Republic of the Philippines REGIONAL DEVELOPMENT COUNCIL Eastern Visayas (Region VIII) REGIONAL PROJECT MONITORING COMMITTEE VIII 4th Quarter CY 2014 Field Monitoring Report Monitoring Visit For Projects in the Provinces of Biliran and Southern Leyte 15-16 December 2014
The Regional Project Monitoring Committee (RPMC) VIII conducted field monitoring visits on 15 – 16 December 2014 on the following projects: 1. Five (5) Bridges under the Spain-assisted Bridge Construction/Replacement Project implemented by the Department of Public Works and Highways (DPWH), to wit: a. Bagacay Bridge in Silago, Southern Leyte b. Lawaan Bridge in Silago, Southern Leyte c. Hibatian Bridge inSilago, Southern Leyte d. Pinut-an Bridge in San Ricardo, Leyte e. Bila-atan Bridge, San Ricardo, Leyte 2. San Ricardo-Bilatan Road - K1101+000 – K1102+000 GRAVEL TO PAVED/Districtwide, Southern Leyte District Engineering Office, Region VIII 3. Improvement/Widening of Access Road leading to Benit Port (Saddle Area), San Ricardo, Southern Leyte WIDENING – PAVED/San Ricardo, Southern Leyte District Engineering Office 4. Widening of Biliran Circumferential Road, Biliran Lone District, K1026+330 - K1027+830, Naval-Almeria Section WIDENING – PAVED 5. Biliran Circumferential Road, Biliran Lone District - K1110+000 - K1116+000, Sangalang-Biliran Section CONCRETING OF SHOULDER 6. Biliran Circumferential Road, Biliran Lone District - K1018+000 - K1023+000, Catmon-Caraycaray Section CONCRETING OF SHOULDER 7. Widening of Biliran Circumferential Road, Biliran Lone District, K1067+300 - K1068+300, Virginia-Culaba Proper WIDENING – PAVED. The monitoring team that visited Southern Leyte were Eng. Art Bulic of the Department of the Interior and Local Government (DILG) VIII, Mr. Romeo Ang of the Department of Budget Management (DBM) VIII, and Mr. Ramon Hidalgo of the National Economic and Development Authority (NEDA) VIII. The monitoring team that visited Biliran were Engr. Laurence Alonzo of DILG VIII, Ms. Lorna Cinco of the Presidential Management Staff (PMS), and Mr. Marlon Dumagsa of NEDA VIII.
1
I.
Spain-assisted Bridge Construction/Replacement Project Five (5) of the ten (10) bridges under the Spain-assisted Bridge Construction/Replacement Project, implemented by the DPWH Regional Office VIII, were monitored and were found to have incurred a negative slippage ranging from -17.81% to -56.67%. All bridges monitored were awarded to the same contractor, J.D. Legaspi Construction with the following timeline: Start of Project Original Completion Date Revised Completion Date
25 October 2012 24 January 2014 13 July 2014
The following information and observations were made during the field monitoring visit: A. Construction of Bagacay Bridge and Approaches in Brgy. Bagacay, Silago, Southern Leyte Contract Cost Physical Accomplishment Slippage
PhP 20,525,896.30 81.32% (-) 18.91%
The bridge proper is 100% completed. The contractor is unable to continue to work on abutment “B” due to non-payment of road right of way (RRW) damages. However, both abutment “A” and “B” and the bridge are open to the traveling public. Documentation required for the processing of payments of RRW damages are still on process. The following photos were taken on site:
2
B. Construction of Lawaan Bridge and Approaches in Brgy. Lawaan, Silago, Southern Leyte Contract Cost Physical Accomplishment Slippage
PhP 32,057,496.13 77.092% (-) 22.91%
The bridge proper is 100% completed. The contractor is unable to continue to work on abutment “A” due to non-payment of RRW damages. Houses along the project will require relocation. The following photos were taken on site:
3
C. Construction of Hibatian Bridge and Approaches in Brgy. Hibatian, Silago, Southern Leyte Contract Cost Physical Accomplishment Slippage
PhP 16,876,758.74 80.688% (-) 19.31%
The bridge proper is 100% completed. The contractor is unable to continue to work on abutment “B” due to non-payment of RRW damages. However, both abutment “A” and “B” and the bridge are open to the traveling public. The required asphalt paver is already on site. The following photos were taken on site:
D. Construction of Bil-atan Bridge and Approaches in Brgy. Bil-atan, San Ricardo, Southern Leyte Contract Cost Physical Accomplishment Slippage
PhP 29,579,420.45 82.186% (-) 17.81%
The bridge proper and the approach slab are 100% completed. Both abutment “A” and “B” and the bridge are open to the traveling public. The approaches are still undergoing repair.
4
The following photos were taken on site:
E. Construction of Pinut-an Bridge and Approaches in Brgy. Pinutan, San Ricardo, Southern Leyte Contract Cost Physical Accomplishment Slippage
PhP 32,523,986.43 43.328% (-) 56.67%
The contractor was unable to continue with the work due to non-payment of RRW damages. Documentation of the payments are still on process.
5
The following photos were taken on site:
6
II.
San Ricardo-Bil-atan Road, K1101-000 – K1102-000 in San Ricardo, Southern Leyte The construction of the San Ricardo – Bil-atan Road Project, implemented by the DPWH Regional Office VIII, was monitored and found to have been 100% completed. With total contract cost at PhP 32,523,986.43, the project covered road construction from station K1101-000 to K1102-000 and the construction of the retaining wall. The project is under JQD Construction and General Services and has followed the timeline below: Start of Project Original Completion Date
14 February 2014 10 October 2014
The following photos were taken on site:
7
III.
Improvement/Widening of Access Road leading to Benit Port (Saddle Area) in Brgy. Manglit, San Ricardo, Southern Leyte
The improvement/widening of access road leading to Benit Port along Brgy. Manglit – Brgy. Son road section, implemented by the DPWH Regional Office VIII, was monitored and was found to be 95% complete, with a negative slippage of 0.05%. The project contract cost is PhP 20 million. The negative slippage is caused by the difficulty experienced by the contractor in road widening due to the boulders situated in the area. The project is under A.C. Rivero Development Corporation and follows the timeline below: Start of Project Original Completion Date
14 February 2014 10 December 2014
The following photos were taken on site:
8
IV.
Widening of Biliran Circumferential Road, Biliran Lone District, K1026+330 - K1027+830, Naval-Almeria Section WIDENING - PAVED The Widening of Biliran Circumferential Road in the Biliran Lone District, from station K1026+330 to K1027+830, implemented by DPWH VIII, Biliran District Engineering Office (DEO) was monitored and was found to be 100% completed. The project contract cost is PhP 45.750 million. The station of project was moved from K1026 + 330 – K1027 + 830 to K1026+800 to connect the road to the Naval municipal road since the road incurs heavy traffic. Minor corrections required involve road shouldering works and will be undertaken by the contractor. The project was noted to have eased the heavy traffic experienced in the area. The project was under B.M Marketing and followed the timeline below: Start of Project Original Completion Date Revised Completion Date
V.
