO

a)

1/7/2013

a)

48,000.00

b)

8/4/2013

b)

43,136.40

c) Leyte 3rd District 080213H00017 San Isidro-Daja Road, a) K1022+000 - K1024+083, GRAVEL a) TO PAVED b) DPWH Region VIII/Leyte 3rd DEO b) c) Leyte 3rd District c)

13,825.20

project's schedule expired

c)

c)

1/7/2013 8/4/2013

a) b)

50,000.00

50,000.00

100

44,914.90

c)

080213H00018

Page 14 of 26

13,452.00

13,452.00

26.90

project's schedule expired

a)

SCHEDULE

Project Name/Title/Scope

a) Start Date

Implementing Agency c) Location

b)

b) Completion Date b) Contract Amount

Sambulawan Jct-Calaguise-Calubian Road, a) K0990+424 - K0992+400, GRAVEL TO PAVED b) DPWH Region VIII/Leyte 3rd DEO c)

a) Prog. Amount

c) Rev.Comp. Date c) a)

1/7/2013

a)

46,368.00

b)

8/4/2013

b)

41,677.60

c)

Leyte 3rd District

Revised (C.A.)

FINANCIAL (P'000)

AA Issued To Date 46,368.00

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

Target

Actual

Slippage

Performance

100

14,449.60

14,449.60

31.16

40.00

50.72

10.72

126.80

49,909.00

100

6,726.00

6,726.00

13.48

35.94

32.37

-3.57

90.07

49,000.00

100

40.00

57.52

17.52

143.80

100

81.00

-19

81.00

99.97

95.00

-4.97

95.03

Employment Generated (Man-Days)

Remarks project's schedule expired

c)

080213H00019 a)

Cabunga-an-Tabunok-Consuegra Road, a) K1015+517-K1017+597 GRAVEL TO PAVED

b) DPWH Region VIII/Leyte 3rd DEO

b)

c)

Leyte 3rd District 080213H00020 Tabango-Catmon-La FortunaManlawaan-Gimarco Road, a) K1040+297 - K1042+307, GRAVEL TO PAVED b) DPWH Region VIII/Leyte 3rd DEO

c)

c)

c)

Leyte 3rd District 080214H00041 Calubian Jct-Sn Isidro-TabangoVillabaa) Palompon Rd - K1006+557 - K1007+490 GRAVEL TO PAVED b) DPWH Region VIII/Leyte 3rd DEO c) Leyte 3rd District

1/7/2013 8/4/2013

a)

49,909.00

b)

44,839.70

c)

a)

1/3/2013

b)

8/4/2013

a) b)

1/30/2014

a)

b)

7/27/2014

b)

c)

b) c)

Belen Bridge and Approaches, leyte, a) Leyte CONSTRUCTION OF NEW BRIDGE

8/10/2012

a)

b) DPWH Regional Office, Region VIII

b)

11/26/2013

b)

c)

c)

project's schedule expired

113,160.00

100

21,276.00

100

100

99.37

-0.63

99.37

100

100

93.50

-6.5

93.50

project's schedule expired

21,276.00

5,066.46

98,794.53

103,860.99

91.78

project's schedule expired

project's schedule expired

c)

OF a)

10/10/2012

b)

10/9/2013

c)

100

103,861.00

8/9/2013 5/25/2014

Tabango, Leyte 3rd District

45,750.00

113,160.00

c)

c)

39.39

28,410.00

a)

b)

Leyte, Leyte 3rd District 080212H00085 Tugas Bridge and Approaches, a) Tabango, Leyte CONSTRUCTION NEW BRIDGE b) DPWH Regional Office, Region VIII

19,302.60

44,039.80

8/10/2012

b) DPWH Regional Office, Region VIII

a)

19,302.60

c)

c)

Leyte, Leyte 3rd District 080212H00084

49,000.00

c)

a)

080212H00082 Construction of Bridge substructure consisting of 2-concrete abutment supported by H-bored piles assembly & a) erection of centunion modular girder bridge, a) construction of approach roads, deck slab, slope protection and appurtenant structures (Contract Package 6)

project's schedule expired

a)

17,730.00

17,730.00

b) c)

080212H00086

Page 15 of 26

project's schedule expired

a)

SCHEDULE

Project Name/Title/Scope

a) Start Date

Implementing Agency c) Location

b)

Lawis Bridge and Approaches, a) Tabango, Leyte CONSTRUCTION NEW BRIDGE b) DPWH Regional Office, Region VIII c) Tabango, Leyte 3rd District

a) Prog. Amount

b) Completion Date b) Contract Amount c) Rev.Comp. Date c) OF

a)

10/10/2012

b)

10/9/20013

c)

080213H00106 Calubian Jct-Sn Isidro-Tabango- VillabaPalompon Road, K1006+487 - K1006+557 a) a) , K1007+490 - K1009+500, GRAVEL TO PAVED b) DPWH Region VIII/Leyte 3rd DEO b) c)

Leyte 3rd District 080213H00124 Sambulawan Jct. - Calaguise Calubian a) Road , K1001 +390-K1003 + 390 GRAVEL TO PAVED b) DPWH Region VIII/Leyte 3rd DEO

c)

c)

c)

Leyte 3rd District

12,521.90

47,844.00

100

10,982.50

10,982.50

44,341.10

a)

Actual

Slippage

Performance

Employment Generated (Man-Days)

Remarks project's schedule expired

100

95.70

-4.3

95.70

25.07

35.94

39.32

3.38

109.40

22.95

39.52

32.64

-6.88

82.59

46.11

50.62

4.51

109.78

-7.38

70.48

project ongoing

project ongoing

project's schedule expired

b)

47,844.00 41,056.10

project's schedule expired

c)

1/8/2013

b)

7/6/2013

b)

20,354.00

20,354.00

100

9,323.80

9,323.80

45.81

41,781.00

100

25.00

191,922.00

100

3.25

5.80

2.55

178.46

14,184.00

100

100

96.50

-3.5

96.50

18,419.31

project's schedule expired

c)

b)

8/8/2015

b)

c)

c)

c)

12,521.90

Target

c)

a)

San Isidro, Leyte 3rd District

100

b)

8/4/2013

b)

49,950.00

8/5/2013

b)

c)

100

49,950.00

2/11/2015

a)

Total

14,184.00

a)

a)

b) c)

Disbursement

Rate (%)

b)

080215H00132 Sambulawan Jct-Calaguise-Calubian Rd a) K0993+493 - K0994+283, K0997+603 K0998+311 GRAVEL TO PAVED b) DPWH Region VIII/Leyte 3rd DEO

a)

Unpaid Obligation

Expenditure

14,184.00

1/8/2013

1/8/2013

Leyte 3rd District 080215H00162 Tabing-Kawayan-Sta. Rosa-Lawis-Tabango Road - K1025+651 - K1025+596, K1025+577 - K1025+537, K1025+165 K1027+875, K1027+898 - K1028+048, K1028+071 -K1028+742, K1028+878 K1029+017, K1029+047 - K1030+087, K1030+168 - K1031+839, K1031+960 1032+266, K1032+372 - K1032+524 GRAVEL TO PAVED DPWH Region VIII/Leyte 3rd DEO Tabango, Leyte 080212H00205 Listing Bridge and Approaches, San Isidro, Leyte - RETROFITTING/ REHABILITATION/STRENGTHENING DPWH Regional Office, Region VIII

AA Issued To Date

PHYSICAL (%)

EXPENDITURE

c)

a)

080213H00125 Calubian Jct-Sn isidro-TabangoVillabaa) Palompon Road, K1036+000 -K1028+355, b) PAVED TO PAVED b) DPWH Region VIII/Leyte 3rd DEO b) c) Leyte 3rd District c)

a)

Revised (C.A.)

