Republic of the Philippines REGIONAL DEVELOPMENT COUNCIL Eastern Visayas (Region VIII) REGIONAL PROJECT MONITORING COMMITTEE VIII 4th Quarter CY 2014 Field Monitoring Report Monitoring Visit For Projects in the Provinces of Biliran and Southern Leyte 15-16 December 2014

The Regional Project Monitoring Committee (RPMC) VIII conducted field monitoring visits on 15 – 16 December 2014 on the following projects: 1. Five (5) Bridges under the Spain-assisted Bridge Construction/Replacement Project implemented by the Department of Public Works and Highways (DPWH), to wit: a. Bagacay Bridge in Silago, Southern Leyte b. Lawaan Bridge in Silago, Southern Leyte c. Hibatian Bridge inSilago, Southern Leyte d. Pinut-an Bridge in San Ricardo, Leyte e. Bila-atan Bridge, San Ricardo, Leyte 2. San Ricardo-Bilatan Road - K1101+000 – K1102+000 GRAVEL TO PAVED/Districtwide, Southern Leyte District Engineering Office, Region VIII 3. Improvement/Widening of Access Road leading to Benit Port (Saddle Area), San Ricardo, Southern Leyte WIDENING – PAVED/San Ricardo, Southern Leyte District Engineering Office 4. Widening of Biliran Circumferential Road, Biliran Lone District, K1026+330 - K1027+830, Naval-Almeria Section WIDENING – PAVED 5. Biliran Circumferential Road, Biliran Lone District - K1110+000 - K1116+000, Sangalang-Biliran Section CONCRETING OF SHOULDER 6. Biliran Circumferential Road, Biliran Lone District - K1018+000 - K1023+000, Catmon-Caraycaray Section CONCRETING OF SHOULDER 7. Widening of Biliran Circumferential Road, Biliran Lone District, K1067+300 - K1068+300, Virginia-Culaba Proper WIDENING – PAVED. The monitoring team that visited Southern Leyte were Eng. Art Bulic of the Department of the Interior and Local Government (DILG) VIII, Mr. Romeo Ang of the Department of Budget Management (DBM) VIII, and Mr. Ramon Hidalgo of the National Economic and Development Authority (NEDA) VIII. The monitoring team that visited Biliran were Engr. Laurence Alonzo of DILG VIII, Ms. Lorna Cinco of the Presidential Management Staff (PMS), and Mr. Marlon Dumagsa of NEDA VIII.

1

I.

Spain-assisted Bridge Construction/Replacement Project Five (5) of the ten (10) bridges under the Spain-assisted Bridge Construction/Replacement Project, implemented by the DPWH Regional Office VIII, were monitored and were found to have incurred a negative slippage ranging from -17.81% to -56.67%. All bridges monitored were awarded to the same contractor, J.D. Legaspi Construction with the following timeline: Start of Project Original Completion Date Revised Completion Date

25 October 2012 24 January 2014 13 July 2014

The following information and observations were made during the field monitoring visit: A. Construction of Bagacay Bridge and Approaches in Brgy. Bagacay, Silago, Southern Leyte Contract Cost Physical Accomplishment Slippage

PhP 20,525,896.30 81.32% (-) 18.91%

The bridge proper is 100% completed. The contractor is unable to continue to work on abutment “B” due to non-payment of road right of way (RRW) damages. However, both abutment “A” and “B” and the bridge are open to the traveling public. Documentation required for the processing of payments of RRW damages are still on process. The following photos were taken on site:

2

B. Construction of Lawaan Bridge and Approaches in Brgy. Lawaan, Silago, Southern Leyte Contract Cost Physical Accomplishment Slippage

PhP 32,057,496.13 77.092% (-) 22.91%

The bridge proper is 100% completed. The contractor is unable to continue to work on abutment “A” due to non-payment of RRW damages. Houses along the project will require relocation. The following photos were taken on site:

3

C. Construction of Hibatian Bridge and Approaches in Brgy. Hibatian, Silago, Southern Leyte Contract Cost Physical Accomplishment Slippage

PhP 16,876,758.74 80.688% (-) 19.31%

The bridge proper is 100% completed. The contractor is unable to continue to work on abutment “B” due to non-payment of RRW damages. However, both abutment “A” and “B” and the bridge are open to the traveling public. The required asphalt paver is already on site. The following photos were taken on site:

D. Construction of Bil-atan Bridge and Approaches in Brgy. Bil-atan, San Ricardo, Southern Leyte Contract Cost Physical Accomplishment Slippage

PhP 29,579,420.45 82.186% (-) 17.81%

The bridge proper and the approach slab are 100% completed. Both abutment “A” and “B” and the bridge are open to the traveling public. The approaches are still undergoing repair.

4

The following photos were taken on site:

E. Construction of Pinut-an Bridge and Approaches in Brgy. Pinutan, San Ricardo, Southern Leyte Contract Cost Physical Accomplishment Slippage

PhP 32,523,986.43 43.328% (-) 56.67%

The contractor was unable to continue with the work due to non-payment of RRW damages. Documentation of the payments are still on process.

5

The following photos were taken on site:

6

II.

San Ricardo-Bil-atan Road, K1101-000 – K1102-000 in San Ricardo, Southern Leyte The construction of the San Ricardo – Bil-atan Road Project, implemented by the DPWH Regional Office VIII, was monitored and found to have been 100% completed. With total contract cost at PhP 32,523,986.43, the project covered road construction from station K1101-000 to K1102-000 and the construction of the retaining wall. The project is under JQD Construction and General Services and has followed the timeline below: Start of Project Original Completion Date

14 February 2014 10 October 2014

The following photos were taken on site:

7

III.

Improvement/Widening of Access Road leading to Benit Port (Saddle Area) in Brgy. Manglit, San Ricardo, Southern Leyte

The improvement/widening of access road leading to Benit Port along Brgy. Manglit – Brgy. Son road section, implemented by the DPWH Regional Office VIII, was monitored and was found to be 95% complete, with a negative slippage of 0.05%. The project contract cost is PhP 20 million. The negative slippage is caused by the difficulty experienced by the contractor in road widening due to the boulders situated in the area. The project is under A.C. Rivero Development Corporation and follows the timeline below: Start of Project Original Completion Date

14 February 2014 10 December 2014

The following photos were taken on site:

8

IV.

Widening of Biliran Circumferential Road, Biliran Lone District, K1026+330 - K1027+830, Naval-Almeria Section WIDENING - PAVED The Widening of Biliran Circumferential Road in the Biliran Lone District, from station K1026+330 to K1027+830, implemented by DPWH VIII, Biliran District Engineering Office (DEO) was monitored and was found to be 100% completed. The project contract cost is PhP 45.750 million. The station of project was moved from K1026 + 330 – K1027 + 830 to K1026+800 to connect the road to the Naval municipal road since the road incurs heavy traffic. Minor corrections required involve road shouldering works and will be undertaken by the contractor. The project was noted to have eased the heavy traffic experienced in the area. The project was under B.M Marketing and followed the timeline below: Start of Project Original Completion Date Revised Completion Date

V.

7 March 2014 23 July 2014 3 October 2014

Biliran Circumferential Road, Biliran Lone District – K1110+000 - K1116+000, Sangalang-Biliran Section CONCRETING OF SHOULDER The Biliran Circumferential Road, Biliran Lone District – K1110+000 - K1116+000, Sangalang-Biliran Section CONCRETING OF SHOULDER, implemented by DPWH VIII, Biliran DEO was monitored and was found to be 100% completed. The project contract cost is PhP 23.860 million. The road spans 2.3 kilometers and with its actual project stationing at K1116+000 – K1113+640. The construction of grouted riprap ranging from 2m to 5m in 4 areas were installed on sides of shoulders was under-taken to protect from excessive water run-off or flooding. Three (3) sections of the on-going grouted riprap works were completed. The project was under CTC Construction and Supplies and followed the timeline below: Start of Project Original Completion Date Revised Completion Date

3 March 2014 30 September 2014 26 November 2014

9

VI.

Biliran Circumferential Road, Biliran Lone District - K1018+000 K1023+000, Catmon-Caraycaray Section CONCRETING OF SHOULDER The Biliran Circumferential Road, Biliran Lone District - K1018+000 K1023+000, Catmon-Caraycaray Section CONCRETING OF SHOULDER, implemented by DPWH VIII, Biliran DEO was monitored and was found to be 100% completed. The project contract cost is PhP 23.910 million. The actual PCCP overlay is 3.1 kilometers from the planned 2.5 kilometers. The project was implemented in an area with an existing concrete drainage structure requiring no embankment and other related cost. The project was under CTC Construction and Supplies and followed the timeline below: Start of Project Original Completion Date Revised Completion Date

VII.