7 March 2014 23 July 2014 3 October 2014
Biliran Circumferential Road, Biliran Lone District – K1110+000 - K1116+000, Sangalang-Biliran Section CONCRETING OF SHOULDER The Biliran Circumferential Road, Biliran Lone District – K1110+000 - K1116+000, Sangalang-Biliran Section CONCRETING OF SHOULDER, implemented by DPWH VIII, Biliran DEO was monitored and was found to be 100% completed. The project contract cost is PhP 23.860 million. The road spans 2.3 kilometers and with its actual project stationing at K1116+000 – K1113+640. The construction of grouted riprap ranging from 2m to 5m in 4 areas were installed on sides of shoulders was under-taken to protect from excessive water run-off or flooding. Three (3) sections of the on-going grouted riprap works were completed. The project was under CTC Construction and Supplies and followed the timeline below: Start of Project Original Completion Date Revised Completion Date
3 March 2014 30 September 2014 26 November 2014
9
VI.
Biliran Circumferential Road, Biliran Lone District - K1018+000 K1023+000, Catmon-Caraycaray Section CONCRETING OF SHOULDER The Biliran Circumferential Road, Biliran Lone District - K1018+000 K1023+000, Catmon-Caraycaray Section CONCRETING OF SHOULDER, implemented by DPWH VIII, Biliran DEO was monitored and was found to be 100% completed. The project contract cost is PhP 23.910 million. The actual PCCP overlay is 3.1 kilometers from the planned 2.5 kilometers. The project was implemented in an area with an existing concrete drainage structure requiring no embankment and other related cost. The project was under CTC Construction and Supplies and followed the timeline below: Start of Project Original Completion Date Revised Completion Date
VII.
3 March 2014 12 July 2014 3 November 2014
Widening of Biliran Circumferential Road, Biliran Lone District K1067+300 K1068+300, Virginia-Culaba Proper WIDENING - PAVED The Widening of Biliran Circumferential Road, Biliran Lone District K1067+300 - K1068+300, Virginia-Culaba Proper WIDENING - PAVED, implemented by DPWH VIII, Biliran DEO was monitored and was found to be 100% completed. The project contract cost is PhP 31.350 million. The project stationing was moved to K1067+000 – K1067+167. Minor remaining work items involves road shouldering work as the housing structures encroaching on the road remain undemolished. The project was under CTC Construction and Supplies and followed the timeline below: Start of Project Original Completion Date Revised Completion Date
6 February 2014 4 September 2014 5 October 2014
10
The following photos were taken on site:
■■
11
PMC Form O-1 REPORT ON THE STATUS OF PROJECTS ENCOUNTERING PROBLEMS IN IMPLEMENTATION As of December 31, 2014 NAME OF PROJECT/PROGRAM
LOCATION
(1)
(2)
IMPLEMENTING IMPLEMENTATION STATUS (%) AGENCY Target Actual Slippage (3)
(4)
(5)
(6)=(5)-(4)
ISSUES
SOURCE OF INFORMATION
ACTION TAKEN/ RECOMMENDATION
(7)
(8)
(9)
NIA
Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
NIA
Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
NIA
Project under suspension due to canal opening at CRMC effective November 2014.
NIA
Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
NIA
Time extension still inder evaluation. Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
HELP FOR CATUBIG AGRICULTURAL ADVANCEMENT PROJECT (HCAAP) HCAAPD-C-1, Construction of Hagbay Diversion Dam and Appurtenant Structures including Supply, Delivery and Stockpilling
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA)-HCAAPPMO
HCAAPD-C-2, Construction of the remaining works of Bulao Diversion Dam and Appurtenant Structures including Supply, Delivery and Installation of Steel Gates
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA)-HCAAPPMO
HCAAPD-C-3, Construction of Pinipisakan Siphonic Bridge Flume and Concrete Lining for Critical Portion of Catubig Right Main Canal (CRMC)
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA)-HCAAPPMO
HCAAPD-C-4, Construction of Catubig Right Main Canal's Lateral 1, 3, 4 and 5 Structures and Creek Improvement
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA)-HCAAPPMO
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA)-HCAAPPMO
HCAAP-LCB-C3-2012, Construction of On-Farm Facilities (Haremasan IA)
100
77.54
84.11
34.54
91.45
59.03
46.95
22.15
23.98
82.28
-40.97
-30.59
-61.96
-10.56
-9.17
Overdue project.
Overdue project.
Overdue project.
Overdue project.
Overdue project.
PMC Form O-1 REPORT ON THE STATUS OF PROJECTS ENCOUNTERING PROBLEMS IN IMPLEMENTATION As of December 31, 2014 NAME OF PROJECT/PROGRAM
LOCATION
(1)
(2)
HCAAP-LCB-C4-2012, Construction of On-Farm Facilities (Robasan IA)
HCAAP-LCB-C5-2012, Construction of On-Farm Facilities (Saliba IA)
IMPLEMENTING IMPLEMENTATION STATUS (%) AGENCY Target Actual Slippage (3)
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA)-HCAAPPMO
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA)-HCAAPPMO
(4)
90.12
49.12
(5)
55.29
9.87
(6)=(5)-(4)
-34.83
-39.25
ISSUES
SOURCE OF INFORMATION
ACTION TAKEN/ RECOMMENDATION
(7)
(8)
(9)
NIA
Time extension still inder evaluation. Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
NIA
Time extension still inder evaluation. Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
NIA
Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
NIA
Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
NIA
Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
Overdue project.
Overdue project.
PINIPISAKAN IRRIGATION PROJECT (PIP) Pinipisakan IP-CP No. 03-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 18+000 to Sta. 20+000
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA) Regional Office No. VIII
Pinipisakan IP-CP No. 04-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 15+800 to Sta. 18+000
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA) Regional Office No. VIII
Pinipisakan IP-CP No. 05-2013, Preparatory Works for CLMC Lateral 4 and Construction of Service Road at Sta. 0+000 to Sta. 4+108
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA) Regional Office No. VIII
27.54
25.64
61.43
15.38
10.99
50.39
-12.16
-14.65
-11.04
Overdue project.
Overdue project.
Overdue project.
PMC Form O-1 REPORT ON THE STATUS OF PROJECTS ENCOUNTERING PROBLEMS IN IMPLEMENTATION As of December 31, 2014 NAME OF PROJECT/PROGRAM
LOCATION
(1)
(2)
IMPLEMENTING IMPLEMENTATION STATUS (%) AGENCY Target Actual Slippage (3)
Pinipisakan IP-CP No. 06-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 13+300 to Sta. 15+400
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA) Regional Office No. VIII
Pinipisakan IP-CP No. 08-2013, Preparatory Works for CLMC Lateral 3 & Const of Service Road, Sta. 0+000 to Sta. 1+500
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA) Regional Office No. VIII
Pinipisakan IP-CP No. 09-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 9+900 to Sta. 12+000
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA) Regional Office No. VIII
Pinipisakan IP-CP No. 10-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 8+600 to Sta. 9+900
Las Navas, Northern Samar (2nd District)
National Irrigation Administration (NIA) Regional Office No. VIII
(4)
18.06
14.91
20.51
21.47
(5)
(6)=(5)-(4)
3.32
0
5.83
6.84
-14.74
-14.91
-14.68
ISSUES
SOURCE OF INFORMATION
ACTION TAKEN/ RECOMMENDATION
(7)
(8)
(9)
NIA
Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
NIA
Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
NIA
Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
NIA
Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
DPWH
DPWH/Managing Consultants to continuously prod contractor to field in required manpower, serviceable equipment and render overtime work when weather permits.