FINANCIAL (P'000)

Funding Support (%)

41,780.00

17.62

c)

a)

3/31/2015

a)

191,922.00

b) c)

3/6/2016

b) c)

183,177.70

a)

10/10/2012

a)

14,184.00

b)

10/9/2013

b) c)

080214h00216

Page 16 of 26

project's schedule expired

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

b)

Tabing-Kawayan - Sta Rosa - LawisTabango Rd - K1032+610 K1033+222,K1035+188 - K1035+1033 GRAVEL TO PAVED DPWH Region VIII/Leyte 3rd DEO Leyte 080214H00217 Cabunga-an-Tabunok-Consuegra Rd Chainage 000 -Chainage 2860,K1014+(-403) - K1014+(-361),K1017+597 - K1018+878 GRAVEL TO PAVED DPWH Region VIII/Leyte 3rd DEO

c)

Leyte 3rd District

a) b) c)

a)

080214H00218 Sambulawan Jct. - Calaguise Calubian Rd - K0992+400a) K0993+493,K1003+390 K1003+914,K0997+395 K0997+603 GRAVEL TO PAVED b) DPWH Region VIII/Leyte 3rd DEO c) Leyte 3rd District

SCHEDULE

a) Start Date

a) Prog. Amount

b) Completion Date b) Contract Amount c) Rev.Comp. Date c) a)

1/30/2014

b)

7/27/2014

a)

Revised (C.A.) 42,561

FINANCIAL (P'000)

AA Issued To Date 42,561

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

Target

Actual

Slippage

Performance

100

100

81

-19

81.00

100

100

62.90

-37.10

62.90

Employment Generated (Man-Days)

Remarks

project schedule expired

c)

a)

2/17/2014

a)

b)

10/18/2014

b)

c)

3/18/2015

c)

a)

1/27/2014

a)

b)

8/6/2014

c)

111,184.00

111,184.00

107,193.50

46,890

46,890

100

100

98.09

-1.91

98.09

28,267.00

28,267.00

100

100

79

-21

79.00

50,750.00

100

65.00

60.00

-5

92.31

100.00

29.50

-70.5

29.50

project's schedule expired

project's schedule expired

b) c)

080214H00220 Calubian Jct-Sn Isidro-TaBango-VillabaPalompon Rd - K1015+818K1006+000,k1016+000 -K1016+530, K1016+676 -K1017 000,K1027+000a) a) k1028+000,K1029+100K1029+900,K1030+000K1031+000,K1031+000K1031+300,K1033+7-- - K1034+479 PAVED Leyte 3rd District Engineering Office, Region b) VIII c) c) Leyte 3rd District 080214H00224 Sn Isidro-Daja Rd K1018+(-497) K1018+(-427),K1018+959 a) a) K1019+403,K1024+083 K1025+047,K1025+573 K1026+138 GRAVEL TO PAVED b) Regional Office, Region VIII b) c) San Isidro, Leyte 3rd District c)

b)

080214H00236 Tabango-Catmon-La Fortuna- Manlawaana) Gimarco Rd K1033+242 - K1039+287.56 GRAVEL TO PAVED b) DPWH Region VIII/Leyte 3rd DEO c) Leyte 3rd District

1/30/2014

7/27/2014

a)

b) c)

1/30/2014

a)

50,750.00

9/23/2014

b)

45,334.29

project's schedule expired

.

c)

a)

2/28/2014

a)

b)

11/4/2014

b)

c)

project's schedule expired

149,510.00

149,510.00

100

c)

080215F0001

Page 17 of 26

project schedule expired

a)

SCHEDULE

Project Name/Title/Scope

a) Start Date

Implementing Agency c) Location

b)

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Construction of Drainage Lines along PaloCarigara-Ormoc Road CONSTRUCTION b) DPWH-Leyte 4th DEO a) c)

a)

2/5/2015

a)

b)

9/6/2015

b)

c)

Leyte 4th District

089913F00002 Ormoc Flood Mitigation Project, a) CONSTRUCTION (along Malbasag Anilao River), Ormoc City b) DPWH-Regional Office, Region VIII

a) Prog. Amount

and

a)

Revised (C.A.) 37,000.00

2/27/2013

a)

100,000.00 84,524.26

9/14/2013

b)

5/12/2014

c)

089913H00002 Construction/Rehab/Improvement of Libungao-Matag-ob-Palompon Road a) (Libungao-Matag-ob-Palompon Section), K1007+942.81 K1015+047.26, w/ exceptions b) DPWH-Regional office VIII

a)

2/21/2013

a)

150,000.00

b)

1/5/2014

b)

144,749.78

c)

c)

3/7/2014

c)

a)

2/27/2013

a)

150,000.00 140,947.82

Leyte 4th District

08913H00004 Construction of Ormoc Diversion Road, including bridges & ROW , a) Sta. 0+000 - Sta. 11+672.86, w/ exceptions GRAVEL TO PAVED b) DPWH-Regional Office VIII

b)

12/23/2013

b)

c)

c)

12/19/2014

c)

a)

3/11/2013

a)

100,000.00

b)

11/15/2013

b)

91,699.50

c)

6/13/2014

c)

a)

2/29/2012

a)

100,000.00 88,252.10

Ormoc City, Leyte 4th District

Unpaid Obligation

Rate (%)

Total

Disbursement -

Expenditure

37,000.00

100

-

-

100,000.00

100

71,942.89

12,581.37

84,524.26

150,000.00

100

86,565.10

58,184.68

144,749.78

150,000.00

100

113,776.82

27,171.00

Target

Actual

Slippage

Performance

25.70

36.85

11.15

143.39

99.49

80.00

-19.49

80.41

93.82

76.27

-17.55

81.29

93.97

83.85

75.00

-8.85

89.45

60.00

-40.00

60.00

(8.04)

91.80

-9.92

71.82

Employment Generated (Man-Days)

Remarks project ongoing

31,657.60

b)

Ormoc City, Leyte 4th District

AA Issued To Date

PHYSICAL (%)

EXPENDITURE

c)

c)

c)

FINANCIAL (P'000)

Funding Support (%)

140,947.82

84.52

38.79

project's schedule expired

project's schedule expired

project's schedule expired

08913H00007 Upgrading of Burauen-Albuera Road, a) Sta.0+698.90 - Sta.5+350, with exception, Albuera Side, ROAD OPENING, CONCRETE b) DPWH-Regional office VIII c) Albuera, Leyte 4th District

100,000.00

100

100,000.00

100

47,187.00

100

91,699.50

23,437

115,137.00

115.14

100.00

19,416.00

107,668.10

107.67

98.04

6,187.50

6,187.50

13.11

35.20

08912H00010 Construction of Ormoc Diversion a) Road Sta. 5+000 - Sta. 11+672.86, w/ exceptions GRAVEL TO PAVED b) DPWH Region VIII

b)

1/23/2013

b)

c)

c)

11/18/2014

c)

a)

1/28/2013

a)

b) DPWH-Leyte 4th DEO

b)

7/25/2013

c)

c)

Ormoc City, Leyte 4th District

88,252.10

90.00

project's schedule expired

project's revised schedule expired

080213H00036 a)

Merida-Lundag-Puting BatoConsolation-Isabel Road, K1114+000-K1115+550, GRAVEL TO PAVED Leyte 4th District

b)

47,187.00 41,250.30

c)

080414H00037

Page 18 of 26

25.28

project's schedule expired

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Mawo Bridge along Daang Maharlika (SM) (San Isidro-San Juanico Bridge a) RETROFITTING/REHABILITATION/ STRENGTRHENING b) DPWH Region VIII

a)

10/21/2014

b)

9/4/2015

c)

c)

Leyte 4th District

a) Prog. Amount

a) b)

Revised (C.A.) 148,126.20

1/28/2013

a)

34,620.00

b)

7/20/2013

b)

30,615.00

c)

c)

c)

Albuera, Leyte 4th District

Rate (%)

Total

Disbursement

100

Target

Actual

Slippage

Performance

28.94

10.58

-18.36

36.56

13.26

36.21

26.32

-9.89

72.69

12.91

24.23

25.15

0.92

103.80

100.00

85.94

-14.06

85.94

100.00

74.75

-25.25

74.75

35.50

15.00

-20.50

28.95

36

7.05

Employment Generated (Man-Days)

Remarks project behind schedule

34,620.00

100

40,380.00

100

100,000.00

100

72,000.00

100

72,000.00

100

38,742.00

100

4,592.30

4,592.30

project's schedule expired

c)

a)

1/28/2013

a)

40,380.00

b)

10/14/2013

b)

34,744.80

c)