3 March 2014 12 July 2014 3 November 2014

Widening of Biliran Circumferential Road, Biliran Lone District K1067+300 K1068+300, Virginia-Culaba Proper WIDENING - PAVED The Widening of Biliran Circumferential Road, Biliran Lone District K1067+300 - K1068+300, Virginia-Culaba Proper WIDENING - PAVED, implemented by DPWH VIII, Biliran DEO was monitored and was found to be 100% completed. The project contract cost is PhP 31.350 million. The project stationing was moved to K1067+000 – K1067+167. Minor remaining work items involves road shouldering work as the housing structures encroaching on the road remain undemolished. The project was under CTC Construction and Supplies and followed the timeline below: Start of Project Original Completion Date Revised Completion Date

6 February 2014 4 September 2014 5 October 2014

10

The following photos were taken on site:

■■

11

PMC Form O-1 REPORT ON THE STATUS OF PROJECTS ENCOUNTERING PROBLEMS IN IMPLEMENTATION As of December 31, 2014 NAME OF PROJECT/PROGRAM

LOCATION

(1)

(2)

IMPLEMENTING IMPLEMENTATION STATUS (%) AGENCY Target Actual Slippage (3)

(4)

(5)

(6)=(5)-(4)

ISSUES

SOURCE OF INFORMATION

ACTION TAKEN/ RECOMMENDATION

(7)

(8)

(9)

NIA

Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

NIA

Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

NIA

Project under suspension due to canal opening at CRMC effective November 2014.

NIA

Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

NIA

Time extension still inder evaluation. Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

HELP FOR CATUBIG AGRICULTURAL ADVANCEMENT PROJECT (HCAAP) HCAAPD-C-1, Construction of Hagbay Diversion Dam and Appurtenant Structures including Supply, Delivery and Stockpilling

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA)-HCAAPPMO

HCAAPD-C-2, Construction of the remaining works of Bulao Diversion Dam and Appurtenant Structures including Supply, Delivery and Installation of Steel Gates

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA)-HCAAPPMO

HCAAPD-C-3, Construction of Pinipisakan Siphonic Bridge Flume and Concrete Lining for Critical Portion of Catubig Right Main Canal (CRMC)

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA)-HCAAPPMO

HCAAPD-C-4, Construction of Catubig Right Main Canal's Lateral 1, 3, 4 and 5 Structures and Creek Improvement

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA)-HCAAPPMO

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA)-HCAAPPMO

HCAAP-LCB-C3-2012, Construction of On-Farm Facilities (Haremasan IA)

100

77.54

84.11

34.54

91.45

59.03

46.95

22.15

23.98

82.28

-40.97

-30.59

-61.96

-10.56

-9.17

Overdue project.

Overdue project.

Overdue project.

Overdue project.

Overdue project.

PMC Form O-1 REPORT ON THE STATUS OF PROJECTS ENCOUNTERING PROBLEMS IN IMPLEMENTATION As of December 31, 2014 NAME OF PROJECT/PROGRAM

LOCATION

(1)

(2)

HCAAP-LCB-C4-2012, Construction of On-Farm Facilities (Robasan IA)

HCAAP-LCB-C5-2012, Construction of On-Farm Facilities (Saliba IA)

IMPLEMENTING IMPLEMENTATION STATUS (%) AGENCY Target Actual Slippage (3)

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA)-HCAAPPMO

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA)-HCAAPPMO

(4)

90.12

49.12

(5)

55.29

9.87

(6)=(5)-(4)

-34.83

-39.25

ISSUES

SOURCE OF INFORMATION

ACTION TAKEN/ RECOMMENDATION

(7)

(8)

(9)

NIA

Time extension still inder evaluation. Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

NIA

Time extension still inder evaluation. Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

NIA

Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

NIA

Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

NIA

Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

Overdue project.

Overdue project.

PINIPISAKAN IRRIGATION PROJECT (PIP) Pinipisakan IP-CP No. 03-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 18+000 to Sta. 20+000

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA) Regional Office No. VIII

Pinipisakan IP-CP No. 04-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 15+800 to Sta. 18+000

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA) Regional Office No. VIII

Pinipisakan IP-CP No. 05-2013, Preparatory Works for CLMC Lateral 4 and Construction of Service Road at Sta. 0+000 to Sta. 4+108

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA) Regional Office No. VIII

27.54

25.64

61.43

15.38

10.99

50.39

-12.16

-14.65

-11.04

Overdue project.

Overdue project.

Overdue project.

PMC Form O-1 REPORT ON THE STATUS OF PROJECTS ENCOUNTERING PROBLEMS IN IMPLEMENTATION As of December 31, 2014 NAME OF PROJECT/PROGRAM

LOCATION

(1)

(2)

IMPLEMENTING IMPLEMENTATION STATUS (%) AGENCY Target Actual Slippage (3)

Pinipisakan IP-CP No. 06-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 13+300 to Sta. 15+400

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA) Regional Office No. VIII

Pinipisakan IP-CP No. 08-2013, Preparatory Works for CLMC Lateral 3 & Const of Service Road, Sta. 0+000 to Sta. 1+500

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA) Regional Office No. VIII

Pinipisakan IP-CP No. 09-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 9+900 to Sta. 12+000

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA) Regional Office No. VIII

Pinipisakan IP-CP No. 10-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 8+600 to Sta. 9+900

Las Navas, Northern Samar (2nd District)

National Irrigation Administration (NIA) Regional Office No. VIII

(4)

18.06

14.91

20.51

21.47

(5)

(6)=(5)-(4)

3.32

0

5.83

6.84

-14.74

-14.91

-14.68

ISSUES

SOURCE OF INFORMATION

ACTION TAKEN/ RECOMMENDATION

(7)

(8)

(9)

NIA

Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

NIA

Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

NIA

Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

NIA

Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

DPWH

DPWH/Managing Consultants to continuously prod contractor to field in required manpower, serviceable equipment and render overtime work when weather permits.

Overdue project.

Overdue project.

Overdue project.

-14.63

Overdue project.

-28.36

Lack of manpower, equipment coupled with unfavorable weather condition experienced at site.

MCC-Assisted Secondary National Road Development Project (SNRDP)

Contract Package 2: Road Rehabilitation, Brgy. Tenani to Sulat/San Julian Mun. Boundary (63.78 km), Eastern Samar

Paranas, Samar and Taft/Sulat, Eastern Samar

DPWH PMO-MCC

45.18

16.82

PMC Form O-2 FINANCIAL AND PHYSICAL STATUS OF CAPITAL INVESTMENT PROGRAMS/PROJECTS As of 31 December 2014 Eastern Visayas (Region VIII) Location Project Title (1)

Agency

Province

Municipality/City

(2)

(3)

(4)

Widening of Daang Maharlika (LT), K0908+(-830) - K0910+472 WIDENING - PAVED, Tacloban City DEO, DPWH Region VIII

DPWH RO8Tacloban City DEO

Leyte

Widening of Daang Maharlika (LT), K0902+146.08 - K0907+173 (with exception) WIDENING - PAVED, Tacloban City DEO, DPWH Region VIII

DPWH RO8Tacloban City DEO

Widening of Picas-San Jose DZR Airport Road, K0910+(-1664) K0910+157.92,K0911+702.74 K0912+050.04 WIDENING - PAVED, Tacloban City DEO, DPWH Region VIII Construction of Flood Control Protection Works of Motiong Bridge along Daang Maharlika, OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS), Motiong, Samar 2nd DEO, DPWH Region VIII

Schedule Target Date Started Completion Date (5)

(6)

Tacloban City

 7/4/2014

Leyte

Tacloban City

DPWH RO8Tacloban City DEO

Leyte

Tacloban City

DPWH RO8Samar 2nd DEO

Samar

Motiong

 6/9/2014

Replacement of bituminous pavement along Daang Maharlika, K0727+000 K0733+000, w/ exception, ASPHALT DPWH RO8OVERLAY (80 MM THICK), Calbayog Samar 1st DEO City, Samar 1st DEO, DPWH Region VIII

Samar

Calbayog City

Daang Maharlika (SM) (Sn Isidro - Sn Juanico Br) K0686 + 805 - K0688 + DPWH RO8000,K0688 + 000 - K0689 + 000 Northern ASPHALT OVERLAY (80 MM THICK), Samar 1st DEO Northern Samar 1st DEO, DPWH Region VIII

Northern Samar

DPWH RO8Leyte 5th DEO

Road Opening/Upgrading of BurauenAlbuera Road including Bridges, Leyte - Burauen Side, Leyte 2nd District Bridges ROAD OPENING, CONCRETE/DistrictWide,Leyte 2nd District Engineering Office,Region VIII

Total Program Amount

AA Issued to Date

Funding Support (%)

Unpaid Obligations

Disbursement

(10)

(11)

Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

(7)

(8)

 12/29/2014

25,000

25,000

100

5

 7/4/2014

 12/29/2014

23,000

23,000

100

5

 6/16/2014

 12/11/2014

45,000

45,000

100

18

 11/7/2014

23,470

23,470

100

75

 6/4/2014

 6/14/2014

23,801

23,801

100

100

San Isidro

 5/23/2014

 9/19/2014

35,328

35,328

100

30

Leyte

Abuyog

 5/21/2014

 11/11/2014

30,000

30,000

100

48

DPWH RO8

Leyte

Burauen

 5/20/2014

 2/13/2015

100,000

100,000

100

6.02

Construction/Upgrading of Baybay City Diversion Road, including Bridges and ROW, Roads & Bridges GRAVEL TO PAVED, Baybay, Leyte 5th DEO, DPWH Region VIII