Overdue project.
Overdue project.
Overdue project.
-14.63
Overdue project.
-28.36
Lack of manpower, equipment coupled with unfavorable weather condition experienced at site.
MCC-Assisted Secondary National Road Development Project (SNRDP)
Contract Package 2: Road Rehabilitation, Brgy. Tenani to Sulat/San Julian Mun. Boundary (63.78 km), Eastern Samar
Paranas, Samar and Taft/Sulat, Eastern Samar
DPWH PMO-MCC
45.18
16.82
PMC Form O-2 FINANCIAL AND PHYSICAL STATUS OF CAPITAL INVESTMENT PROGRAMS/PROJECTS As of 31 December 2014 Eastern Visayas (Region VIII) Location Project Title (1)
Agency
Province
Municipality/City
(2)
(3)
(4)
Widening of Daang Maharlika (LT), K0908+(-830) - K0910+472 WIDENING - PAVED, Tacloban City DEO, DPWH Region VIII
DPWH RO8Tacloban City DEO
Leyte
Widening of Daang Maharlika (LT), K0902+146.08 - K0907+173 (with exception) WIDENING - PAVED, Tacloban City DEO, DPWH Region VIII
DPWH RO8Tacloban City DEO
Widening of Picas-San Jose DZR Airport Road, K0910+(-1664) K0910+157.92,K0911+702.74 K0912+050.04 WIDENING - PAVED, Tacloban City DEO, DPWH Region VIII Construction of Flood Control Protection Works of Motiong Bridge along Daang Maharlika, OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS), Motiong, Samar 2nd DEO, DPWH Region VIII
Schedule Target Date Started Completion Date (5)
(6)
Tacloban City
7/4/2014
Leyte
Tacloban City
DPWH RO8Tacloban City DEO
Leyte
Tacloban City
DPWH RO8Samar 2nd DEO
Samar
Motiong
6/9/2014
Replacement of bituminous pavement along Daang Maharlika, K0727+000 K0733+000, w/ exception, ASPHALT DPWH RO8OVERLAY (80 MM THICK), Calbayog Samar 1st DEO City, Samar 1st DEO, DPWH Region VIII
Samar
Calbayog City
Daang Maharlika (SM) (Sn Isidro - Sn Juanico Br) K0686 + 805 - K0688 + DPWH RO8000,K0688 + 000 - K0689 + 000 Northern ASPHALT OVERLAY (80 MM THICK), Samar 1st DEO Northern Samar 1st DEO, DPWH Region VIII
Northern Samar
DPWH RO8Leyte 5th DEO
Road Opening/Upgrading of BurauenAlbuera Road including Bridges, Leyte - Burauen Side, Leyte 2nd District Bridges ROAD OPENING, CONCRETE/DistrictWide,Leyte 2nd District Engineering Office,Region VIII
Total Program Amount
AA Issued to Date
Funding Support (%)
Unpaid Obligations
Disbursement
(10)
(11)
Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
(7)
(8)
12/29/2014
25,000
25,000
100
5
7/4/2014
12/29/2014
23,000
23,000
100
5
6/16/2014
12/11/2014
45,000
45,000
100
18
11/7/2014
23,470
23,470
100
75
6/4/2014
6/14/2014
23,801
23,801
100
100
San Isidro
5/23/2014
9/19/2014
35,328
35,328
100
30
Leyte
Abuyog
5/21/2014
11/11/2014
30,000
30,000
100
48
DPWH RO8
Leyte
Burauen
5/20/2014
2/13/2015
100,000
100,000
100
6.02
Construction/Upgrading of Baybay City Diversion Road, including Bridges and ROW, Roads & Bridges GRAVEL TO PAVED, Baybay, Leyte 5th DEO, DPWH Region VIII
DPWH RO8
Leyte
Baybay
5/20/2014
4/2/2015
150,000
150,000
100
12.5
San Juanico-Basey-Sohoton Road, K0896+(-934) - K0908+222, with exceptions WIDENING-PAVED, Basey, Samar 2nd DEO, DPWH Region VIII
DPWH RO8 Samar 2nd DEO
Samar
Basey
5/10/2014
8/30/2014
20,000
20,000
100
35
Construction of Junction AbuyogSilago Road-Cadac-an-Malaguicay Road Section (Malaguicay Falls), GRAVEL TO PAVED, Abuyog, Leyte 5th DEO, DPWH Region VIII
(9)
Physical (%)
Financial (PhP '000)
Employment Generated (man-days)
Remarks
(18)
(19)
Location Project Title
Agency
(1)
Basey-Marabut-Pinamitinan Road, K0912+689 - K0914+479 WIDENING - PAVED/DistrictWide,Samar 2nd District Engineering Office,Region VIII
Schedule Target Date Started Completion Date
Province
Municipality/City
(2)
(3)
(4)
DPWH RO8 Samar 2nd DEO
Samar
Basey
5/10/2014
Higatangan Circumferential Road leading to Higatangan Island, Naval, Biliran GRAVEL TO PAVED, Biliran DEO, DPWH Region VIII
DPWH RO8
Biliran
Naval
Access Road to Borongan-Llorente Closed Canopy Forest Area, Maydolong, Eastern Samar GRAVEL TO PAVED, Eastern Samar DEO, DPWH Region VIII
DPWH RO8 Easter Samar DEO
Eastern Samar
Widening of Government Center Road Network (S00047LT), K0912+(-250)- DPWH RO8 K0913+595 WIDENING - PAVED, Leyte 1st DEO Palo, Leyte 1st DEO, Region VIII
(5)
(6)
Total Program Amount
AA Issued to Date
Funding Support (%) (9)
Physical (%)
Financial (PhP '000) Unpaid Obligations
Disbursement
(10)
(11)
Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
(7)
(8)
8/30/2014
20,000
20,000
100
30
5/9/2014
12/31/2014
100,000
100,000
100
5
Maydolong
4/28/2014
11/5/2014
50,000
50,000
100
20
Leyte
Palo
4/23/2014
8/19/2014
15,500
15,500
100
68.81
Mainit-Sn Miguel-Santol Road K0947+558 - K0947+944,K0948+000 - K0948+846,K0950+362 DPWH RO8 K0950+399,K0949+758 - K0950+042 Leyte 1st DEO GRAVEL TO PAVED, Leyte 1st DEO, DPWH Region VIII
Leyte
San Miguel
4/23/2014
8/21/2014
39,210
39,210
100
78
Leyte-Samar Inter-Prov'l Road K0907+368 - K0908+000,K0908+642 DPWH RO8 - K0908+754, K0908+816 Leyte 1st DEO K0909+216 GRAVEL TO PAVED, Leyte 1st DEO, DPWH Region VIII
Leyte
Babatngon
4/23/2014
7/22/2014
28,221
28,221
100
56