080214H00105 Road Opening/Upgrading of Burauen-Albuera Road, including bridges, a) a) Albuera Side (Sta. 3+461.90 - Sta. 13+700 with Exceptions) b) b) DPWH Regional Office/Leyte 4th DEO

148,126.20

Unpaid Obligation

Expenditure

129,520.00

a)

080213H00102 Merida-Lundag-Puting BatoConsolation-Isabel Road, a) K1109+059-K1110+000, K110+057-K1111+(-389), GRAVEL TO PAVED b) DPWH-Leyte 4th DEO c) Leyte 4th District

AA Issued To Date

PHYSICAL (%)

EXPENDITURE

c)

080213H00045 Merida-Lundag-Puting BatoConsolation-Isabel Road, a) K1121+162 - K1122+255, GRAVEL TO PAVED b) DPWH-Leyte 4th DEO Leyte 4th District

FINANCIAL (P'000)

Funding Support (%)

5,211.70

5,211.70

project's schedule expired

c)

4/18/2014

a)

100,000.00

12/13/2014

b)

89,780.85

c)

76,633.72

13,147.13

89,780.85

89.78

project's schedule expired

c)

080215H00115 Road Opening/Upgrading of Burauena) Albuera Road including Bridges, Leyte Albuera Side

a)

4/18/2014

a)

b) DPWH-Leyte 4th DEO

b)

11/3/2014

b)

c)

c)

2/8/2015

c)

a)

4/21/2014

a)

72,000.00

b) DPWH-Regional office VIII

b)

11/6/2014

b)

61,165.10

c)

c)

Leyte 4th District

72,000.00

-

-

-

56,872.70

project's schedule expired

080214H00115 a)

Road Opening/Upgrading of Burauen-Albuera Road including Bridges, Albuera Side, Bridges ROAD OPENING, CONCRETE Albuera, Leyte 4th District 080215H00171

Palo-Carigara-Ormoc Road - K0990+416, a) K1005+(-296) - K1005+801.84 WIDENING - a) PAVED b) DPWH-Leyte 4th DEO b) c)

Leyte 4th District

c)

-

-

-

project's schedule expired

c)

2/5/2015

a)

8/13/2015

b)

38,742.00 33,254.90

c)

080212H00214

Page 19 of 26

-

-

-

124.35

project ongoing

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

a) Prog. Amount

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Construction/Rehab/Improvement of a) Libungao-Matag-ob-Palompon Road a) K1015+047.26 - K1020+600, w/ exceptions)

11/26/2012

a)

Revised (C.A.) 100,000.00

b) DPWH Region VIII

b)

9/1/2013

b)

c)

c)

9/21/2014

c)

a)

3/14/2014

a)

61,965.47

58,557.34

Leyte 4th District

AA Issued To Date

100,000.00

PHYSICAL (%)

EXPENDITURE

Unpaid Obligation

Disbursement

100

35,517.54

59,998.37

Expenditure

Rate (%)

Total 95,515.91

Target

Actual

Slippage

Performance

95.52

100.00

90.00

-10.00

90.00

94.50

100.00

97

-3.00

97.00

91.78

100

95.00

-5.00

95.00

Employment Generated (Man-Days)

Remarks

project's schedule expired

95,515.91

080214H00215 Merida-Lundag-Puting Bato- ConsolationIsabel Road, K1111+315 - K1111+660; K1112+271 - K1112+419; K11187+290a) K1118+543; K1120+000-K1121+117; & K1112+419-K1112+719, GRAVEL TO PAVED b) DPWH-Leyte 4th DEO

b)

11/5/2014

b)

c)

c)

12/26/2014

c)

a)

9/17/2013

a)

100,000.00

b)

4/14/2014

b)

95,777.10

c)

3/10/2015

c)

a)

1/14/2014

a)

150,000.00

b) c)

11/27/14 7/25/2015

b) c)

145,459.00

a)

4/2/2014

a)

30,000.00

b) c)

9/23/2014 6/10/2015

b) c)

26,766.20

a)

2/13/2015

a)

b)

7/12/2015

b)

Leyte 4th District

FINANCIAL (P'000)

Funding Support (%)

61,965.47

100

100,000.00

100

27,855.90

30,701.45

58,557.34

project's schedule expired

080212H00377 Improvement/Upgrading of a) Libungao-Matag-ob-Palompon Road (K0990+961-K1024+688,with exceptions) b) DPWH Region VIII c) Leyte 4th District 080212H00519 a) Construction of Ormoc Diversion Road Including Bridges & ROW, Ormoc City PAVED (CONCRETE) TO PAVED (CONCRETE) b) DPWH Region VIII c) Ormoc City, Leyte 4th District 080214G00002 Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure a) including Local Projects - Construction of City Library, Baybay City CONSTRUCTION b) DPWH-Region VIII/Leyte 5th DE0 c) Baybay City 080215H00008 Panilahan Bridge (B00571LT along OrmocBaybay-Southern Leyte Boundary Road b) DPWH Region VIII/5th DEO a)

c)

Baybay City, Leyte 080215H00038 Daang Maharlika (LT) - K0981+200 K0982+000, K1002+830 - K1002+930 a) OTHER IMPROVEMENT WORKS (SLOPE PROTECTION, DRAINAGE, SIDEWALKS) b) DPWH-Region VIII/Leyte 5th DE0 c) Leyte 5th District

c)

57,000.00

91,780.30

91,780.30

project's revised schedule expired

150,000.00

100

53.5

2.88

-50.62

5.38

30,000.00

100

68.43

68.43

0.00

100.00

project ongoing

2.00

-3

40.00

project ongoing

2.15

116.73

project ongoing

57,000.00

100

-

-

-

5.00

40,000.00

100

-

-

-

12.85

project ongoing

53,518.70

c)

a)

3/9/2015

a)

b) c)

9/3/2015

b) c)

40,000.00 35,057.30

080215H00123

Page 20 of 26

15

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Tacloban -Baybay South Road - K0986+050 K0986+200, K0986+580 - K0986+730, K0987+000 - K0987+150, K0988+000 K0988+100, K0989+000 - K0989+200, a) K0993+700 - K0993+800, K0994+700 a) K0994+800, K0996+400- K0997+000, K0999+000- K0999+150, K1000+000 K1000+200 OTHER IMPRVT. WORKS (SLOPE PROTECTION, DRAINAGE, SIDEWALKS) b) DPWH-Region VIII/Leyte 5th DE0 b) c) Leyte 5th District c) 080215H00125 Ormoc -Baybay- Southern Leyte Bdry. Road - K1049+000 - K1049180, K1061+800 K1082+400, K1064+800 - K1065+400, K1067+200 - K1067+500, K1070+500 a) a) K1071+350, K1085+050 - K1085+250 OTHER IMPRVT. WORKS (SLOPE PROTECTION, DRAINAGE, SIDEWALKS) b) DPWH-Region VIII/Leyte 5th DE0 c) Leyte 5th District

a) Prog. Amount Revised (C.A.)

FINANCIAL (P'000)

AA Issued To Date

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE

Expenditure

Rate (%)

Total

Disbursement

Target

Actual

Slippage

Performance

Employment Generated (Man-Days)

Remarks

37,500.00

100

-

-

-

6.70

10

3.30

149.25

project ongoing

29,000.00

100

-

-

-

14.38

30

15.62

208.62

project ongoing

30,000.00

30,000.00

100

100

48.00

-52.00

48.00

150,000.00

100

97.56

95.00

-2.56

97.38

project ongoing

95,744.00

100

100

96.20

-3.80

96.20

project ongoing

3/20/2015

a)

37,500.00

9/14/2015

b) c)

3/9/2015

a)

b) c)

8/15/2015

b) c)

26,368.80

a)

 5/21/2014

a)

b)

 11/11/2014

31,127.10

29,000.00

080214H00153 a) Construction of Junction Abuyog-Silago

Road-Cadac-an-Malaguicay Road Section (Malaguicay Falls), Abuyog, Leyte 5th LD GRAVEL TO PAVED/Abuyog

b) Leyte 5th DEO, Region VIII c) Abuyog, Leyte

c)

project's schedule expired

c)