DPWH RO8

Leyte

Baybay

 5/20/2014

 4/2/2015

150,000

150,000

100

12.5

San Juanico-Basey-Sohoton Road, K0896+(-934) - K0908+222, with exceptions WIDENING-PAVED, Basey, Samar 2nd DEO, DPWH Region VIII

DPWH RO8 Samar 2nd DEO

Samar

Basey

 5/10/2014

 8/30/2014

20,000

20,000

100

35

Construction of Junction AbuyogSilago Road-Cadac-an-Malaguicay Road Section (Malaguicay Falls), GRAVEL TO PAVED, Abuyog, Leyte 5th DEO, DPWH Region VIII

(9)

Physical (%)

Financial (PhP '000)

Employment Generated (man-days)

Remarks

(18)

(19)

Location Project Title

Agency

(1)

Basey-Marabut-Pinamitinan Road, K0912+689 - K0914+479 WIDENING - PAVED/DistrictWide,Samar 2nd District Engineering Office,Region VIII

Schedule Target Date Started Completion Date

Province

Municipality/City

(2)

(3)

(4)

DPWH RO8 Samar 2nd DEO

Samar

Basey

 5/10/2014

Higatangan Circumferential Road leading to Higatangan Island, Naval, Biliran GRAVEL TO PAVED, Biliran DEO, DPWH Region VIII

DPWH RO8

Biliran

Naval

Access Road to Borongan-Llorente Closed Canopy Forest Area, Maydolong, Eastern Samar GRAVEL TO PAVED, Eastern Samar DEO, DPWH Region VIII

DPWH RO8 Easter Samar DEO

Eastern Samar

Widening of Government Center Road Network (S00047LT), K0912+(-250)- DPWH RO8 K0913+595 WIDENING - PAVED, Leyte 1st DEO Palo, Leyte 1st DEO, Region VIII

(5)

(6)

Total Program Amount

AA Issued to Date

Funding Support (%) (9)

Physical (%)

Financial (PhP '000) Unpaid Obligations

Disbursement

(10)

(11)

Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

(7)

(8)

 8/30/2014

20,000

20,000

100

30

 5/9/2014

 12/31/2014

100,000

100,000

100

5

Maydolong

 4/28/2014

 11/5/2014

50,000

50,000

100

20

Leyte

Palo

 4/23/2014

 8/19/2014

15,500

15,500

100

68.81

Mainit-Sn Miguel-Santol Road K0947+558 - K0947+944,K0948+000 - K0948+846,K0950+362 DPWH RO8 K0950+399,K0949+758 - K0950+042 Leyte 1st DEO GRAVEL TO PAVED, Leyte 1st DEO, DPWH Region VIII

Leyte

San Miguel

 4/23/2014

 8/21/2014

39,210

39,210

100

78

Leyte-Samar Inter-Prov'l Road K0907+368 - K0908+000,K0908+642 DPWH RO8 - K0908+754, K0908+816 Leyte 1st DEO K0909+216 GRAVEL TO PAVED, Leyte 1st DEO, DPWH Region VIII

Leyte

Babatngon

 4/23/2014

 7/22/2014

28,221

28,221

100

56

Road Opening/Upgrading of BurauenAlbuera Road including Bridges, Albuera Side, ROAD OPENING, CONCRETE, Leyte 4th DEO, DPWH Region VIII

DPWH RO8

Leyte

Albuera

 4/21/2014

 11/6/2014

72,000

72,000

100

15

Road Opening/Upgrading of BurauenAlbuera Road including Bridges, Albuera Side, ROAD OPENING, CONCRETE, Leyte 4th DEO, DPWH Region VIII

DPWH RO8

Leyte

Albuera

 4/21/2014

 12/13/2014

100,000

100,000

100

6.88

Road from Brgy. Ngolos-Brgy. Sulangan (Guiuan-Sulangan Road), Guiuan, Eastern Samar GRAVEL TO PAVED, Eastern Samar DEO, DPWH Region VIII

DPWH RO8

Eastern Samar

Guiuan

 4/18/2014

 1/2/2015

120,000

120,000

100

32.61

Limasawa Circumferential Road, Limasawa, Southern Leyte GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII

DPWH RO8 Southern Leyte DEO

Southern Leyte

Limasawa

 4/15/2014

 10/10/2014

32,000

32,000

100

62

Road leading to Danao Camp Tree Park, Maasin City, Southern Leyte GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII

DPWH RO8

Southern Leyte

Maasin City

 4/14/2014

 11/19/2014

88,000

88,000

100

91.5

Palo-Carigara-Ormoc Road, K0957 + 100 - K0957 + 360, K0964 + 000 K0967 + 764.8, K0974 + 753 K0979 + 000 PAVED TO PAVED, Leyte 2nd DEO, DPWH Region VIII

DPWH RO8

Leyte

Carigara

 4/14/2014

 10/17/2014

95,744

95,744

100

20.12

Employment Generated (man-days)

Remarks

(18)

(19)

Location Project Title

Agency

(1)

(2)

Province

Municipality/City

(3)

(4)

Road Slip along Pangpang-PalapagMapanas-Gamay-Lapinig Road, K000+000 - K0000+065, Brgy. Cadac- DPWH RO8 an, Gamay Section, K0804+200 Northern K0820+600,K0834+600 Samar 2nd K0834+800,K0856+500 - K0859+000 DEO PAVED TO PAVED, Northern Samar 2nd DEO, DPWH Region VIII

Northern Samar

Gamay

Road Slip along Catarman-Laoang Road - K0767+000 - K0768+000 (with exception), San Roque Section,K0773+800 - K0774+000 (with exception), Pambujan Section,K0783+000 - K0784+000 (with exception), Brgy. Burabod, Laoang Section PAVED TO PAVED, Northern Samar 2nd DEO, DPWH Region VIII

DPWH RO8 Northern Samar 2nd DEO

Northern Samar

Const/Repair/Rehab/Impvt of VILPs Construction of City Library, Baybay City, CONSTRUCTION, Leyte 5th DEO, DPWH Region VIII

DPWH RO8 Leyte 5th DEO

Leyte

Baybay City

Palo-Carigara-Ormoc Road, K0948+250 - K0951+450, Brgy. San Vicente-Brgy. Abango, Tunga & Barugo, Leyte CONCRETING OF SHOULDER, Leyte 2nd DEO, DPWH Region VIII

DPWH RO8 Leyte 2nd DEO

Leyte

Bagahupi-Babatngon-Sta Cruz-BarugoCarigara Road, K0931+420 DPWH RO8 K0932+244, GRAVEL TO PAVED, Leyte 2nd DEO Leyte 2nd DEO, DPWH Region VIII Dulag-Julita-Burauen Road, K0941+000 - K0944+214, Brgy. San Vicente - Brgy. Del Pilar, Dulag, Leyte, CONCRETING OF SHOULDER, Leyte 2nd DEO, DPWH Region VIII Road Opening/Construction of Arteche, Brgy. Catumsan-Jipapad-Las Navas-Catubig-Rawis Road (including Bridges and ROW), ROAD OPENING, CONCRETE, Eastern Samar DEO, DPWH Region VIII Road Slip along Tacloban-Baybay South Road, K0990+500 K0990+600, Maihi Section,K0986+650 - K0986+750, Nebga Section, PAVED TO PAVED, Leyte 5th DEO, DPWH Region VIII Merida-Lundag-Puting BatoConsolacion-Isabel Rd, K1111+315K1111+660; K1112+271K1112+419; K1118+290K1118+543; K1120+000-K1121+117 & K1112+419-K1112+719, GRAVEL TO PAVED,Merida, Leyte 4th DEO, DPWH Region VIII

Schedule Target Date Started Completion Date (5)

(6)

Total Program Amount

AA Issued to Date

(7)

(8)

Funding Support (%) (9)

Physical (%)

Financial (PhP '000) Unpaid Obligations

Disbursement

(10)

(11)

Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

 4/10/2014

 10/5/2014

40,000

40,000

100

40.21

San Roque/Pambujan/  4/10/2014 Laoang

 9/16/2014

30,000

30,000

100

84.88

 4/2/2014

 9/23/2014

30,000

30,000

100

10

Tunga/Barugo

 3/28/2014

 9/4/2014

28,000

28,000

100

75

Leyte

Barugo

 3/28/2014

 10/3/2014

21,000

21,000

100

63

DPWH RO8 Leyte 2nd DEO

Leyte

Dulag

 3/24/2014

 9/19/2014

25,000

25,000

100

 75 %

DPWH RO8

Eastern Samar

Arteche

 3/20/2014

 11/11/2014

100,000

100,000

100

41.16

DPWH RO8 Leyte 5th DEO

Leyte

Baybay City

 3/19/2014

 9/13/2014

20,000

20,000

100

89

DPWH RO8

Leyte

Merida

 3/14/2014

 11/5/2014

65,638

65,638

100

33.68

Employment Generated (man-days)

Remarks

(18)

(19)

Location Project Title

Agency

Province

Municipality/City

Schedule Target Date Started Completion Date

(1)

(2)

(3)

(4)

Jct. Taft-Oras-San Policarpo-Arteche Road, K0881+(-117)-K0900+435, K0900+435-K0908+000, K0909+000K0912+1120, K0914+1403K0919+000, K0920+949-K0926+000, K0943+950-K0950+000, K0950+000K0957+000 CONCRETING OF SHOULDER, Eastern Samar DEO, DPWH Region VIII