Road Opening/Upgrading of BurauenAlbuera Road including Bridges, Albuera Side, ROAD OPENING, CONCRETE, Leyte 4th DEO, DPWH Region VIII
DPWH RO8
Leyte
Albuera
4/21/2014
11/6/2014
72,000
72,000
100
15
Road Opening/Upgrading of BurauenAlbuera Road including Bridges, Albuera Side, ROAD OPENING, CONCRETE, Leyte 4th DEO, DPWH Region VIII
DPWH RO8
Leyte
Albuera
4/21/2014
12/13/2014
100,000
100,000
100
6.88
Road from Brgy. Ngolos-Brgy. Sulangan (Guiuan-Sulangan Road), Guiuan, Eastern Samar GRAVEL TO PAVED, Eastern Samar DEO, DPWH Region VIII
DPWH RO8
Eastern Samar
Guiuan
4/18/2014
1/2/2015
120,000
120,000
100
32.61
Limasawa Circumferential Road, Limasawa, Southern Leyte GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII
DPWH RO8 Southern Leyte DEO
Southern Leyte
Limasawa
4/15/2014
10/10/2014
32,000
32,000
100
62
Road leading to Danao Camp Tree Park, Maasin City, Southern Leyte GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII
DPWH RO8
Southern Leyte
Maasin City
4/14/2014
11/19/2014
88,000
88,000
100
91.5
Palo-Carigara-Ormoc Road, K0957 + 100 - K0957 + 360, K0964 + 000 K0967 + 764.8, K0974 + 753 K0979 + 000 PAVED TO PAVED, Leyte 2nd DEO, DPWH Region VIII
DPWH RO8
Leyte
Carigara
4/14/2014
10/17/2014
95,744
95,744
100
20.12
Employment Generated (man-days)
Remarks
(18)
(19)
Location Project Title
Agency
(1)
(2)
Province
Municipality/City
(3)
(4)
Road Slip along Pangpang-PalapagMapanas-Gamay-Lapinig Road, K000+000 - K0000+065, Brgy. Cadac- DPWH RO8 an, Gamay Section, K0804+200 Northern K0820+600,K0834+600 Samar 2nd K0834+800,K0856+500 - K0859+000 DEO PAVED TO PAVED, Northern Samar 2nd DEO, DPWH Region VIII
Northern Samar
Gamay
Road Slip along Catarman-Laoang Road - K0767+000 - K0768+000 (with exception), San Roque Section,K0773+800 - K0774+000 (with exception), Pambujan Section,K0783+000 - K0784+000 (with exception), Brgy. Burabod, Laoang Section PAVED TO PAVED, Northern Samar 2nd DEO, DPWH Region VIII
DPWH RO8 Northern Samar 2nd DEO
Northern Samar
Const/Repair/Rehab/Impvt of VILPs Construction of City Library, Baybay City, CONSTRUCTION, Leyte 5th DEO, DPWH Region VIII
DPWH RO8 Leyte 5th DEO
Leyte
Baybay City
Palo-Carigara-Ormoc Road, K0948+250 - K0951+450, Brgy. San Vicente-Brgy. Abango, Tunga & Barugo, Leyte CONCRETING OF SHOULDER, Leyte 2nd DEO, DPWH Region VIII
DPWH RO8 Leyte 2nd DEO
Leyte
Bagahupi-Babatngon-Sta Cruz-BarugoCarigara Road, K0931+420 DPWH RO8 K0932+244, GRAVEL TO PAVED, Leyte 2nd DEO Leyte 2nd DEO, DPWH Region VIII Dulag-Julita-Burauen Road, K0941+000 - K0944+214, Brgy. San Vicente - Brgy. Del Pilar, Dulag, Leyte, CONCRETING OF SHOULDER, Leyte 2nd DEO, DPWH Region VIII Road Opening/Construction of Arteche, Brgy. Catumsan-Jipapad-Las Navas-Catubig-Rawis Road (including Bridges and ROW), ROAD OPENING, CONCRETE, Eastern Samar DEO, DPWH Region VIII Road Slip along Tacloban-Baybay South Road, K0990+500 K0990+600, Maihi Section,K0986+650 - K0986+750, Nebga Section, PAVED TO PAVED, Leyte 5th DEO, DPWH Region VIII Merida-Lundag-Puting BatoConsolacion-Isabel Rd, K1111+315K1111+660; K1112+271K1112+419; K1118+290K1118+543; K1120+000-K1121+117 & K1112+419-K1112+719, GRAVEL TO PAVED,Merida, Leyte 4th DEO, DPWH Region VIII
Schedule Target Date Started Completion Date (5)
(6)
Total Program Amount
AA Issued to Date
(7)
(8)
Funding Support (%) (9)
Physical (%)
Financial (PhP '000) Unpaid Obligations
Disbursement
(10)
(11)
Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
4/10/2014
10/5/2014
40,000
40,000
100
40.21
San Roque/Pambujan/ 4/10/2014 Laoang
9/16/2014
30,000
30,000
100
84.88
4/2/2014
9/23/2014
30,000
30,000
100
10
Tunga/Barugo
3/28/2014
9/4/2014
28,000
28,000
100
75
Leyte
Barugo
3/28/2014
10/3/2014
21,000
21,000
100
63
DPWH RO8 Leyte 2nd DEO
Leyte
Dulag
3/24/2014
9/19/2014
25,000
25,000
100
75 %
DPWH RO8
Eastern Samar
Arteche
3/20/2014
11/11/2014
100,000
100,000
100
41.16
DPWH RO8 Leyte 5th DEO
Leyte
Baybay City
3/19/2014
9/13/2014
20,000
20,000
100
89
DPWH RO8
Leyte
Merida
3/14/2014
11/5/2014
65,638
65,638
100
33.68
Employment Generated (man-days)
Remarks
(18)
(19)
Location Project Title
Agency
Province
Municipality/City
Schedule Target Date Started Completion Date
(1)
(2)
(3)
(4)
Jct. Taft-Oras-San Policarpo-Arteche Road, K0881+(-117)-K0900+435, K0900+435-K0908+000, K0909+000K0912+1120, K0914+1403K0919+000, K0920+949-K0926+000, K0943+950-K0950+000, K0950+000K0957+000 CONCRETING OF SHOULDER, Eastern Samar DEO, DPWH Region VIII
(5)
(6)
DPWH RO8
Eastern Samar
Taft
3/7/2014
10/17/2014
Widening of Biliran Circumferential Road, Biliran Lone District, K1026+330 - K1027+830, NavalAlmeria Section, WIDENING - PAVED, Biliran District Engineering Office, DPWH Region VIII
DPWH RO8 Biliran DEO
Biliran
Naval
3/7/2014
9/2/2014
DPWH RO8 Leyte 2nd DEO
Leyte
Burauen
3/7/2014
8/28/2014
Biliran Circumferential Road, K1110+000 - K1116+000, SangalangDPWH RO8 Biliran Section, CONCRETING OF Biliran DEO SHOULDER, Biliran DEO, DPWH Region VIII
Biliran
Biliran
3/3/2014