080214H00235 Construction/Upgrading of Baybay City a) Diversion Road, including Bridges and ROW b) b) DPWH-Region VIII/Leyte 5th DE0 c) c) Baybay City 080214H00258

5/20/2014

a)

150,000.00

4/2/2015 6/23/2015

b) c)

144,746.30

Palo-Carigara-Ormoc Road K0957+100 a) K0957+360, K0967+000 -K0987+764.8, K0967+753 -K0979+000 PAVED TO PAVED

a)

2/24/2014

a)

95,744.00

b) DPWH-Region VIII c) Palo to Carigara to Ormoc Road

b) c)

10/18/2014 6/20/2015

b) c)

80,967.70

a)

88,849.72

Biliran Circumferential Road 080613H0003

Page 21 of 26

45,476.22

134,325.94

89.55

a)

Project Name/Title/Scope

Implementing Agency c) Location

b) a)

b) c)

a) b) c) a) b) c)

Biliran Circumferential Rd, K1073+760 K1074+640, GRAVEL TO PAVED DPWH-Biliran DEO Biliran 08114H0003 Biliran Circumferential Road, Biliran Lone District - K1110+000 - K1116+000, Sangalang-Biliran Section CONCRETING OF SHOULDER DPWH-Biliran DEO Biliran 08514H00012 Biliran Circumferential Rd, K1089+100K1096+640, GRAVEL TO PAVED DPWH-Biliran DEO Biliran

08114H00013 Widening of Biliran Circumferential Road, a) Biliran Lone District, K1026+330 K1027+830, Naval- Almeria Section WIDENING - PAVED b) Biliran DEO, VIII c) Biliran 08114H00015 Widening of Biliran Circumferential Road, Biliran Lone District, K1067+300 a) K1027+830, Naval-Almeria Section WIDENING -PAVED b) Biliran DEO, VIII c) Biliran 080114H00019

SCHEDULE

a) Start Date

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Revised (C.A.)

a)

2/7/2013

b)

22,000.00

b) c)

7/7/2013

b) c)

20,088.90

a)

3/3/2014

a)

b) c)

9/30/2014

b) c)

a)

2/7/2013

a)

b)

6/7/2013

b)

a)

3/7/2014

a)

b)

8/13/2014

b)

c)

FINANCIAL (P'000)

AA Issued To Date

Funding Support (%)

22,000.00

100

23,860.00

23,860.00

100

45,450.00

45,450.00

100

45,750.00

100

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement 3,013.30

17,499.20

Expenditure

Total 3,013.30

17,499.20

Rate (%)

13.7

36.81

Target

Actual

Slippage

Performance

15.00

30.00

15.00

200.00

100

45

-55.00

45.00

100

40.00

-60.00

40.00

100

40.00

-60.00

40.00

43,665.40

45,750.00

Employment Generated (Man-Days)

Remarks project's schedule expired

project's schedule expired

project's schedule expired

project's schedule expired

c)

a)

2/6/2014

b)

8/4/2014

a)

313,450.00

313,450.00

100

100

40.00

-60.00

40.00

c)

Construction/Improvement of Access Roads a) a) Leading to Declared Tourist Destination (Higatangan Circumferential Road) b) Biliran DEO c) Biliran Province

a) Prog. Amount

5/9/2014

a)

100,000.00

b) c)

12/31/2014

b) c)

a)

2/16'2015

a)

84,393.00

b)

9/23/2015

b)

75,478.00

project's schedule expired

Recommended for termination of contract. Letter to contractor dated 10 July 2014 inform that project incurred (-) 15% slippage. No reply was received to date.

100,000.00

100

100

5.00

-95.00

5.00

84,394.00

100

2.39

2.39

0.00

100

Project ongoing

100

20.00

22.00

2.00

110.00

project ongoing

92,197.78

080115H00023

Naval-Caibiran Cross Country Rd a) K1030+600 - K1035+286 WIDENING PAVED b) DPWH Region VIII c)

Biliran 080115H00030 Biliran Circumferential Rd, a) K1027+943 - K1029+300, WIDENINGPAVED b) DPWH-Biliran DEO c) Biliran

c)

c)

a)

2/6/2015

b)

47,075.00

b) c)

10/3/2015

b) c)

42,732.10

47,075.00

Southern Leyte Road Projects 0803-15-F-00001

Page 22 of 26

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

a) Prog. Amount

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Revised (C.A.)

Construction/Repair/Rehabilitation/ Improvement of Various Infrastructure a) including Local Projects - Fabrication of a) Concrete Breaker (Maasin City National High School) (CONSTRUCTION)

2/6/2015

a)

30,000.00

b) DPWH Region VIII/Southern Leyte DEO

b)

7/26/2015

b)

c)

c)

27,102.70

Southern Leyte

c)

FINANCIAL (P'000)

AA Issued To Date

30,000.00

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

Target

100

5.00

100

100

Actual

2.00

Slippage

Performance

-3.00

40.00

-38.00

62.00

Employment Generated (Man-Days)

Remarks

project ongoing

080314H00008 a) b) c)

Limasawa Circumferential Road, Limasawa, a) Southern Leyte -GRAVEL TO PAVED Southern Leyte District Engineering Office, Region VIII Limasawa, Southern Leyte

080315H00008 Panilahan Br. (B00571LT) along OrmocBaybay-Southern Leyte Bdry Rd a) RETROFITTING/REHABILITATION/ STRENGTHENING

b)

4/15/2014 10/10/2014

c)

a)

62.00

b)

project's schedule expired

project ongoing

57,000.00

57,001.00

100

100

2.00

-98.00

2.00

37,900.00

37,900.00

100

100

100

0

100

project completed

a)

88,000.00

88,000.00

100

100

100

0

100

b)

81,754.74

project completed

45,990.00

100

75.00

75.00

0.00

100.00

project ongoing

47,310.00

100

55.00

53.00

-2.00

96.36

project ongoing

2/13/2015

a)

b) DPWH Region VIII

b)

7/12/2015

b)

c)

c)

c)

a)

2/14/2014

a)

b)

8/11/2014

b)

c)

080314H000018 Road leading to Danao Camp Tree Park, a) Maasin City, Southern Leyte GRAVEL TO a) PAVED b) Regional Office, Region VIII b) c) Maasin City, Southern Leyte c)

32,000.00

c)

a)

Southern Leyte 080314H00017 Sn Ricardo-Bilatan Rd - K1101+000 a) K1102+000 GRAVEL TO PAVED b) DPWH Region VIII/Southern Leyte DEO c) San Ricardo, Southern Leyte

32,000.00

c)

4/14/2014 11/19/2014

8,175.97

73,578.76

81,754.74

92.90

c)

080313F00018 Construction/Rehabilitation of Flood Control Structures: Dasay Flood Control (Phase II) a) a) along Jct. Himay-angan-SilagoAbuyog Road CONSTRUCTION b) DPWH Region VIII/Southern Leyte DEO c) Hinunangan, Southern Leyte

9/6/2014

a)

45,990.00

b)

3/18/2015

b)

42,072.50

c)

4/17/2015

c)

10/1/2014

a)

47,310.00

3/27/2015

b)

43,278.30

4/26/2015

c)

080313F00019 Construction/Rehabilitation of Flood Control Structures: Canturing Flood Control (Phase a) a) II) along Bdry. Southern Leyte-MaasinMacrohon Road CONSTRUCTION b) b) DPWH Region VIII/Southern Leyte DEO c)

Maasin City, Southern Leyte

c)

080312H00033

Page 23 of 26

a)

SCHEDULE

Project Name/Title/Scope

a) Start Date

Implementing Agency c) Location

b)

a) Prog. Amount

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Construction of Bil-atan Bridge and a) Approaches, Sann Ricardo, So. Leyte GRAVEL TO PAVED

a)

10/25/2012

a)

b) DPWH Regional Office, Region VIII

b)

3/10/2014

b)

c)

c)

Southern Leyte

a)

10/25/2012

a)

b)

3/10/2014

b)

c)

c)

Const.of Lawaan Bridge and a) approaches, Silago, So. Leyte TO PAVED b) Regional Office, Region VIII c)

Const. Of Hibatian Bridge and a) approaches, Silago so. Leyte TO PAVED

10/25/2012

b)