(5)

(6)

DPWH RO8

Eastern Samar

Taft

 3/7/2014

 10/17/2014

Widening of Biliran Circumferential Road, Biliran Lone District, K1026+330 - K1027+830, NavalAlmeria Section, WIDENING - PAVED, Biliran District Engineering Office, DPWH Region VIII

DPWH RO8 Biliran DEO

Biliran

Naval

 3/7/2014

 9/2/2014

DPWH RO8 Leyte 2nd DEO

Leyte

Burauen

 3/7/2014

 8/28/2014

Biliran Circumferential Road, K1110+000 - K1116+000, SangalangDPWH RO8 Biliran Section, CONCRETING OF Biliran DEO SHOULDER, Biliran DEO, DPWH Region VIII

Biliran

Biliran

 3/3/2014

Biliran Circumferential Road, K1018+000 - K1023+000, CatmonCaraycaray Section, CONCRETING OF SHOULDER, Biliran DEO, DPWH Region VIII

DPWH RO8 Biliran DEO

Biliran

Naval

Construction/Improvement (Concreting) of Catbalogan City Diversion Road, GRAVEL TO PAVED, Samar 2nd DEO, DPWH Region VIII

DPWH RO8

Samar

Tabango-Catmon-La FortunaManlawaan-Gimarco Road, K1033+242 - K1039+287.56 GRAVEL TO PAVED, Tabango, Leyte 3rd DEO, DPWH Region VIII

DPWH RO8

Construction/Rehabilitation of Flood Control Structure, Brgy. Mag-ubay, Oquendo District, Calbayog City, CONSTRUCTION, Samar 1st DEO, DPWH Region VIII Calbayog Old National Route, Calbayog City, CONCRETING OF SHOULDER, Samar 1st DEO, DPWH Region VIII

Total Program Amount (7)

AA Issued to Date (8)

Funding Support (%) (9)

Physical (%)

Financial (PhP '000) Unpaid Obligations

Disbursement

(10)

(11)

Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

124,315

124,315

100

42

45750

45,750

100

57

48,889

48,889

100

70

 9/30/2014

23,860

23,860

100

50

 3/3/2014

 9/3/2014

23,910

23,910

100

40

Catbalogan City

 2/28/2014

 10/15/2014

80,000

80,000

100

8.47

Leyte

Tabango

 2/28/2014

 11/14/2014

149,510

149,510

100

33.55

DPWH RO8 Samar 1st DEO

Samar

Calbayog City

 2/24/2014

 9/19/2014

25,000

25,000

100

25

DPWH RO8 Samar 1st DEO

Samar

Calbayog City

 2/24/2014

 7/25/2014

20,000

20,000

100

48

Widening of Daang Maharlika (San Isidro-San Juanico Bridge), DPWH RO8 K0769+000 - K0771+000, San Jorge, Samar 1st DEO Samar, WIDENING - PAVED, Samar 1st DEO, DPWH Region VIII

Samar

San Jorge

 2/24/2014

 7/24/2014

50,000

50,000

100

53

Jaro-Dagami-Burauen-Lapaz Road, K0951+217 - K0951+480, K0951+530 - K0951+664, K0951+765 - K0951+920, K0957+657 - K0958+841, K0959+025 - K0959+363, GRAVEL TO PAVED, Leyte 2nd DEO, DPWH Region VIII

Employment Generated (man-days)

Remarks

(18)

(19)

Location Project Title

Agency

(1)

(2)

Province

Municipality/City

Schedule Target Date Started Completion Date

(3)

(4)

Tinambacan Br. along Daang Maharlika (SM) (Sn Isidro-San Juanico Br.) DPWH RO8 RETROFITTING/REHABILITATION/ST Samar 1st DEO RENGTHENING,Calbayog City, Samar 1st DEO, DPWH Region VIII

(5)

Samar

Sta. Margarita

 2/24/2014

Widening of Gomez Extension, Calbayog City, WIDENING - PAVED, Samar 1st DEO, DPWH Region VIII

DPWH RO8 Samar 1st DEO

Samar

Calbayog City

Const/Repair/Rehab/Impvt of VILPs Construction of Gandara-Matuguinao DPWH RO8 Road, Sta. 00+000 - Sta. 22+000, Samar 1st DEO GRAVEL TO PAVED, Gandara, Samar 1st DEO, DPWH Region VIII

Samar

Daang Maharlika (SM) (Sn Isidro - Sn Juanico Br) K0710 +650 - K0711 + 250,K0694 + 762 - K0695 + DPWH RO8 450,K0701 + 050 - K0701 + 216 Samar 1st DEO ASPHALT OVERLAY (80 MM THICK), Samar 1st DEO, DPWH Region VIII

(6)

Total Program Amount

AA Issued to Date

Funding Support (%) (9)

Physical (%)

Financial (PhP '000) Unpaid Obligations

Disbursement

(10)

(11)

Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

(7)

(8)

 8/22/2014

25,602

25,602

100

32

 2/24/2014

 7/1/2014

25,000

25,000

100

76

Gandara

 2/24/2014

 6/23/2014

50,000

50,000

100

72

Samar

Sta. Margarita

 2/24/2014

 4/28/2014

24,233

24,233

100

100

Cagmanipis Br. along Daang Maharlika (SM) (Sn Isidro-Sn Juanico DPWH RO8 Br.) RETROFITTING/REHABILITATION/ST Samar 1st DEO RENGTHENING, Samar 1st DEO, DPWH Region VIII

Samar

Calbayog City

 2/24/2014

 8/22/2014

30,000

30,000

100

64

Construction/Rehabilitation of Monbon Flood Control Structure, Brgy. DPWH RO8 Monbon, Sta. Margarita, Samar, Samar 1st DEO CONSTRUCTION, Samar 1st DEO, DPWH Region VIII

Samar

Sta. Margarita

 2/24/2014

 8/12/2014

20,000

20,000

100

69

Construction/Rehabilitation of Flood Control Structure,Calbayog City, Minlawa-an (Phase II), Brgy. San Policarpo, CONSTRUCTION, Samar 1st DEO, DPWH Region VIII

DPWH RO8 Samar 1st DEO

Samar

Calbayog City

 2/24/2014

 8/12/2014

20,000

20,000

100

80

Construction/Rehabilitation of Flood Control Structure,Calbayog City, Cagnipa (Phase II), Brgy. Cagnipa, Tinambacan District, CONSTRUCTION, Samar 1st DEO, DPWH Region VIII

DPWH RO8 Samar 1st DEO

Samar

Calbayog City

 2/24/2014

 8/13/2014

20,000

20,000

100

85

Rehabilitation/Improvement of Drainage System along Daang DPWH RO8 Maharlika, K0762+500 - K0767+500, Samar 1st DEO OTHERS, Gandara, Samar 1st DEO, DPWH Region VIII

Samar

Gandara

 2/24/2014

 8/19/2014

28,496

28,496

100

78

Road Opening/Construction of Jct. Himay-angan-Silago-Abuyog DPWH RO8 Boundary Road (Bagacay-Bulak), Leyte 5th DEO K1137 + 000 - K1042 + 000, ROAD OPENING, CONCRETE, Abuyog, Leyte 5th DEO, DPWH Region VIII

Leyte

Abuyog

 2/24/2014

 8/17/2014

30,000

30,000

100

91

Construction of Flood Control DPWH RO8 Structure, Calbayog City, Brgy. Bugtong, CONSTRUCTION, Samar 1st Samar 1st DEO DEO, DPWH Region VIII

Samar

Calbayog City

 2/24/2014

 8/14/2014

25,000

25,000

100

92

Employment Generated (man-days)

Remarks

(18)

(19)

Location Project Title

Agency

(1)

Schedule Target Date Started Completion Date

Total Program Amount

AA Issued to Date

Funding Support (%)

Physical (%)

Financial (PhP '000) Unpaid Obligations

Disbursement

(10)

(11)

Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

Province

Municipality/City

(2)

(3)

(4)

DPWH RO8

Leyte

Leyte

 2/17/2014

 10/19/2014

111,084

111,084

100

28.98

Das-ay Br. along Jct Himay-anganDPWH RO8 Silago-Abuyog Bdry Road, RETROFITTING/REHABILITATION/ST Southern Leyte DEO RENGTHENING, Southern Leyte DEO, DPWH Region VIII

Southern Leyte

Silago

 2/14/2014

 10/11/2014

20,000

20,000

100

95

Improvement/Widening of Access Road leading to Benit Port (Saddle Area), San Ricardo, Southern Leyte, WIDENING - PAVED, Southern Leyte DEO, DPWH Region VIII

DPWH RO8 Southern Leyte DEO

Southern Leyte

San Ricardo

 2/14/2014

 10/11/2014

20,000

20,000

100

72.84

Construction/Rehabilitation of Antiao River Control, Catbalogan City, Samar, CONSTRUCTION, Samar 2nd DEO, DPWH Region VIII

DPWH RO8

Samar

Catbalogan City

 2/14/2014

 9/11/2014

75,000

75,000

100

50.25

San Ricardo-Bilatan Road, K1101+000 - K1102+000, GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII

DPWH RO8 Southern Leyte DEO

Southern Leyte

San Ricardo

 2/14/2014

 9/10/2014

37,900

37,900

100

70

Jct Himay-angan-Silago-Abuyog Bdry Road, K1136+(-183) - K1137+000, GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII

DPWH RO8 Southern Leyte DEO

Southern Leyte

Silago

 2/14/2014

 9/10/2014

27,400

27,400

100

42

Bagacay Old Route, Chainage 0000 Chainage 1225, PAVED TO PAVED, Samar 2nd DEO, DPWH Region VIII

DPWH RO8 Samar 2nd DEO

Samar

Hinabangan

 2/13/2014

 8/31/2014

20,753

20,753

100

30

Daang Maharlika (SM) (Sn Isidro - Sn Juanico Br) K0825 + 344 - K0826 + 656, ASPHALT OVERLAY (80 MM THICK), Samar 2nd DEO, DPWH Region VIII

DPWH RO8 Samar 2nd DEO

Samar

Sta. Rita

 2/13/2014

 8/13/2014

21,891

21,891

100

75

Dolongan-Basey Road, Chainage 1391-Chainage 2816, GRAVEL TO PAVED, Samar 2nd DEO, DPWH Region VIII

DPWH RO8 Samar 2nd DEO

Samar

Basey

 2/13/2014

 8/13/2014

31,562

31,562

100

33

Widening of Naval-Caibiran Cross Country Road, K1029+000 K1030+600, San Juan-Poro Kube Section, WIDENING - PAVED, Biliran DEO, DPWH Region VIII

DPWH RO8 Biliran DEO

Biliran

Caibiran

 2/12/2014

 9/9/2014

48,300

48,300

100

37

Widening of Biliran Circumferential Road, K1067+300 - K1068+300, Virginia-Culaba Proper, WIDENING PAVED, Biliran DEO, DPWH Region VIII

DPWH RO8 Biliran DEO

Biliran

Culaba

 2/6/2014

 9/4/2014

31,350

31,350

100

45

DPWH RO8

Leyte

San Isidro

 1/30/2014

 9/23/2014

50,750

50,750

100

73

Cabunga-an-Tabunok-Consuegra Rd Chainage 000 -Chainage 2860, K1014+(-403) - K1014+(361),K1017+597 - K1018+878, GRAVEL TO PAVED, Leyte 3rd DEO, DPWH Region VIII

Sn Isidro-Daja Road, K1018+(-497)K1018+(-427), K1018+959K1019+403, K1024+083-K1025+047, K1025+573-K1026+138, GRAVEL TO PAVED, San Isidro, Leyte 3rd DEO, DPWH Region VIII

(5)

(6)

(7)

(8)

(9)

Employment Generated (man-days)

Remarks

(18)

(19)

Location Project Title

Agency

(1)

(2)

Province

Municipality/City

Schedule Target Date Started Completion Date

(3)

(4)

Tabing - Kawayan - Sta Rosa - Lawis Tabango Road, K1032+610 DPWH RO8 K1033+222,K1035+188 Leyte 3rd DEO K1035+1033, GRAVEL TO PAVED, Leyte 3rd DEO, DPWH Region VIII

(5)

Leyte

San Isidro

 1/30/2014

Calubian Jct-Sn Isidro-TabangoVillaba-Palompon Road, K1015+818 K1016+000, K1016+000 K1016+530, K1016+676 - K1017+ DPWH RO8 000, K1027+000 - K1028+000, Leyte 3rd DEO K1029+100 - K1029+900, K1030+000 - K1031+000, K1031+000-1031+300, K1033+700 K1034+479, Leyte 3rd DEO, DPWH Region VIII

Leyte

San Isidro

Calubian Jct-San Isidro-TabangoVillaba-Palompon Road, K1006+557 - DPWH RO8 K1007+490, GRAVEL TO PAVED, Leyte 3rd DEO Leyte 3rd DEO, DPWH Region VIII

Leyte

Jct. Buenavista-Lawaan-Marabut DPWH RO8 Road, K0959+828-K0996+238, Eastern Samar CONCRETING OF SHOULDER, Eastern DEO Samar DEO, DPWH Region VIII

(6)

Total Program Amount

AA Issued to Date

Funding Support (%) (9)

Physical (%)

Financial (PhP '000) Unpaid Obligations

Disbursement

(10)

(11)

Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

(7)

(8)

 8/26/2014

42,561

42,561

100

88

 1/30/2014

 8/26/2014

28,267

28,267

100

85

Tabango

 1/30/2014

 8/26/2014

28,410

28,410

100

88

Eastern Samar

Lawaan

 1/29/2014

 7/2/2014

44,578

44,578

100

95

Sambulawan Jct. - Calaguise Calubian Road, K0992+400 K0993+493, K1003+390 K1003+914, K0997+395 K0997+603, GRAVEL TO PAVED, Leyte 3rd DEO, DPWH Region VIII

DPWH RO8 Leyte 3rd DEO

Leyte

Leyte

 1/27/2014

 8/23/2014

46,890

46,890

100

95

Burauen-Mahagnao Road, K0984+241 - K0985+1064, GRAVEL TO PAVED, Leyte 2nd DEO, DPWH Region VIII

DPWH RO8 Leyte 2nd DEO

Leyte

Burauen

 1/24/2014

 8/14/2014

49,000

49,000

100

90

Construction/Rehabilitation of Drainage Sytem/Protection Works along Palo-Carigara-Ormoc Road, K0975+000 - K0983+255 (with exception), CONSTRUCTION, Leyte 2nd DEO, DPWH Region VIII

DPWH RO8 Leyte 2nd DEO

Leyte

Carigara

 1/23/2014

 9/9/2014

19,710

19,710

100

80

Widening of Daang Maharlika (LT), K0915+411 - K0916+911,K0919+754 DPWH RO8 - K0920+300.15, WIDENING Leyte 1st DEO PAVED, Leyte 1st DEO, DPWH Region VIII

Leyte

Palo

 1/17/2014

 7/31/2014

37,413

37,413

100

89.8

Widening of Pawing-Campetic Road, K0917+(-334) - K0917+986, WIDENING - PAVED, Leyte 1st DEO, DPWH Region VIII

DPWH RO8 Leyte 1st DEO

Leyte

Palo

 1/17/2014

 6/13/2014

24,000

24,000

100

 77 %

Road Opening of San MiguelBabatngon-Tacloban City Road along Bagahupi-Babatngon-Sta. CruzCaraycaray Section, ROAD OPENING, CONCRETE, Leyte 1st DEO, DPWH Region VIII

DPWH RO8 Leyte 1st DEO

Leyte

Babatngon

 1/17/2014

 8/15/2014

50,000

50,000

100

97.5

Expansion, Polompon District Hospital (Dr. Manuel B. Veloso Memorial DPWH RO8 Hospital), CONSTRUCTION, Leyte 4th Leyte 4th DEO DEO, DPWH Region VIII

Leyte

Palompon

 12/2/2013

 8/21/2014

20,000

20,000

100

32

Employment Generated (man-days)

Remarks

(18)

(19)

Location Project Title

Agency

(1)

Province

Municipality/City

Schedule Target Date Started Completion Date

(2)

(3)

(4)

Rehabiliation/Improvement along Magsaysay Boulevard, K0909+124K0910+(-343), Tacloban City, GRAVEL TO PAVED, Tacloban City DEO, DPWH Region VIII

DPWH RO8 Tacloban City DEO

Leyte

Tacloban City

 6/17/2013

Ormoc Flood Mitigation Project, CONSTRUCTION,Ormoc City, DPWH Regional Office VIII

DPWH RO8

Leyte

Ormoc City

Matag-ob-Palompon Road (LibungaoMatag-ob-Palompon Section), Matagob & Palompon, Leyte, GRAVEL TO PAVED, DPWH Regional Office VIII

DPWH RO8

Leyte

Widening of Ormoc-Baybay-Southern Leyte Bdry Road, K1038 + (-732) K1038 + 000, K1039 + 000 - K1040 + 000, K1041 + 000 - K1042 + 000, K1043 + 000 - K1049 + 000, ASPHALT OVERLAY (80 MM THICK), Leyte 5th DEO, DPWH Region VIII

DPWH RO8

Biliran Circumferential Road, K1008 + 000 - K1008 + 1000, K1011 + 000 K1016 + 000, K1018 + 100 - K1019 + 600, K1019 + 750 - K1021 + 115, ASPHALT OVERLAY (50 MM THICK), Biliran DEO, DPWH Region VIII

DPWH RO8

Funding Support (%)

Unpaid Obligations

Disbursement

(10)

(11)

Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

 1/6/2014

35,635

35,635

100

25

 2/27/2013

 10/3/2014

92,700

92,700

100

75

Palompon

 2/21/2013

 3/7/2014

150,000

150,000

100

76.27

Leyte

Baybay City

 2/19/2013

 6/3/2014

99,730

99,730

100

89.48

Biliran

Biliran

 2/15/2013

 12/26/2013

63,598

63,598

100

44.69

Northern Samar

San Antonio

 2/7/2013

 11/3/2013

46,368

46,368

100

80

DPWH RO8

Leyte

Ormoc City

 2/7/2013

 12/19/2014

150,000

150,000

100

70

DPWH RO8 Eastern Samar DEO

Eastern Samar

Balangiga

 12/13/2013  7/24/2014

29,000

29,000

100

85

Rehabilitation of San Juanico Bridge along Daang Maharlika, RETROFITTING/REHABILITATION/ST RENGTHENING, Leyte 1st DEO, DPWH Region VIII