Biliran Circumferential Road, K1018+000 - K1023+000, CatmonCaraycaray Section, CONCRETING OF SHOULDER, Biliran DEO, DPWH Region VIII
DPWH RO8 Biliran DEO
Biliran
Naval
Construction/Improvement (Concreting) of Catbalogan City Diversion Road, GRAVEL TO PAVED, Samar 2nd DEO, DPWH Region VIII
DPWH RO8
Samar
Tabango-Catmon-La FortunaManlawaan-Gimarco Road, K1033+242 - K1039+287.56 GRAVEL TO PAVED, Tabango, Leyte 3rd DEO, DPWH Region VIII
DPWH RO8
Construction/Rehabilitation of Flood Control Structure, Brgy. Mag-ubay, Oquendo District, Calbayog City, CONSTRUCTION, Samar 1st DEO, DPWH Region VIII Calbayog Old National Route, Calbayog City, CONCRETING OF SHOULDER, Samar 1st DEO, DPWH Region VIII
Total Program Amount (7)
AA Issued to Date (8)
Funding Support (%) (9)
Physical (%)
Financial (PhP '000) Unpaid Obligations
Disbursement
(10)
(11)
Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
124,315
124,315
100
42
45750
45,750
100
57
48,889
48,889
100
70
9/30/2014
23,860
23,860
100
50
3/3/2014
9/3/2014
23,910
23,910
100
40
Catbalogan City
2/28/2014
10/15/2014
80,000
80,000
100
8.47
Leyte
Tabango
2/28/2014
11/14/2014
149,510
149,510
100
33.55
DPWH RO8 Samar 1st DEO
Samar
Calbayog City
2/24/2014
9/19/2014
25,000
25,000
100
25
DPWH RO8 Samar 1st DEO
Samar
Calbayog City
2/24/2014
7/25/2014
20,000
20,000
100
48
Widening of Daang Maharlika (San Isidro-San Juanico Bridge), DPWH RO8 K0769+000 - K0771+000, San Jorge, Samar 1st DEO Samar, WIDENING - PAVED, Samar 1st DEO, DPWH Region VIII
Samar
San Jorge
2/24/2014
7/24/2014
50,000
50,000
100
53
Jaro-Dagami-Burauen-Lapaz Road, K0951+217 - K0951+480, K0951+530 - K0951+664, K0951+765 - K0951+920, K0957+657 - K0958+841, K0959+025 - K0959+363, GRAVEL TO PAVED, Leyte 2nd DEO, DPWH Region VIII
Employment Generated (man-days)
Remarks
(18)
(19)
Location Project Title
Agency
(1)
(2)
Province
Municipality/City
Schedule Target Date Started Completion Date
(3)
(4)
Tinambacan Br. along Daang Maharlika (SM) (Sn Isidro-San Juanico Br.) DPWH RO8 RETROFITTING/REHABILITATION/ST Samar 1st DEO RENGTHENING,Calbayog City, Samar 1st DEO, DPWH Region VIII
(5)
Samar
Sta. Margarita
2/24/2014
Widening of Gomez Extension, Calbayog City, WIDENING - PAVED, Samar 1st DEO, DPWH Region VIII
DPWH RO8 Samar 1st DEO
Samar
Calbayog City
Const/Repair/Rehab/Impvt of VILPs Construction of Gandara-Matuguinao DPWH RO8 Road, Sta. 00+000 - Sta. 22+000, Samar 1st DEO GRAVEL TO PAVED, Gandara, Samar 1st DEO, DPWH Region VIII
Samar
Daang Maharlika (SM) (Sn Isidro - Sn Juanico Br) K0710 +650 - K0711 + 250,K0694 + 762 - K0695 + DPWH RO8 450,K0701 + 050 - K0701 + 216 Samar 1st DEO ASPHALT OVERLAY (80 MM THICK), Samar 1st DEO, DPWH Region VIII
(6)
Total Program Amount
AA Issued to Date
Funding Support (%) (9)
Physical (%)
Financial (PhP '000) Unpaid Obligations
Disbursement
(10)
(11)
Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
(7)
(8)
8/22/2014
25,602
25,602
100
32
2/24/2014
7/1/2014
25,000
25,000
100
76
Gandara
2/24/2014
6/23/2014
50,000
50,000
100
72
Samar
Sta. Margarita
2/24/2014
4/28/2014
24,233
24,233
100
100
Cagmanipis Br. along Daang Maharlika (SM) (Sn Isidro-Sn Juanico DPWH RO8 Br.) RETROFITTING/REHABILITATION/ST Samar 1st DEO RENGTHENING, Samar 1st DEO, DPWH Region VIII
Samar
Calbayog City
2/24/2014
8/22/2014
30,000
30,000
100
64
Construction/Rehabilitation of Monbon Flood Control Structure, Brgy. DPWH RO8 Monbon, Sta. Margarita, Samar, Samar 1st DEO CONSTRUCTION, Samar 1st DEO, DPWH Region VIII
Samar
Sta. Margarita
2/24/2014
8/12/2014
20,000
20,000
100
69
Construction/Rehabilitation of Flood Control Structure,Calbayog City, Minlawa-an (Phase II), Brgy. San Policarpo, CONSTRUCTION, Samar 1st DEO, DPWH Region VIII
DPWH RO8 Samar 1st DEO
Samar
Calbayog City
2/24/2014
8/12/2014
20,000
20,000
100
80
Construction/Rehabilitation of Flood Control Structure,Calbayog City, Cagnipa (Phase II), Brgy. Cagnipa, Tinambacan District, CONSTRUCTION, Samar 1st DEO, DPWH Region VIII
DPWH RO8 Samar 1st DEO
Samar
Calbayog City
2/24/2014
8/13/2014
20,000
20,000
100
85
Rehabilitation/Improvement of Drainage System along Daang DPWH RO8 Maharlika, K0762+500 - K0767+500, Samar 1st DEO OTHERS, Gandara, Samar 1st DEO, DPWH Region VIII
Samar
Gandara
2/24/2014
8/19/2014
28,496
28,496
100
78
Road Opening/Construction of Jct. Himay-angan-Silago-Abuyog DPWH RO8 Boundary Road (Bagacay-Bulak), Leyte 5th DEO K1137 + 000 - K1042 + 000, ROAD OPENING, CONCRETE, Abuyog, Leyte 5th DEO, DPWH Region VIII
Leyte
Abuyog
2/24/2014
8/17/2014
30,000
30,000
100
91
Construction of Flood Control DPWH RO8 Structure, Calbayog City, Brgy. Bugtong, CONSTRUCTION, Samar 1st Samar 1st DEO DEO, DPWH Region VIII
Samar
Calbayog City
2/24/2014
8/14/2014
25,000
25,000
100
92
Employment Generated (man-days)
Remarks
(18)
(19)
Location Project Title
Agency
(1)
Schedule Target Date Started Completion Date
Total Program Amount
AA Issued to Date
Funding Support (%)
Physical (%)
Financial (PhP '000) Unpaid Obligations
Disbursement
(10)
(11)
Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