3/10/2014

c)

10/25/2012

b)

3/10/2014

c)

0803-14-H-00040 Local Infrastructure Program a) Construction of Road Hinunangan to St. a) Bernard, So. Leyte GRAVEL TO PAVED b) DPWH Region VIII/Southern Leyte DEO c) Southern Leyte

a)

a)

Slippage

Performance

30,207.00

30,207.00

100

100

72.47

-27.53

72.47

21,153.00

21,153.00

100

100

78.11

-21.89

78.11

100

100

74.18

-25.82

74.18

100

100

77.63

-22.37

77.63

100

59.75

58

-1.75

97.07

100

100

51

-49.00

51.00

100

85

85

0

100.00

32,685.00

17,504

32,685.00

17,504

b)

10/27/2014

a)

24,500.00

b)

4/23/2015

b)

c)

5/23/2015

c)

22,620.10

2/14/2014

a)

b)

10/11/2014

b)

c)

c)

20,000.00

Employment Generated (Man-Days)

Remarks

project's schedule expired

project's schedule expired

project's schedule expired

project's schedule expired

24,500.00

20,000.00

project substantially completed

project's schedule expired

c)

a)

10/14/2014

a)

36,912.00

b)

4/23/2015

b)

33,233.20

c)

Actual

c)

a)

0803-14-H-00046 Repair/rehabilitation of Liloan Steel Bridge, K-1054+508 - K1054+806 along Daang a) Maharlika (Bdry. Mahaplag-Sogod-LibagonLiloan Road) RETROFITTING/ REHABILITATION/STRENGTHENING b) DPWH Region VIII/Southern Leyte DEO c) Maasin City, So. Leyte

Total

Target

b)

08314H00041 Improvement/Widening of Acess Road a) leading to Benit Port (Saddle Area), San Ricardo WIDENING - PAVED b) DPWH Region VIII/Southern Leyte DEO San Ricardo, Southern Leyte

Disbursement

Rate (%)

c)

GRAVEL a)

b) DPWH Regional Office, Region VIII c) Southern Leyte

Unpaid Obligation

Expenditure

c)

GRAVEL a)

Southern Leyte 080312H00036

AA Issued To Date

PHYSICAL (%)

EXPENDITURE

c)

080312H00034 Const. Of Barangay Bridge and a) approaches, Silage, So. Leyte GRAVEL TO PAVED b) DPWH Regional Office, Region VIII Southern Leyte 080312H00035

Revised (C.A.)

FINANCIAL (P'000)

Funding Support (%)

c)

36,912.00

0803-14-H-00048

Page 24 of 26

project ongoing

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

SCHEDULE

a) Start Date

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

Ma. Clara-Cagnituan Road leading to Maasin City Tourism Loop (Monte Cueva, Danao a) Camp Tree Park, St. Francis Javier Shrine, a) Maasin City Zoo Theme Park, Maasin City GRAVEL TO PAVED b) DPWH Region VIII b) c)

Maasin City, So. Leyte

a) Prog. Amount Revised (C.A.)

3/30/2015

a)

85,000.00

11/14/2015

b)

82,015.30

c)

c)

080312H00061 Construction of Pinut-an Bridge and a) Approaches, Southern Leyte CONSTRUCTION OF NEW BRIDGE b) DPWH Region VIII

a)

10/25/2012

a)

32,524.00

b)

3/10/2014

b)

32,524.00

c)

c)

7/13/2014

c)

a)

3/23/2015

a)

b) c)

9/17/2015

b) c)

a)

2/25/2015

a)

b) c)

8/15/2015

b) c)

45,099.10

a)

3/2/2015

a)

150,000.00

b) c)

11/25/2015

b) c)

a)

3/23/2015

a)

b) c)

9/17/2015

b) c)

43,855.40

a)

2/6/2015

a)

142,810.00

b) c)

11/1/2015

b) c)

Southern Leyte

FINANCIAL (P'000)

AA Issued To Date

Funding Support (%)

85,000.00

100

32,524.00

100

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE

Expenditure

Rate (%)

Total

Disbursement

32,524.00

32,524.00

100.00

Target

Actual

Slippage

Performance

0.87

21

20.13

2413.79

100

43.33

-56.67

43.33

Employment Generated (Man-Days)

Remarks

project ongoing

project's revised schedule expired

Other Roads of Strategic Importance Tacloban City a) b) c)

a)

b) c)

a) b) c) a) b) c)

a)

080215H00007 Daang Maharlika (LT) (S00002LT) K0904+342 -K0905 +200 WIDENING PAVED DPWH-Tacloban City DEO Tacloban City 080215H00017 La Paz-Javier-Bito Rd. -Chainage 2558 Chainage 2848, Chainage 2900 -Chainage 3095, Chainage 3649 -Chainage 3807, Chainage 4105 - Chainage 4522, Chainage 4602 -Chainage 5625, Chainage 5923Chainage 6315 GRAVEL TO PAVED DPWH-Tacloban City DEO Tacloban City 080215H00115 Construction of Palo West By-Pass Road, including Bridge, Pawing-CampeticGuindapunan-San Jose-Arado, Palo GRAVEL TO PAVED DPWH Region VIII Palo, Leyte 080215H00126 Daang Maharlika (LT) (S00022LT) K0908+130 -K0909 + 111 WIDENING PAVED DPWH-Tacloban City DEO Tacloban City 080215H00145 Construction of Tacloban City By-Pass Road, (Including ROW), Sta. 3+400 - Sta. 6+400, Brgy. Caiubaan, Tacloban City - GRAVEL TO PAVED

b) DPWH Region VIII c) Tacloban City

32,594.00

32,594.00

100

-

-

-

7.00

22

15.00

314.29

project ongoing

50,000.00

100

-

-

-

10.00

30

20.00

300.00

project ongoing

-

-

-

0.55

0.91

0.36

165.45

project ongoing

29,650.10

50,000.00

150,000.00

144,822.70

48,000.00

48,000.00

100

-

-

-

7.00

22

15.00

314.29

project ongoing

142,810.00

100

-

-

-

0.56

5.02

4.46

896.43

project ongoing

126,052.00

080214H00159

Page 25 of 26

a)

Project Name/Title/Scope

Implementing Agency c) Location

b)

a) Tigbao-Bridge along Daang Maharlika (LT) RETROFITTING/ REHABILITATION/ STRENGTHENING b) DPWH Region VIII, Tacloban City DEO c) Tacloban City DE

SCHEDULE

a) Start Date

b) Completion Date b) Contract Amount c) Rev.Comp. Date c)

b) DPWH Region VIII, Tacloban City DEO c) Tacloban City

2/27/2015

a)

40,000.00

b)

9/9/2015

b)

40,000.00

c)

a)

a)

a)

AA Issued To Date 40,000.00

Unpaid Obligation

100

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

Target 8.00

Actual 15.10

Slippage 7.10

Performance 188.75

Employment Generated (Man-Days)

Remarks project ongoing

29,000.00

29,000.00

100

0.00

#DIV/0!

project ongoing

b) c)

a)

10/21/2014

a)

48,000.00

b)

4/17/2015

b)

44,028.40

c)

Widening of Picas-San Jose DZR Airport Road, Tacloban City, Leyte 1st LD , K0910+(a) 1664) - K0910+ 157.92, K0911+702.74 K0912+050.04 WIDENING - PAVED

a)

b) DPWH Region VIII, Tacloban City DEO c) Tacloban City

FINANCIAL (P'000)

Funding Support (%)

c)

c)

080214H00229

Revised (C.A.)

a)

080214H00180 Widening along Apitong-Paterno Road, K0908+(-922) - K0909+442, system, a) a) Tacloban City, Leyte 1st LD WIDENING PAVED b) DPWH/Tacloban City DEO b) c) Tacloban City c) 080214H00225 a) Widening of Tacloban-Baybay South Road, K0911+515 (S00025LT), K0913+053 K0913+505 (S00027LT),K0915+(267) K0915+243 (S00020LT) WIDENING -PAVED

a) Prog. Amount

b) c)

45,000

48,000.00

45,000

100

70.00

60.00

100

-10.00

0.00

85.71

#DIV/0!

project's schedule expired

project ongoing

b) c)