DPWH RO8

Leyte

Tacloban City

 9/17/2013

 8/1/2014

43,785

43,785

100

88.87

Improvement/Upgrading of LibungaoMatag-ob-Palompon Road, K0990+961-K1024+688, with exceptions, Kanganga, Matag-ob and Palompon, GRAVEL TO PAVED, Leyte 4th DEO, DPWH Region VIII

DPWH RO8

Leyte

Palompon

 9/17/2013

 8/15/2014

100,000

100,000

100

90

Leyte

Burauen

 3/19/2013

 3/7/2014

50,000

50,000

100

75

Rehabilitation of Seawall located at Brgys. 04, 05, and 06, Balangiga, Eastern Samar, REHABILITATION, Eastern Samar DEO, DPWH Region VIII

Road Opening Burauen-Albuera Road DPWH RO8 Including Bridges, Burauen Side, Leyte 2nd DEO ROAD OPENING, CONCRETE, Leyte 2nd DEO, DPWH Region VIII

(9)

Physical (%)

Financial (PhP '000)

(8)

Construction of Ormoc Diversion Road includings & Bridges & ROW, Ormoc City, WIDENING - PAVED, DPWH Regional Office VIII

(6)

AA Issued to Date

(7)

San Antonio Circumferential Road, K0001+919-K0003+765, K0004+655- DPWH RO8 K0004+737, K0004+748-K0005+280, Northern GRAVEL TO PAVED, Northern Samar Samar 1st DEO 1st DEO, DPWH Region VIII

(5)

Total Program Amount

Employment Generated (man-days)

Remarks

(18)

(19)

Location Project Title

Agency

(1)

Province

Municipality/City

Repair/Rehabilitation/Construction of Drainage System along Government Center Road Network, Maharlika Highway and Pawing-Campetic Road, Brgy. Candahug to Brgy. Pawing, Palo, OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS), Leyte 1st DEO,DPWH Region VIII

(2)

(3)

(4)

DPWH RO8 Leyte 1st DEO

Leyte

Palo

Const. of Hibatian Bridge and approaches, Silago, So. Leyte GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII

DPWH RO8

Southern Leyte

Const. of Lawaan Bridge and approaches, Silago, So. Leyte GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII

DPWH RO8

Const. of Bagacay Bridge and approaches, Silago, So. Leyte GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII

Schedule Target Date Started Completion Date (5)

AA Issued to Date

Funding Support (%)

Unpaid Obligations

Disbursement

(10)

(11)

Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

(8)

 3/15/2014

40,000

40,000

100

100

Silago

 10/25/2012  3/10/2014

17,504

17,504

100

80.688

Southern Leyte

Silago

 10/25/2012  3/10/2014

32,685

32,685

100

77.092

DPWH RO8

Southern Leyte

Silago

 10/25/2012  3/10/2014

21,153

21,153

100

81.32

Const. of Bil-atan Bridge and Approaches, San Ricardo, So. Leyte GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII

DPWH RO8

Southern Leyte

San Ricardo

 10/25/2012  3/10/2014

30,207

30,207

100

78.536

Construction of Pinut-an Bridge and Approaches, CONSTRUCTION OF NEW BRIDGE, Southern Leyte DEO, DPWH Region VIII

DPWH RO8

Southern Leyte

San Ricardo

 10/25/2012  3/10/2014

32,524

32,524

100

19.22

Listing Bridge and Approaches, San Isidro, RETROFITTING/ REHABILITATION/ STRENGTHENING, Leyte 3rd DEO, DPWH Region VIII

DPWH RO8

Leyte

San Isidro

 10/10/2012  10/9/2013

14,184

14,184

100

96.5

Tugas Bridge and Approaches, Tabango, CONSTRUCTION OF NEW BRIDGE, Leyte 3rd DEO, DPWH Region VIII

DPWH RO8

Leyte

Tabango

 10/10/2012  10/9/2013

17,730

17,730

100

93.25

Lawis Bridge and Approaches, Tabango, CONSTRUCTION OF NEW BRIDGE, Leyte 3rd DEO, DPWH Region VIII

DPWH RO8

Leyte

Tabango

 10/10/2012  10/9/2013

14,184

14,184

100

95.7

Consuerga Bridge and Approaches, Leyte, CONSTRUCTION OF NEW BRIDGE, Leyte 3rd DEO, DPWH Region VIII

DPWH RO8

Leyte

Leyte

 8/10/2012

 8/9/2013

21,276

21,276

100

95.03

Belen Bridge and Approaches, Leyte, CONSTRUCTION OF NEW BRIDGE, Leyte 3rd DEO, DPWH Region VIII

DPWH RO8

Leyte

Leyte

 8/10/2012

 11/26/2013

21,276

21,276

100

99.47

Gaps along Lapinig-Arteche Road, GRAVEL TO PAVED, DPWH Regional Office VIII

DPWH RO8

Northern and Eastern Samar

 11/4/2013

200,000

200,000

100

95.1

Pangpang-Palapag-Mapanas-GamayLapinig Road, K0838+000 K0838+400, K0846+208-K0847+440, K0848+200 - K0849+820 &K0809+573 - K0811+201, with exceptions GRAVEL TO PAVED, Northern Samar 2nd DEO, DPWH Region VIII

DPWH RO8

Northern Samar

 11/15/2013

97,853

97,853

100

76.87

Lapinig & Arteche  7/30/2012

Palapag

 4/30/2012

(9)

Physical (%)

Financial (PhP '000)

(7)

 2/20/2013

(6)

Total Program Amount

Employment Generated (man-days)

Remarks

(18)

(19)

Location Project Title

Agency

(1)

Province

Municipality/City

Schedule Target Date Started Completion Date

(8)

(9)

Physical (%)

Financial (PhP '000) Unpaid Obligations

Disbursement

(10)

(11)

Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

(3)

(4)

DPWH RO8

Samar

Catbalogan City

 3/5/2012

 4/28/2013

100,000

100,000

100

95

Ormoc Diversion Road, GRAVEL TO PAVED, DPWH Regional Office VIII

DPWH RO8

Leyte

Ormoc City

 2/29/2012

 11/18/2014

100,000

100,000

100

79.95

Eastern Samar

San Policarpo

 1/26/2012

 1/19/2013

29,340

29,340

100

95

Leyte

Carigara

 3/27/2012

 10/3/2013

114,281

114,281

100

95

DPWH RO8

(7)

Funding Support (%)

(2)

Reconstruction of Carigara Bridge along Palo-Carigara-Ormoc Road, Carigara, REPLACEMENT OF DAMAGED BRIDGE, Leyte 2nd DEO, DPWH Region VIII

(6)

AA Issued to Date

Catbalogan Diversion Road, ROAD OPENING, CONCRETE, DPWH Regional Office VIII

Alugan Bridge 4 along Jct Taft-OrasDPWH RO8 Sn Policarpo-Arteche Road, REPLACEMENT OF DAMAGED BRIDGE Eastern Samar ,Eastern Samar DEO, DPWH Region DEO VIII

(5)

Total Program Amount

Employment Generated (man-days)

Remarks

(18)

(19)

PMC Form O-2 FINANCIAL AND PHYSICAL STATUS OF CAPITAL INVESTMENT PROGRAMS/PROJECTS As of 31 December 2014 Eastern Visayas (Region VIII) Location Project Title

Agency

(1)

Schedule Target Completion Date

Financial (PhP '000) Funding Unpaid Disburseme Support Obligatio nt (%) ns

Physical (%)

Employment Generated (man-days)

Remarks

(18)

(19)

Total Program Amount

AA Issued to Date

(6)

(7)

(8)

01 Jul 2013

06 Jun 2014

837,651.30

Paranas/ Taft/ Sulat

01 Jul 2013

31 Mar 2016

2,500,000.01

45.18

16.82

-28.36

37.23

Project behind schedule

San Julian/ Borongan/ Maydolong/ Balangkayan

20 Sep 2012

23 Oct 2015

2,455,881.55

70.97

65.86

-5.11

92.80

Project behind schedule

Llorente/Hernani/G en.MacArthur/ 16 Apr 2013 Quinapondan/ Salcedo/Mercedes/ Guiuan

15 Apr 2016

2,200,000.00

32.11

30.66

-1.45

95.48

Project behind schedule

Expenditure Rate

Province

Municipality/City

Date Started

(2)

(3)

(4)

(5)

Contract Package 1: Road Rehabilitation, Buray Junction to Brgy. Tenani (16.36 km), Paranas, Samar

DPWH PMO-MCC

Samar

Paranas

Contract Package 2: Road Rehabilitation, Brgy. Tenani to Sulat/San Julian Mun. Boundary (63.78 km), Eastern Samar