Province
Municipality/City
(2)
(3)
(4)
DPWH RO8
Leyte
Leyte
2/17/2014
10/19/2014
111,084
111,084
100
28.98
Das-ay Br. along Jct Himay-anganDPWH RO8 Silago-Abuyog Bdry Road, RETROFITTING/REHABILITATION/ST Southern Leyte DEO RENGTHENING, Southern Leyte DEO, DPWH Region VIII
Southern Leyte
Silago
2/14/2014
10/11/2014
20,000
20,000
100
95
Improvement/Widening of Access Road leading to Benit Port (Saddle Area), San Ricardo, Southern Leyte, WIDENING - PAVED, Southern Leyte DEO, DPWH Region VIII
DPWH RO8 Southern Leyte DEO
Southern Leyte
San Ricardo
2/14/2014
10/11/2014
20,000
20,000
100
72.84
Construction/Rehabilitation of Antiao River Control, Catbalogan City, Samar, CONSTRUCTION, Samar 2nd DEO, DPWH Region VIII
DPWH RO8
Samar
Catbalogan City
2/14/2014
9/11/2014
75,000
75,000
100
50.25
San Ricardo-Bilatan Road, K1101+000 - K1102+000, GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII
DPWH RO8 Southern Leyte DEO
Southern Leyte
San Ricardo
2/14/2014
9/10/2014
37,900
37,900
100
70
Jct Himay-angan-Silago-Abuyog Bdry Road, K1136+(-183) - K1137+000, GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII
DPWH RO8 Southern Leyte DEO
Southern Leyte
Silago
2/14/2014
9/10/2014
27,400
27,400
100
42
Bagacay Old Route, Chainage 0000 Chainage 1225, PAVED TO PAVED, Samar 2nd DEO, DPWH Region VIII
DPWH RO8 Samar 2nd DEO
Samar
Hinabangan
2/13/2014
8/31/2014
20,753
20,753
100
30
Daang Maharlika (SM) (Sn Isidro - Sn Juanico Br) K0825 + 344 - K0826 + 656, ASPHALT OVERLAY (80 MM THICK), Samar 2nd DEO, DPWH Region VIII
DPWH RO8 Samar 2nd DEO
Samar
Sta. Rita
2/13/2014
8/13/2014
21,891
21,891
100
75
Dolongan-Basey Road, Chainage 1391-Chainage 2816, GRAVEL TO PAVED, Samar 2nd DEO, DPWH Region VIII
DPWH RO8 Samar 2nd DEO
Samar
Basey
2/13/2014
8/13/2014
31,562
31,562
100
33
Widening of Naval-Caibiran Cross Country Road, K1029+000 K1030+600, San Juan-Poro Kube Section, WIDENING - PAVED, Biliran DEO, DPWH Region VIII
DPWH RO8 Biliran DEO
Biliran
Caibiran
2/12/2014
9/9/2014
48,300
48,300
100
37
Widening of Biliran Circumferential Road, K1067+300 - K1068+300, Virginia-Culaba Proper, WIDENING PAVED, Biliran DEO, DPWH Region VIII
DPWH RO8 Biliran DEO
Biliran
Culaba
2/6/2014
9/4/2014
31,350
31,350
100
45
DPWH RO8
Leyte
San Isidro
1/30/2014
9/23/2014
50,750
50,750
100
73
Cabunga-an-Tabunok-Consuegra Rd Chainage 000 -Chainage 2860, K1014+(-403) - K1014+(361),K1017+597 - K1018+878, GRAVEL TO PAVED, Leyte 3rd DEO, DPWH Region VIII
Sn Isidro-Daja Road, K1018+(-497)K1018+(-427), K1018+959K1019+403, K1024+083-K1025+047, K1025+573-K1026+138, GRAVEL TO PAVED, San Isidro, Leyte 3rd DEO, DPWH Region VIII
(5)
(6)
(7)
(8)
(9)
Employment Generated (man-days)
Remarks
(18)
(19)
Location Project Title
Agency
(1)
(2)
Province
Municipality/City
Schedule Target Date Started Completion Date
(3)
(4)
Tabing - Kawayan - Sta Rosa - Lawis Tabango Road, K1032+610 DPWH RO8 K1033+222,K1035+188 Leyte 3rd DEO K1035+1033, GRAVEL TO PAVED, Leyte 3rd DEO, DPWH Region VIII
(5)
Leyte
San Isidro
1/30/2014
Calubian Jct-Sn Isidro-TabangoVillaba-Palompon Road, K1015+818 K1016+000, K1016+000 K1016+530, K1016+676 - K1017+ DPWH RO8 000, K1027+000 - K1028+000, Leyte 3rd DEO K1029+100 - K1029+900, K1030+000 - K1031+000, K1031+000-1031+300, K1033+700 K1034+479, Leyte 3rd DEO, DPWH Region VIII
Leyte
San Isidro
Calubian Jct-San Isidro-TabangoVillaba-Palompon Road, K1006+557 - DPWH RO8 K1007+490, GRAVEL TO PAVED, Leyte 3rd DEO Leyte 3rd DEO, DPWH Region VIII
Leyte
Jct. Buenavista-Lawaan-Marabut DPWH RO8 Road, K0959+828-K0996+238, Eastern Samar CONCRETING OF SHOULDER, Eastern DEO Samar DEO, DPWH Region VIII
(6)
Total Program Amount
AA Issued to Date
Funding Support (%) (9)
Physical (%)
Financial (PhP '000) Unpaid Obligations
Disbursement
(10)
(11)
Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
(7)
(8)
8/26/2014
42,561
42,561
100
88
1/30/2014
8/26/2014
28,267
28,267
100
85
Tabango
1/30/2014
8/26/2014
28,410
28,410
100
88
Eastern Samar
Lawaan
1/29/2014
7/2/2014
44,578
44,578
100
95
Sambulawan Jct. - Calaguise Calubian Road, K0992+400 K0993+493, K1003+390 K1003+914, K0997+395 K0997+603, GRAVEL TO PAVED, Leyte 3rd DEO, DPWH Region VIII
DPWH RO8 Leyte 3rd DEO
Leyte
Leyte
1/27/2014
8/23/2014
46,890
46,890
100
95
Burauen-Mahagnao Road, K0984+241 - K0985+1064, GRAVEL TO PAVED, Leyte 2nd DEO, DPWH Region VIII
DPWH RO8 Leyte 2nd DEO
Leyte
Burauen
1/24/2014
8/14/2014
49,000
49,000
100
90
Construction/Rehabilitation of Drainage Sytem/Protection Works along Palo-Carigara-Ormoc Road, K0975+000 - K0983+255 (with exception), CONSTRUCTION, Leyte 2nd DEO, DPWH Region VIII
DPWH RO8 Leyte 2nd DEO
Leyte
Carigara
1/23/2014
9/9/2014
19,710
19,710
100
80
Widening of Daang Maharlika (LT), K0915+411 - K0916+911,K0919+754 DPWH RO8 - K0920+300.15, WIDENING Leyte 1st DEO PAVED, Leyte 1st DEO, DPWH Region VIII
Leyte
Palo
1/17/2014
7/31/2014
37,413
37,413
100
89.8
Widening of Pawing-Campetic Road, K0917+(-334) - K0917+986, WIDENING - PAVED, Leyte 1st DEO, DPWH Region VIII