080214H00234 Tigbao-Sta. Fe-San Miguel Road - K909+(-172) a) - K0909+(-103), K0907+375 - K0907+455, K0908+258 - K0908+933 - GRAVEL TO PAVED

b) DPWH Region VIII, Tacloban City DEO c) Tacloban City DE

080214H00243

b)

a)

42,400.00

6/25/2015

b)

37,558.20

c)

Reconstruction of Burayan Bridge (B00026LT) along Picas-San Jose DZR a) Airport Road, Tacloban City OTHER a) IMPVT WORKS(SLOPE PROTECTION, DRAINAIGE, SIDEWALKS) b) Regional Office, Region VIII b) c) Tacloban City c) 080213H00284 Rehabilitation/Improvement along Magsaysay Boulevard, K0909+124a) a) K0910+(-343), Tacloban City GRAVEL TO PAVED b) b) Tacloban City DEO c) c) Tacloban City

Source: DPWH Region VIII

12/29/2014

100

40.00

55.00

15.00

137.50

project ongoing

56,750.00

100

100

97.23

-2.77

97.23

project substantially completed

35,635.00

100

100

-75.00

25.00

42,400.00

c)

6/12/2014

a)

56,750.00

11/8/2014

b) c)

46,539.70

6/17/2013

a)

35,635.00

11/7/2013 1/6/2014

b) c)

Page 26 of 26

25.00

project's schedule expired

PMC Form O-2 FINANCIAL AND PHYSICAL STATUS OF CAPITAL INVESTMENT PROGRAMS/PROJECTS As of April 15, 2015 a)

Project Name/Title/Scope

Implementing Agency c) Location b)

SCHEDULE a) Start Date

FINANCIAL (P'000) a) Prog. Amount

b) Completion Date b) Contract Amount c)

Rev.Comp. Date c)

AA Issued To Date

Revised (C.A.)

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

PerTarget Actual Slippage formanc e

Employment Generated (Man-Days)

Remarks

Help for Catubig Agricultural Advancement Project HCAAPD-C-1 Construction of Hagbay Diversion Dam and Appurtenant Structures a) a) including Supply, Delivery and Stockpilling

7/2/2010 a)

231,888.88

1/21/2013 b) 5/15/2013 c) 5/13/2014

231,888.88

c)

Construction of the remaining works of Bulao Diversion Dam a) and Appurtenant Structures including Supply, Delivery and Installation of Steel Gates

a)

9/9/2011 a)

172,723.00

b) NIA-HCAAP-PMO

b)

1/29/2014 b) 9/14/2014 c)

172,723.00

10/31/2012 a)

66,120.80

66,120.80

b) NIA-HCAAP-PMO

c) Las Navas, N. Samar 2nd District

b)

Just resumed. Contractor 65.49 requested for time extension due to variation which is under evaluation

231,888.88

100

29,800.64

29,800.64

12.85

90.14

59.03 -31.11

172,723.00

100

81,092.89

81,092.89

46.95

77.54

46.95 -30.59

66,121

100

1,587.36

1,587.36

2.40

80.14

22.15

-57.99

27.64

104,988

100

12,980.39

12,980.39

12.36

34.54

28.5

-6.04

82.51

HCAAPD-C-2

c) Las Navas, N. Samar 2nd District

c)

60.55

Just resumed after suspension

HCAAPD-C-3 Construction of Pinipisakan Siphonic Bridge Flume and a) a) Concrete Lining for Critical Portion of Catubig Right Main Canal b) NIA-HCAAP-PMO

b)

8/12/2014 b)

c) Las Navas, N. Samar 2nd District

c)

12/12/2014 c)

HCAAPD-C-4 Construction of Catubig Right a) Main Canal's Lateral 1, 3, 4 and 5 a) Structures and Creek Improvement

10/31/2012 a)

104,988.06

Page 1 of 7

Just resumed after suspension

ongoing

a)

Project Name/Title/Scope

Implementing Agency c) Location b) NIA-HCAAP-PMO c) Las Navas, N. Samar 2nd District HCAAP-LCB-C2-2012

b)

a)

SCHEDULE a) Start Date

b) Completion Date b) Contract Amount c)

Rev.Comp. Date c)

b)

1/9/2015 b) 5/11/2015 c)

104,988.06

a)

15,995.36

b)

b)

c)

6/30/2014 c)

15,995.36

Construction of On-Farm Facilities a) (Haremasan IA)

a)

17,662.72

b)

b)

c)

8/30/2014 c)

17,662.72

Construction of On-Farm Facilities a) (Robasan IA)

a)

14,249.64

1/20/2013 b) 6/30/2014 c)

14,249.64

a)

22,899.56

5/18/2013 b) 8/31/2014 c)

22,899.56

c)

Construction of On-Farm Facilities a) (Pinipisakan IA)

b) NIA-HCAAP-PMO

c) Las Navas, N. Samar 2nd District

HCAAP-LCB-C3-2012

a)

b) NIA-HCAAP-PMO

c) Las Navas, N. Samar 2nd District

HCAAP-LCB-C4-2012

a)

b) NIA-HCAAP-PMO

c) Las Navas, N. Samar 2nd District

b) c)

HCAAP-LCB-C5-2012

a)

FINANCIAL (P'000) a) Prog. Amount

Construction of On-Farm Facilities a) (Saliba IA)

b) NIA-HCAAP-PMO

c) Las Navas, N. Samar 2nd District

b) c)

AA Issued To Date

Revised (C.A.)

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

15,995.36

100

17,662.72

100

12,213.77

12,213.77

69.15

14,249.64

100

7,878.11

7,878.11

22,899.56

100

1,305.57

11,593.04

100

541.45

PerTarget Actual Slippage formanc e

100

100

0

100

91.45

82.28

-9.17

89.97

55.29

64.45

55.29

-9.16

85.79

1,305.57

5.70

55.45

9.99 -45.46

18.02

541.45

4.67

100

71.07 -28.93

71.07

Pinipisakan Irrigation Project (PIP) CY 2013 Pinipisakan IP - CP No. 01-2013

a)

Diversion Road to Catubig Left Main Canal (CLMC) Access Road

a)

11/6/2013 a)

11,593.04 11,593.04

b) NIA-Region VIII

b)

3/6/2014 b)

c) Las Navas, N. Samar 2nd District

c)

7/23/2014 c)

Page 2 of 7

Employment Generated (Man-Days)

Remarks

completed

ongoing

For resumption after suspension due to standing crops

Ongoing. For termination of contract

a)

Project Name/Title/Scope

Implementing Agency c) Location Pinipisakan IP - CP No. 02-2013

b)

SCHEDULE a) Start Date

FINANCIAL (P'000) a) Prog. Amount

b) Completion Date b) Contract Amount c)

Rev.Comp. Date c)

a) Construction of Service Road at

a)

6/26/2013 a)

29,804.85

b) NIA-Region VIII

b) c)

1/22/2014 b) 8/21/2014 c)

29,804.85

a) Construction of Service Road at

a)

11/26/2013 a)

31,030.29

b) NIA-Region VIII

b)

5/14/2014 b)

31,030.29

c) Las Navas, N. Samar 2nd District

c)

8/15/2014 c)

a) Construction of Service Road at

a)

11/8/2013 a)

25,700.46

b) NIA-Region VIII

b) c)

6/6/2014 b) 8/17/2014 c)

25,700.46

a)

7/1/2013 a)

39,342.82

b)

1/27/2014 b) 8/15/2014 c)

39,342.82

c)

a)

7/1/2013 a)

39,980.29 39,980.29

Preparatory Works for CLMC and Sta. 20+000 to Sta. 22+585

c) Las Navas, N. Samar 2nd District

AA Issued To Date

Revised (C.A.)

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

14,955.99

Rate (%)

PerTarget Actual Slippage formanc e

50.18

92.45

Expenditure

Total

29,804.85

100

14,955.99

89.23

31,030.29

100

25,700.46

100

39,342.82

100

39,980.29

100

25.47

22.1

-3.37

86.77

28,306.65

100

60.12

55.78

-4.34

92.78

Employment Generated (Man-Days)

Remarks

-3.2

96.52

100

23.42 -76.58

23.42

92.01

14.59 -77.42

100

51.15 -48.85

15.86 Contracts have just resumed last February 1, 2015. Contractor request for time extensions which is still under evaluation. All contracts are 51.15 ongoing.