DPWH PMO-MCC

Samar/ Eastern Samar

Contract Package 3: Road Rehabilitation, San Julian/Sulat Mun. Boundary to Balangkayan/Llorente Mun. Boundary (64.6 km), Eastern Samar

DPWH PMO-MCC

Eastern Samar

Contract Package 4: Road Rehabilitation, Balangkayan/Llorente Mun. Boundary to Guiuan (79.5 km), Eastern Samar

DPWH PMO-MCC

Eastern Samar

Palo-Carigara-Ormoc Road, PAVED (Concrete) TO PAVED (Concrete), Leyte 1st & 2nd DEOs, DPWH Region VIII

DPWH PMO-ADB

Leyte

Palo / Carigara

 3/3/2014

 8/24/2015

372,902

372,902

100

1.193

Daang Maharlika Road (Liloan-Naval Highway), PAVED (CONCRETE) TO PAVED (CONCRETE), Leyte 1st & 2nd DEOs, DPWH Region VIII

DPWH PMO-ADB

Leyte

Palo / Carigara

 3/3/2014

 8/24/2015

239,115

239,115

100

1.193

Calbayog-Catarman Road, K0803+950-K0809+801 with exception (AWPI/PM-06A-2), Samar 1st DEO, DPWH Region VIII

DPWH PMO-J-RUPP

Samar

Calbayog City

 2/17/2014  12/20/2014

96,277

96,277

100

23.862

Calbayog-Catarman Road, K0797+316-K0803+950 with exception (AWPI/PM-06A-1), Samar 1st DEO, DPWH Region VIII

DPWH PMO-J-RUPP

Samar

Calbayog City

 2/17/2014  11/28/2014

108,064

108,064

100

37.324

AWP for 1st Yr. (150 km) (AWP-1), Daang Maharlika, Calbayog-Catarman DPWH Road, K0795+446 to K0784+739 w/ PMO-J-RUPP exception (AWP 1/PM-06B), Samar 1st DEO, DPWH Region VIII

Samar

Calbayog City

 1/2/2014

116,244

116,244

100

18.078

 11/18/2014

(9)

(10)

(11)

Total

(12)=(10+ (13)=(12/7) 11)

Target

Actual

(14)

(15)

Slippage

Performance

(16)=(15-14) (17)=(15/14)

Substantially Completed

98.24

Colab-og-Lungib-BuenasuertePasabuena-Maxville Road, GRAVEL TO PAVED, Victoria, Northern Samar 1st DEO, DPWH Region VIII

DPWH PMO-MCC

Northern Samar

Victoria

 11/12/201  6/18/2013 2

48,500

48,500

100

60

Tucdao Bridge and Approaches, Kawayan, Biliran DEO, DPWH Region VIII

DPWH PMO-Special Bridges

Biliran

Kawayan

 2/13/2013  10/12/2013

20,252

20,252

100

62.18

Talibong Bridge and Approaches, Cabucgayan, Biliran DEO, DPWH Region VIII

DPWH PMO-Special Bridges

Biliran

Cabucgayan

 1/13/2013  9/11/2013

24,802

24,802

100

29.81

PMC Form O-2 FINANCIAL AND PHYSICAL STATUS OF CAPITAL INVESTMENT PROGRAMS/PROJECTS As of 31 December 2014 Eastern Visayas (Region VIII)

Location

Schedule Target Municipality/City Date Started Completion Date

Total Program Amount

Financial (PhP '000) Funding Unpaid Disbursement Support Obligations (%)

Physical (%)

Project Title

Agency

(1)

(2)

(3)

HCAAPD-C-1, Construction of Hagbay Diversion Dam and Appurtenant Structures including Supply, Delivery and Stockpilling

NIA HCAAP-PMO

Northern Samar

Las Navas

7/2/2010

5/13/2014

231,888.88

231,888.88

100

29,800.64

29,800.64

12.85

100.00

HCAAPD-C-2, Construction of the remaining works of Bulao Diversion Dam and Appurtenant Structures including Supply, Delivery and Installation of Steel Gates

NIA HCAAP-PMO

Northern Samar

Las Navas

9/9/2011

1/5/2015

172,723.00

172,723.00

100

81,092.89

81,092.89

46.95

HCAAPD-C-3, Construction of Pinipisakan Siphonic Bridge Flume and Concrete Lining for Critical Portion of Catubig Right Main Canal

NIA HCAAP-PMO

Northern Samar

Las Navas

10/31/2012

12/11/2014

66,120.80

66,120.80

100

1,587.36

1,587.36

HCAAPD-C-4, Construction of Catubig Right Main Canal's Lateral 1, 3, 4 and 5 Structures and Creek Improvement

NIA HCAAP-PMO

Northern Samar

Las Navas

10/31/2012

5/10/2015

104,988.06

104,988.06

100

12,980.39

12,980.39

HCAAP-LCB-C2-2012, Construction of On-Farm Facilities (Pinipisakan IA)

NIA HCAAP-PMO

Northern Samar

Las Navas

11/24/2012

6/30/2014

15,995.36

15,995.36

100

HCAAP-LCB-C3-2012, Construction of On-Farm Facilities (Haremasan IA)

NIA HCAAP-PMO

Northern Samar

Las Navas

12/14/2012

8/30/2014

17,662.72

17,662.72

100

12,213.77

12,213.77

69.15

91.45

82.28

HCAAP-LCB-C4-2012, Construction of On-Farm Facilities (Robasan IA)

NIA HCAAP-PMO

Northern Samar

Las Navas

1/20/2013

6/30/2014

22,899.56

22,899.56

100

7,878.11

7,878.11

34.40

90.12

55.29

HCAAP-LCB-C5-2012, Construction of On-Farm Facilities (Saliba IA)

NIA HCAAP-PMO

Province

(4)

(5)

(6)

(7)

HELP for Catubig Agricultural Advancement Project (HCAAP) - Irrigation and Drainage Component

AA Issued to Date (8)

(9)

(10)

(11)

Employment Generated (man-days)

Remarks

(18)

(19)

Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

59.03

-40.97

59.03

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

77.54

46.95

-30.59

60.55

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

2.40

84.11

22.15

-61.96

26.33

Under suspension due to canal opening at CRMC effective November 2014.

12.36

34.54

23.98

-10.56

69.43

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

100

Project Completed

-9.17

89.97

Time extension still under evaluation. Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

-34.83

61.35

Time extension still under evaluation. Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

20.09

Time extension still under evaluation. Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

100

49.12

100

9.87

0

Northern Samar

Las Navas

5/18/2013

8/31/2014

22,899.56

22,899.56

100

1,305.57

1,305.57

5.70

-39.25

Pinipisakan IP-CP No.01-2013, Diversion Road to Catubig Left Main Canal (CLMC) Access Road

NIA Regional Office Northern Samar VIII

Las Navas

11/6/2013

7/23/2014

11,593.04

11,593.04

100

541.45

541.45

4.67

70.45

62.54

-7.91

88.77

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

Pinipisakan IP-CP No.02-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 20+000 to Sta. 22+585

NIA Regional Office Northern Samar VIII

Las Navas

6/26/2013

8/21/2014

29,804.85

29,804.85

100

14,955.99

14,955.99

50.18

85.45

86.93

1.48

101.73

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

Pinipisakan Irrigation Project (PIP)

Location Project Title

Agency

(1)

(2)

Province (3)

Schedule Target Municipality/City Date Started Completion Date (4)

(5)

(6)

Total Program Amount (7)

AA Issued to Date (8)

Financial (PhP '000) Funding Unpaid Disbursement Support Obligations (%) (9)

(10)

(11)

Physical (%) Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

Employment Generated (man-days)

Remarks

(18)

(19)

Pinipisakan IP-CP No.03-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 18+000 to Sta. 20+000

NIA Regional Office Northern Samar VIII

Las Navas

11/26/2013

8/15/2014

31,030.29

31,030.29

100

27.54

15.38

-12.16

55.85

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

Pinipisakan IP-CP No.04-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 15+800 to Sta. 18+000

NIA Regional Office Northern Samar VIII

Las Navas

11/8/2013

8/17/2014

25,700.46

25,700.46

100

25.64

10.99

-14.65

42.86

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

Pinipisakan IP-CP No.05-2013, NIA Preparatory Works for CLMC Lateral 4 Regional Office Northern Samar and Construction of Service Road at VIII Sta. 0+000 to Sta. 4+108

Las Navas

7/1/2013

8/17/2014

39,342.82

39,342.82

100

61.43

50.39

-11.04

82.03

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

Pipisakan IP-CP No.06-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 13+300 to Sta. 15+400

NIA Regional Office Northern Samar VIII

Las Navas

7/1/2013

1/27/2014

39,980.29

39,980.29

100

18.06

3.32

-14.74

18.38

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

Pinipisakan IP-CP No.07-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 12+000 to Sta. 13+300

NIA Regional Office Northern Samar VIII

Las Navas

7/1/2013

1/27/2014

28,306.65

28,306.65

100

27.54

30.17

2.63

109.55

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

Pinipisakan IP-CP No. 08-2013, NIA Preparatory Works for CLMC Lateral 3 Regional Office Northern Samar & Const of Service Road, Sta. 0+000 VIII to Sta. 1+500

Las Navas

11/7/2013

6/5/2014

25,734.33

25,734.33

100

14.91

0

-14.91

0.00

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

Pinipisakan IP-CP No. 09-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 9+900 to Sta. 12+000

NIA Regional Office Northern Samar VIII

Las Navas

6/28/2013

1/24/2014

37,032.67

37,032.67

100

20.51

5.83

-14.68

28.43

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

Pinipsakan IP-CP No. 10-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 8+600 to Sta. 9+900

NIA Regional Office Northern Samar VIII

Las Navas

6/28/2013

6/28/2014

30,069.46

30,069.46

100

21.47

6.84

-14.63

31.86

Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.