DPWH RO8 Leyte 1st DEO
Leyte
Palo
1/17/2014
6/13/2014
24,000
24,000
100
77 %
Road Opening of San MiguelBabatngon-Tacloban City Road along Bagahupi-Babatngon-Sta. CruzCaraycaray Section, ROAD OPENING, CONCRETE, Leyte 1st DEO, DPWH Region VIII
DPWH RO8 Leyte 1st DEO
Leyte
Babatngon
1/17/2014
8/15/2014
50,000
50,000
100
97.5
Expansion, Polompon District Hospital (Dr. Manuel B. Veloso Memorial DPWH RO8 Hospital), CONSTRUCTION, Leyte 4th Leyte 4th DEO DEO, DPWH Region VIII
Leyte
Palompon
12/2/2013
8/21/2014
20,000
20,000
100
32
Employment Generated (man-days)
Remarks
(18)
(19)
Location Project Title
Agency
(1)
Province
Municipality/City
Schedule Target Date Started Completion Date
(2)
(3)
(4)
Rehabiliation/Improvement along Magsaysay Boulevard, K0909+124K0910+(-343), Tacloban City, GRAVEL TO PAVED, Tacloban City DEO, DPWH Region VIII
DPWH RO8 Tacloban City DEO
Leyte
Tacloban City
6/17/2013
Ormoc Flood Mitigation Project, CONSTRUCTION,Ormoc City, DPWH Regional Office VIII
DPWH RO8
Leyte
Ormoc City
Matag-ob-Palompon Road (LibungaoMatag-ob-Palompon Section), Matagob & Palompon, Leyte, GRAVEL TO PAVED, DPWH Regional Office VIII
DPWH RO8
Leyte
Widening of Ormoc-Baybay-Southern Leyte Bdry Road, K1038 + (-732) K1038 + 000, K1039 + 000 - K1040 + 000, K1041 + 000 - K1042 + 000, K1043 + 000 - K1049 + 000, ASPHALT OVERLAY (80 MM THICK), Leyte 5th DEO, DPWH Region VIII
DPWH RO8
Biliran Circumferential Road, K1008 + 000 - K1008 + 1000, K1011 + 000 K1016 + 000, K1018 + 100 - K1019 + 600, K1019 + 750 - K1021 + 115, ASPHALT OVERLAY (50 MM THICK), Biliran DEO, DPWH Region VIII
DPWH RO8
Funding Support (%)
Unpaid Obligations
Disbursement
(10)
(11)
Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
1/6/2014
35,635
35,635
100
25
2/27/2013
10/3/2014
92,700
92,700
100
75
Palompon
2/21/2013
3/7/2014
150,000
150,000
100
76.27
Leyte
Baybay City
2/19/2013
6/3/2014
99,730
99,730
100
89.48
Biliran
Biliran
2/15/2013
12/26/2013
63,598
63,598
100
44.69
Northern Samar
San Antonio
2/7/2013
11/3/2013
46,368
46,368
100
80
DPWH RO8
Leyte
Ormoc City
2/7/2013
12/19/2014
150,000
150,000
100
70
DPWH RO8 Eastern Samar DEO
Eastern Samar
Balangiga
12/13/2013 7/24/2014
29,000
29,000
100
85
Rehabilitation of San Juanico Bridge along Daang Maharlika, RETROFITTING/REHABILITATION/ST RENGTHENING, Leyte 1st DEO, DPWH Region VIII
DPWH RO8
Leyte
Tacloban City
9/17/2013
8/1/2014
43,785
43,785
100
88.87
Improvement/Upgrading of LibungaoMatag-ob-Palompon Road, K0990+961-K1024+688, with exceptions, Kanganga, Matag-ob and Palompon, GRAVEL TO PAVED, Leyte 4th DEO, DPWH Region VIII
DPWH RO8
Leyte
Palompon
9/17/2013
8/15/2014
100,000
100,000
100
90
Leyte
Burauen
3/19/2013
3/7/2014
50,000
50,000
100
75
Rehabilitation of Seawall located at Brgys. 04, 05, and 06, Balangiga, Eastern Samar, REHABILITATION, Eastern Samar DEO, DPWH Region VIII
Road Opening Burauen-Albuera Road DPWH RO8 Including Bridges, Burauen Side, Leyte 2nd DEO ROAD OPENING, CONCRETE, Leyte 2nd DEO, DPWH Region VIII
(9)
Physical (%)
Financial (PhP '000)
(8)
Construction of Ormoc Diversion Road includings & Bridges & ROW, Ormoc City, WIDENING - PAVED, DPWH Regional Office VIII
(6)
AA Issued to Date
(7)
San Antonio Circumferential Road, K0001+919-K0003+765, K0004+655- DPWH RO8 K0004+737, K0004+748-K0005+280, Northern GRAVEL TO PAVED, Northern Samar Samar 1st DEO 1st DEO, DPWH Region VIII
(5)
Total Program Amount
Employment Generated (man-days)
Remarks
(18)
(19)
Location Project Title
Agency
(1)
Province
Municipality/City
Repair/Rehabilitation/Construction of Drainage System along Government Center Road Network, Maharlika Highway and Pawing-Campetic Road, Brgy. Candahug to Brgy. Pawing, Palo, OTHER IMPVT WORKS(SLOPE PROTECTION, DRAINAGE, SIDEWALKS), Leyte 1st DEO,DPWH Region VIII
(2)
(3)
(4)
DPWH RO8 Leyte 1st DEO
Leyte
Palo
Const. of Hibatian Bridge and approaches, Silago, So. Leyte GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII
DPWH RO8
Southern Leyte
Const. of Lawaan Bridge and approaches, Silago, So. Leyte GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII
DPWH RO8
Const. of Bagacay Bridge and approaches, Silago, So. Leyte GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII
Schedule Target Date Started Completion Date (5)
AA Issued to Date
Funding Support (%)
Unpaid Obligations
Disbursement
(10)
(11)
Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
(8)
3/15/2014
40,000
40,000
100
100
Silago
10/25/2012 3/10/2014
17,504
17,504
100
80.688
Southern Leyte
Silago
10/25/2012 3/10/2014
32,685
32,685
100
77.092
DPWH RO8
Southern Leyte
Silago
10/25/2012 3/10/2014
21,153
21,153
100
81.32
Const. of Bil-atan Bridge and Approaches, San Ricardo, So. Leyte GRAVEL TO PAVED, Southern Leyte DEO, DPWH Region VIII
DPWH RO8
Southern Leyte
San Ricardo
10/25/2012 3/10/2014
30,207
30,207
100
78.536
Construction of Pinut-an Bridge and Approaches, CONSTRUCTION OF NEW BRIDGE, Southern Leyte DEO, DPWH Region VIII
DPWH RO8
Southern Leyte
San Ricardo