Pinipisakan IP - CP No. 03-2013 Preparatory Works for CLMC and Sta. 18+000 to Sta. 20+000

Pinipisakan IP - CP No. 04-2013

Preparatory Works for CLMC and Sta. 15+800 to Sta. 18+000

c) Las Navas, N. Samar 2nd District

Pinipisakan IP - CP No. 05-2013 Preparatory Works for CLMC Lateral 4 and Construction of a) Service Road at Sta. 0+000 to Sta. 4+108 b) NIA-Region VIII c) Las Navas, N. Samar 2nd District Pinipisakan IP - CP No. 06-2013 Preparatory Works for CLMC and

a) Construction of Service Road at

Sta. 13+300 to Sta. 15+400

b) NIA-Region VIII

b)

1/27/2014 b)

c)

c)

a) Construction of Service Road at

a)

7/1/2013 a)

28,306.65

b) NIA-Region VIII

b)

1/27/2014 b)

c)

c)

28,306.65

c) Las Navas, N. Samar 2nd District

6817.38

6817.38

17.33

Pinipisakan IP - CP No. 07-2013

Preparatory Works for CLMC and Sta. 12+000 to Sta. 13+300

c) Las Navas, N. Samar 2nd District

Page 3 of 7

a)

Project Name/Title/Scope

Implementing Agency c) Location Pinipisakan IP - CP No. 08-2013

b)

SCHEDULE a) Start Date

FINANCIAL (P'000) a) Prog. Amount

b) Completion Date b) Contract Amount c)

Rev.Comp. Date c)

a) Lateral 3 & Const of Service Road, a)

11/7/2013 a)

25,734.33

b)

6/5/2014 b)

c)

c)

25,734.33

a) Construction of Service Road at

a)

6/28/2013 a)

37,032.67

b) NIA-Region VIII

b)

1/24/2014 b)

c)

c)

37,032.67

a) Construction of Service Road at

a)

6/28/2013 a)

30,069.46

b) NIA-Region VIII

b)

Preparatory Works for CLMC Sta. 0+000 to Sta. 1+500

b) NIA-Region VIII

c) Las Navas, N. Samar 2nd District

AA Issued To Date

Revised (C.A.)

25,734.33

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

100

PerTarget Actual Slippage formanc e

64.87

20.99 -43.88

Pinipisakan IP - CP No. 09-2013

Preparatory Works for CLMC and Sta. 9+900 to Sta. 12+000

c) Las Navas, N. Samar 2nd District

37,032.67

100

25.47

21.25

-4.22

30,069.46

100

80.78

6.84

-73.94

11,985.93

100

-

-

-

34,880.16

100

-

-

-

-

3.19

0

-3.19

-

2.23

0

-2.23

Pinipisakan IP - CP No. 10-2013

Preparatory Works for CLMC and Sta. 8+600 to Sta. 9+900

c) Las Navas, N. Samar 2nd District

c)

1/24/2014 b) 6/28/2014 c)

30,069.46

a) Hinaga Siphonic Box Culvert

a)

a)

11,985.93

b) NIA-HCAAP-PMO

b)

b)

c) Las Navas, N. Samar 2nd District

c)

c)

11,985.93

a) Hinaga Bridge Flume

a)

11/7/2013 a)

34,880.16

b) NIA-Region VIII

b)

5/6/2014 b)

34,880.16

c) Las Navas, N. Samar 2nd District

c)

c)

Pinipisakan IP - CP No. 11-2013

572.54

572.54

1.90

Employment Generated (Man-Days)

Remarks

32.36

Contracts have just resumed last February 1, 2015. Contractor request 83.43 for time extensions which is still under evaluation. All contracts are ongoing. 8.47

-

No NTP yet

Pinipisakan IP - CP No. 12-2013

Under suspension

Pinipisakan Irrigation Project (PIP) CY 2014

Pinipisakan IP - CP No. 01-2014 Diversion Road to CLMC Access a) Road b) NIA-Region VIII c) Las Navas, N. Samar 2nd District Pinipisakan IP - CP No. 02-2014

a)

a)

b) c)

9/8/2015 b) 10/25/2015 c)

a) Construction of Service Road at

a)

a)

b) NIA-Region VIII

b)

9/18/2015 b)

Preparatory Works for CLMC and Sta. 20+000 to Sta. 22+585

26,778,076.79

26,523,615.02

Page 4 of 7

0.00

Ongoing joint survey at project site. Contractor has initial clearing as preparation for their 0.00 full implementqation

a)

Project Name/Title/Scope

b)

Implementing Agency Location Las Navas, N. Samar 2nd District Pinipisakan IP - CP No. 03-2014 Preparatory Works for CLMC and Construction of Service Road at Sta. 18+000 to Sta. 20+000 NIA-Region VIII Las Navas, N. Samar 2nd District Pinipisakan IP - CP No. 04-2014 Preparatory Works for CLMC and Construction of Service Road at Sta. 18+000 to Sta. 20+000

c)

c)

a) b) c)

a)

SCHEDULE a) Start Date

FINANCIAL (P'000) a) Prog. Amount

b) Completion Date b) Contract Amount c)

Rev.Comp. Date c)

c)

11/4/2015 c)

a)

a)

b) c)

9/8/2015 b) 10/25/2015 c)

a)

a)

b) NIA-Region VIII

b)

9/28/2015 b)

c) Las Navas, N. Samar 2nd District

c)

11/14/2015 c)

AA Issued To Date

Revised (C.A.)

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

PerTarget Actual Slippage formanc e

-

3.19

0

-3.19

0.00

-

2.23

0

-2.23

0.00

-

3.38

0

-3.38

0.00

3.14

0

-3.14

0.00

-

3.38

0

-3.38

0.00

-

2.67

0

-2.67

0.00

26,563,615.02

Employment Generated (Man-Days)

Remarks

Ongoing joint survey at project site. Contractor has initial clearing as preparation for their full implementqation

39,806,149.13

Bulao Irrigation Project (PIP) CY 2014 Bulao IP - CP No. 01-2014

Construction of Bulao Irrigation

a) Subsystem On-Farm Facilities at

a)

a)

b) NIA-Region VIII

b) c)

5/30/2015 b) 7/16/2015 c)

a) Subsystem On-Farm Facilities at

a)

a)

b) NIA-Region VIII

b)

BUNAMAS Service Area - 1

c) Las Navas, N. Samar 2nd District

Bulao IP - CP No. 02-2014

Construction of Bulao Irrigation BUNAMAS Service Area - 1

c) Las Navas, N. Samar 2nd District

c)

7/29/2015 b) 9/14/2015 c)

a)

a)

a)

b) c)

5/29/2015 b) 7/15/2015 c)

a)

a)

b) c)

a)

Bulao IP - CP No. 03-2014 Construction of Bulao Irrigation Subsystem On-Farm Facilities at BUNAMAS Service Area - 2 NIA-HCAAP-PMO Las Navas, N. Samar 2nd District Bulao IP - CP No. 04-2014 Construction of Bulao Supplemental Canal

b) NIA-Region VIII

b)

9/27/2015 b)

c) Las Navas, N. Samar 2nd District

c)

11/13/2015 c)

10,828,857.43

15,828,153.76

10,190,506.15

39,831,764.52

Page 5 of 7

Ongoing joint survey. Ongoing hauling of construction materials at project site

a)

Project Name/Title/Scope

Implementing Agency c) Location b)

SCHEDULE a) Start Date

FINANCIAL (P'000) a) Prog. Amount

b) Completion Date b) Contract Amount c)

Rev.Comp. Date c)

AA Issued To Date

Revised (C.A.)