11,985.93

11,985.93

100

34,880.16

34,880.16

100

Mondragon

92,150.00

92,150.00

100

98

90.09

-7.91

91.93

Project still ongoing.

San Roque

138,225.00

138,225.00

100

71.93

80.15

8.22

111.43

Project still ongoing.

Calbiga

156,655.00

156,655.00

100

100

100.00

Project completed.

Sta. Rita

27,645.00

27,645.00

100

100

95.44

Project still ongoing.

Pinipisakan IP-CP No. 11-2013, Hinaga Siphonic Box Culvert Pinipisakan IP-CP No. 12-2013, Hinaga Bridge Flume

NIA Regional Office Northern Samar VIII NIA Regional Office Northern Samar VIII

Las Navas

Las Navas

11/7/2013

5/6/2014

6,817.38

6,817.38

17.33

No Notice To Proceed Yet

-

-

Under suspension.

-

OTHER MAJOR IRRIGATION PROJECTS Bugko Irrigation Project

Bantayan Irrigation Project

Calbiga Irrigation Project

Sta. Rita SRIP

NIA Regional Office Northern Samar VIII NIA Regional Office Northern Samar VIII NIA Samar Regional Office VIII NIA Samar Regional Office VIII

100

95.44

0

-4.56

Location Project Title (1)

Hibulangan SRIP

Agency (2)

NIA Regional Office VIII

Province (3)

Leyte

Schedule Target Municipality/City Date Started Completion Date (4)

Villaba

(5)

(6)

Total Program Amount (7)

92,150.00

AA Issued to Date (8)

92,150.00

Financial (PhP '000) Funding Unpaid Disbursement Support Obligations (%) (9)

100

(10)

(11)

Physical (%) Total

Expenditure Rate

Target

Actual

Slippage

Performance

(12)=(10+11)

(13)=(12/7)

(14)

(15)

(16)=(15-14)

(17)=(15/14)

100

100

0

100.00

Employment Generated (man-days)

Remarks

(18)

(19)

Project completed.

RPMES Report 4th Qtr 2014.pdf

Page 1 of 30. Republic of the Philippines. REGIONAL DEVELOPMENT COUNCIL. Eastern Visayas (Region VIII). REGIONAL PROJECT MONITORING ...

6MB Sizes 13 Downloads 158 Views

Recommend Documents

RPMES Report 2nd Quarter 2015.pdf
investment cost of PhP 27.222 billion. Projects included in this report were those. funded through Official Development Assistance (ODA), and those funded by ...

Quarterly Report of Operation 1st Qtr 2017.pdf
o. 3. Page 1 of 1. Quarterly Report of Operation 1st Qtr 2017.pdf. Quarterly Report of Operation 1st Qtr 2017.pdf. Open. Extract. Open with. Sign In. Main menu.

RPMES Report 1st Quarter 2015.pdf
K1008+150-K1008+360 Boundary Mahaplag-Liloan, Sogod. Other. Improvement Works (Slope Protection, Drainage, Sidewalks). 4. Construction/Rehabilitation of Flood Control Structures, Subang Daku Flood. Control (Phase II) (Along Boundary Southern Leyte-Ma

USLP India Progress 2014PDF - Hul
Ÿ Project Shakti network expanded to include over 70,000 ... The 'Help a Child Reach 5' handwashing campaign started in 2013 in .... while promoting the benefits of clean toilets and good hygiene. .... social investment in India has continued to sup

2017 3rd Qtr RES.pdf
Page 1 of 14. CAR Regional Economic Situationer | 1. Third Quarter 2017. Cordillera Administrative Region. ASSESSMENT OF LEADING ECONOMIC. INDICATORS. Leading economic indicators showed a mix picture of. the regional economy for the quarter. Compared

Rly Qtr Aplication.pdf
Camotes Sea, on the west by the Bohol Strait, and on the. south by the Mindanao Sea. Capital Tagbilaran City. Land Area ... Cost of Doing Business. LABOR RATES: Tagbilaran City Municipalities. Non-Agri ... MESSENGERIAL (DHL) US Japan Middle East Fran

Serai qtr EBook.pdf
NED University of Engineering and Technology. A Research Project Sponsored by the Ministry of Culture, Government of Sindh. © Department of Architecture ...

04 2nd qtr profit loss.pdf
Page 1 of 1. Account Programs Administrative Fundraising Total YTD. Income (includes FY2011 receivables). A1 Contributions 124300 5820 0 130120. A3 Program Services - Earned Income 92189 3075 0 95264. Interest Income 0 0 0 0. 22 Cash Assets (carry-ov

3rd Quarter CY 2016 RPMES Digest.pdf
DILG-X to closely monitor and. coordinate with the LGUs concerned. DSWD Delayed implementation of. programs/projects due failure of. bidding/delayed ...

2015 3rd Qtr. (income).pdf
1 2 3 4 5 6 7 8=(4+5+6+7) 9 10 11=(9+10) 12=(8-3) 13=(12/3) 14 ... Remarks. VARIANCE. Remittance to. BTR. Deposited with. AGDB. Total Amount %.

RPMES 3rd Quarter 2016 with Comparative performance-after ...
Infrastructure. 77.70%. Economic. 5.10%. Page 4 of 22. RPMES 3rd Quarter 2016 with Comparative performance-after consultation.pdf. RPMES 3rd Quarter ...

2nd qtr 2015 BAR No1.pdf
P- Occ. Mindoro 1 1 1 1. updating of existing plans P- Or. ... Oriental Mdo. 1 1 1 3 1 1. Marinduque 1 1 2 1 .... C-Calapan 3 3 3 3 3 3 3 3. C-Socorro 3 3 3 3 3 3 3 3.

REPORT OF THE ICT UNIV3RSITY 4th GRADUATION CEREMONY.pdf
It was graced by a cultural jamboree. 26th May 2017. The ceremony started at 9:00 am with a procession from the MUBS campus to the ceremonial grounds. The DVC of the ICT University, Prof Elizabeth Tamajong read the names of the grandaunts, the Provos

REPORT OF THE ICT UNIV3RSITY 4th GRADUATION CEREMONY ...
REPORT OF THE ICT UNIV3RSITY 4th GRADUATION CEREMONY.pdf. REPORT OF THE ICT UNIV3RSITY 4th GRADUATION CEREMONY.pdf. Open. Extract.

4th Grade Report Card Rev1.pdf
Life Science- Constructs an argument that. plants and animals in Idaho have structures. that function to support survival, growth, and. behavior. Earth Science - Uses maps, observations, and. past evidence to explain changes in landscape. over time.

Quarterly Suicide Report (QSR) 4th Quarter, CY 2017
Apr 9, 2018 - George Parisi, Acting Director. Defense Suicide Prevention Office. (DSPO). The estimated cost of this report or study for the Department.

q-Gram Tetrahedral Ratio (qTR) for Approximate Pattern Matching
matching is to increase automated record linkage. Valid linkages will be determined by the user and should represent those “near matches” that the user.

Region 5 2nd Qtr 2015 Accomp.pdf
1,200 122 507 153.35 528.6020 30% 44%. Sorsogon 420 36 170 88 201 48%. (ha.) 420 36 170 300.2000 71%. applications processed. and forwarded to PENRO. (no./has) Total 3,600 333 1,440 455 1,560 32% 43%. 4,100 387.0000 1,634.0000 411.2653 2,002.3810 25%

RPMES 3rd Quarter 2016 with Comparative performance-after ...
There was a problem previewing this document. Retrying... Download. Connect more apps... RPMES 3rd Qu ... ultation.pdf. RPMES 3rd Qu ... ultation.pdf. Open.

q-Gram Tetrahedral Ratio (qTR) for Approximate Pattern Matching
possible to create a table of aliases for domain- specific alphanumeric values, however, it is unlikely that all possible errors could be anticipated in advance. 2.

report
Mar 7, 2016 - a cluttered bin, can be performed with hardly any advance planning, relying instead ... attempt, and a large-scale data collection framework for.

report
Mar 7, 2016 - objects by embedding the finger into the center of the ob- ject, while harder objects were .... national Conference on Robotics and Automation, pp. 1316–1322, 2015. ... Contact Wrench Space Metrics. In IEEE International.

2017 3rd Qtr BCBS Inservice Instructions.pdf
Page 1 of 1. 3601 W. Devon Ave. Suite 108, Chicago, IL60659 | 701 Deerfield Parkway Suite 101, Buffalo Grove, IL 60089. Phone (847) 403-3053 Fax (847) 943-2107. [email protected]. www.newagecare.net. Blue Cross Blue Shield - 2017 - 3. rd Quar