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

PerTarget Actual Slippage formanc e

Employment Generated (Man-Days)

Remarks

Hagbay Irrigation Project (PIP) CY 2014 Hagbay IP- CP No. 01-2014

Preparatory Works for CLMC and

a) Construction of Service Road at

Sta. 9+900 to Sta. 12+000

b) NIA-Region VIII

c) Las Navas, N. Samar 2nd District

a)

a)

b)

7/25/2015 b) 9/10/2015 c)

c)

Hagbay IP- CP No. 02-2014

Preparatory Works for CLMC and a) Construction of Service Road at Sta. 8+600 to Sta. 9+900

a)

a)

b) NIA-Region VIII

b)

c) Las Navas, N. Samar 2nd District

c)

7/28/2015 b) 9/13/2015 c)

a) Hinaga Siphonic Box Culvert

a)

a)

b) NIA-Region VIII

b)

7/28/2015 b) 9/13/2015 c)

Hagbay IP- CP No. 03-2014

c) Las Navas, N. Samar 2nd District

c)

Hagbay IP- CP No. 04-2014 a) Hinaga Bridge Flume

a)

a)

b) NIA-Region VIII

b)

7/28/2015 b)

c) Las Navas, N. Samar 2nd District

c)

9/13/2015 c)

-

5.17

6.06

0.89

117.21

Ongoing, Bunkhouse completed

14,994,954.63

-

5.17

0

-5.17

-

5.17

15.5

10.33

18,719,696.05

17,388,759.52

-

5.17

17,882,856.60

Page 6 of 7

0

-5.17

Construction of Temporary Facilities 0.00 is at 75% completed. Ongoing joint survey

299.81

Ongoing

Construction of Temporary Facilities 0.00 is at 75% completed. Ongoing joint survey

a)

Project Name/Title/Scope

Implementing Agency c) Location b)

SCHEDULE a) Start Date

FINANCIAL (P'000) a) Prog. Amount

b) Completion Date b) Contract Amount c)

Rev.Comp. Date c)

AA Issued To Date

Revised (C.A.)

Funding Support (%)

Unpaid Obligation

PHYSICAL (%)

EXPENDITURE Disbursement

Expenditure

Total

Rate (%)

PerTarget Actual Slippage formanc e

Employment Generated (Man-Days)

Remarks

OTHER MAJOR IRRIGATION PROJECTS a) Bugko Irrigation Project

a)

a)

b) NIA-Region VIII

b)

b)

c) Mondragon, Northern Samar

c)

c)

a) Bantayan Irrigation Project

a)

a)

b) NIA-Region VIII

b)

b)

c) San Roque, Northern Samar

c)

c)

a) Calbiga Irrigation Project

a)

a)

b) NIA-Region VIII

b)

b)

c) Calbiga, Samar

c)

c)

a) Sta. Rita SRIP

a)

a)

b) NIA-Region VIII

b)

b)

c) Sta. Rita, Samar

c)

c)

a) Hibulangan SRIP

a)

a)

b) NIA-Region VIII

b)

b)

c)

c)

c) Villaba, Leyte

Source: NIA Region VIII

92,150.00

92,150.00

100

98

90.09

-7.91

91.929

138,225.00

138,225.00

100

71.93

80.15

8.22

111.43

156,655.00

156,655.00

100

100

100

0

27,645.00

27,645.00

100

100

95.44

-4.56

92,150.00

92,150.00

100

100

100

Page 7 of 7

0

100

95.44

100

Project still ongoing

Project still ongoing

Project Completed

Project still ongoing

Project completed

RPMES Report 1st Quarter 2015.pdf

K1008+150-K1008+360 Boundary Mahaplag-Liloan, Sogod. Other. Improvement Works (Slope Protection, Drainage, Sidewalks). 4. Construction/Rehabilitation of Flood Control Structures, Subang Daku Flood. Control (Phase II) (Along Boundary Southern Leyte-Maasin-Macrohon Road). Sogod, Southern Leyte.

4MB Sizes 1 Downloads 268 Views

Recommend Documents

RPMES Report 2nd Quarter 2015.pdf
investment cost of PhP 27.222 billion. Projects included in this report were those. funded through Official Development Assistance (ODA), and those funded by ...

3rd Quarter CY 2016 RPMES Digest.pdf
DILG-X to closely monitor and. coordinate with the LGUs concerned. DSWD Delayed implementation of. programs/projects due failure of. bidding/delayed ...

Newsletter - 1st Quarter 2017 - Geocomp
The Los Angeles Regional Connector. Tunnel Boring Machine (TBM), nicknamed “Angeli,” has embarked on its 1.1 mile journey underneath. Los Angeles.

RPMES 3rd Quarter 2016 with Comparative performance-after ...
Infrastructure. 77.70%. Economic. 5.10%. Page 4 of 22. RPMES 3rd Quarter 2016 with Comparative performance-after consultation.pdf. RPMES 3rd Quarter ...

RPMES 3rd Quarter 2016 with Comparative performance-after ...
There was a problem previewing this document. Retrying... Download. Connect more apps... RPMES 3rd Qu ... ultation.pdf. RPMES 3rd Qu ... ultation.pdf. Open.

2017 1st Quarter InService Certification.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. 2017 1st Quarter ...

1st quarter 2014.pages.pdf
a local church; (2) utilizing a community. based health care ministry among the. marginalized and indigenous population. Our UMVIM teams have been great.

2017 | 1st Quarter Report.pdf
Oct 31, 2016 - PGE analysis. ∂ Nickel (QVR) – re-logged two historic diamond drill holes sited. within the embayment feature at the Spargos Prospect and.

1st Quarter Mr. Han Due
What advice did Mrs. Rosen give the girls about behaving outside? 2. What advice ... What were the “booms and lights in the sky” on Kirsti's birthday? Inferential ...

SHHS 1st Quarter Honor Roll.pdf
69 Murphy, Kaytlynn 12. 70 Nelson, Layne 12. 71 Reel, Erica 12. 72 Reifschneider, Lane 12. 73 Robinson, Austin 12. 74 Santor, Jake 12. 75 Urrestta Velez, Laura 12. Page 3 of 3. SHHS 1st Quarter Honor Roll.pdf. SHHS 1st Quarter Honor Roll.pdf. Open. E

final 1st quarter news.pdf
Starblazer Connection. Make the Internet work for you! teacher by visiting our school webpage,. clicking on “Faculty and Staff” and then. clicking the name of any staff member to. access the webpage. LPSS provides lots of resources for parents. t

2017 | 1st Quarter Report.pdf
complete a review of historic Forrestania databases to identify. pegmatites hosting lithium mineralisation adjacent to tenure. held by Kidman ... the historic high grade Blue Haze gold mine. Corporate ... 2017 | 1st Quarter Report.pdf. 2017 | 1st ...

Newsletter – 1st Quarter 2018 - Geocomp
Below is an example comparing the results of a properly prepared sample vs. saw cut ends. 1. Compressive strength measured on six specimens of the same ...

final 1st quarter news.pdf
There was a problem loading this page. Retrying... Whoops! There was a problem loading this page. Retrying... final 1st quarter news.pdf. final 1st quarter news.

RPMES Report 4th Qtr 2014.pdf
Page 1 of 30. Republic of the Philippines. REGIONAL DEVELOPMENT COUNCIL. Eastern Visayas (Region VIII). REGIONAL PROJECT MONITORING ...

(QSR) 1st Quarter, CY 2018 - Defense Suicide Prevention Office
6 days ago - compared to the 1st Quarter of 2017 (23 versus 32 deaths) o Air National Guard deaths are up by 1 o Army National Guard deaths are down by ...

1st Quarter As On 30 Sept 2015.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. 1st Quarter As ...

ACADEMICGOALWORKSHEET – G r 10 1st Quarter ...
WHAT DO YOU WANT TO ACHIEVE THIS YEAR? You've completed one year of high school but you might be finding your courses challenging. How are you ...

2016-2017 1st Quarter - Statutory Bodies Financial Report.pdf ...
2016-2017 1st Quarter - Statutory Bodies Financial Report.pdf. 2016-2017 1st Quarter - Statutory Bodies Financial Report.pdf. Open. Extract. Open with. Sign In.

2011-2012 1st Quarter Review - Science.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. 2011-2012 1st ...

1st Report, 2017.pdf
May 25, 2017 - Conclusions____________________________________________________________4. Annex A. Justice Sub-Committee on Policing. Report on governance of the Scottish Police Authority, 1st Report, 2017 (Session 5). Page 3 of 15. 1st Report, 2017.p