10/25/2012 3/10/2014
32,524
32,524
100
19.22
Listing Bridge and Approaches, San Isidro, RETROFITTING/ REHABILITATION/ STRENGTHENING, Leyte 3rd DEO, DPWH Region VIII
DPWH RO8
Leyte
San Isidro
10/10/2012 10/9/2013
14,184
14,184
100
96.5
Tugas Bridge and Approaches, Tabango, CONSTRUCTION OF NEW BRIDGE, Leyte 3rd DEO, DPWH Region VIII
DPWH RO8
Leyte
Tabango
10/10/2012 10/9/2013
17,730
17,730
100
93.25
Lawis Bridge and Approaches, Tabango, CONSTRUCTION OF NEW BRIDGE, Leyte 3rd DEO, DPWH Region VIII
DPWH RO8
Leyte
Tabango
10/10/2012 10/9/2013
14,184
14,184
100
95.7
Consuerga Bridge and Approaches, Leyte, CONSTRUCTION OF NEW BRIDGE, Leyte 3rd DEO, DPWH Region VIII
DPWH RO8
Leyte
Leyte
8/10/2012
8/9/2013
21,276
21,276
100
95.03
Belen Bridge and Approaches, Leyte, CONSTRUCTION OF NEW BRIDGE, Leyte 3rd DEO, DPWH Region VIII
DPWH RO8
Leyte
Leyte
8/10/2012
11/26/2013
21,276
21,276
100
99.47
Gaps along Lapinig-Arteche Road, GRAVEL TO PAVED, DPWH Regional Office VIII
DPWH RO8
Northern and Eastern Samar
11/4/2013
200,000
200,000
100
95.1
Pangpang-Palapag-Mapanas-GamayLapinig Road, K0838+000 K0838+400, K0846+208-K0847+440, K0848+200 - K0849+820 &K0809+573 - K0811+201, with exceptions GRAVEL TO PAVED, Northern Samar 2nd DEO, DPWH Region VIII
DPWH RO8
Northern Samar
11/15/2013
97,853
97,853
100
76.87
Lapinig & Arteche 7/30/2012
Palapag
4/30/2012
(9)
Physical (%)
Financial (PhP '000)
(7)
2/20/2013
(6)
Total Program Amount
Employment Generated (man-days)
Remarks
(18)
(19)
Location Project Title
Agency
(1)
Province
Municipality/City
Schedule Target Date Started Completion Date
(8)
(9)
Physical (%)
Financial (PhP '000) Unpaid Obligations
Disbursement
(10)
(11)
Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
(3)
(4)
DPWH RO8
Samar
Catbalogan City
3/5/2012
4/28/2013
100,000
100,000
100
95
Ormoc Diversion Road, GRAVEL TO PAVED, DPWH Regional Office VIII
DPWH RO8
Leyte
Ormoc City
2/29/2012
11/18/2014
100,000
100,000
100
79.95
Eastern Samar
San Policarpo
1/26/2012
1/19/2013
29,340
29,340
100
95
Leyte
Carigara
3/27/2012
10/3/2013
114,281
114,281
100
95
DPWH RO8
(7)
Funding Support (%)
(2)
Reconstruction of Carigara Bridge along Palo-Carigara-Ormoc Road, Carigara, REPLACEMENT OF DAMAGED BRIDGE, Leyte 2nd DEO, DPWH Region VIII
(6)
AA Issued to Date
Catbalogan Diversion Road, ROAD OPENING, CONCRETE, DPWH Regional Office VIII
Alugan Bridge 4 along Jct Taft-OrasDPWH RO8 Sn Policarpo-Arteche Road, REPLACEMENT OF DAMAGED BRIDGE Eastern Samar ,Eastern Samar DEO, DPWH Region DEO VIII
(5)
Total Program Amount
Employment Generated (man-days)
Remarks
(18)
(19)
PMC Form O-2 FINANCIAL AND PHYSICAL STATUS OF CAPITAL INVESTMENT PROGRAMS/PROJECTS As of 31 December 2014 Eastern Visayas (Region VIII) Location Project Title
Agency
(1)
Schedule Target Completion Date
Financial (PhP '000) Funding Unpaid Disburseme Support Obligatio nt (%) ns
Physical (%)
Employment Generated (man-days)
Remarks
(18)
(19)
Total Program Amount
AA Issued to Date
(6)
(7)
(8)
01 Jul 2013
06 Jun 2014
837,651.30
Paranas/ Taft/ Sulat
01 Jul 2013
31 Mar 2016
2,500,000.01
45.18
16.82
-28.36
37.23
Project behind schedule
San Julian/ Borongan/ Maydolong/ Balangkayan
20 Sep 2012
23 Oct 2015
2,455,881.55
70.97
65.86
-5.11
92.80
Project behind schedule
Llorente/Hernani/G en.MacArthur/ 16 Apr 2013 Quinapondan/ Salcedo/Mercedes/ Guiuan
15 Apr 2016
2,200,000.00
32.11
30.66
-1.45
95.48
Project behind schedule
Expenditure Rate
Province
Municipality/City
Date Started
(2)
(3)
(4)
(5)
Contract Package 1: Road Rehabilitation, Buray Junction to Brgy. Tenani (16.36 km), Paranas, Samar
DPWH PMO-MCC
Samar
Paranas
Contract Package 2: Road Rehabilitation, Brgy. Tenani to Sulat/San Julian Mun. Boundary (63.78 km), Eastern Samar
DPWH PMO-MCC
Samar/ Eastern Samar
Contract Package 3: Road Rehabilitation, San Julian/Sulat Mun. Boundary to Balangkayan/Llorente Mun. Boundary (64.6 km), Eastern Samar
DPWH PMO-MCC
Eastern Samar
Contract Package 4: Road Rehabilitation, Balangkayan/Llorente Mun. Boundary to Guiuan (79.5 km), Eastern Samar
DPWH PMO-MCC
Eastern Samar
Palo-Carigara-Ormoc Road, PAVED (Concrete) TO PAVED (Concrete), Leyte 1st & 2nd DEOs, DPWH Region VIII
DPWH PMO-ADB
Leyte
Palo / Carigara
3/3/2014
8/24/2015
372,902
372,902
100
1.193
Daang Maharlika Road (Liloan-Naval Highway), PAVED (CONCRETE) TO PAVED (CONCRETE), Leyte 1st & 2nd DEOs, DPWH Region VIII
DPWH PMO-ADB
Leyte
Palo / Carigara
3/3/2014
8/24/2015
239,115
239,115
100
1.193
Calbayog-Catarman Road, K0803+950-K0809+801 with exception (AWPI/PM-06A-2), Samar 1st DEO, DPWH Region VIII
DPWH PMO-J-RUPP
Samar
Calbayog City
2/17/2014 12/20/2014
96,277
96,277
100
23.862
Calbayog-Catarman Road, K0797+316-K0803+950 with exception (AWPI/PM-06A-1), Samar 1st DEO, DPWH Region VIII
DPWH PMO-J-RUPP
Samar
Calbayog City
2/17/2014 11/28/2014
108,064
108,064
100
37.324
AWP for 1st Yr. (150 km) (AWP-1), Daang Maharlika, Calbayog-Catarman DPWH Road, K0795+446 to K0784+739 w/ PMO-J-RUPP exception (AWP 1/PM-06B), Samar 1st DEO, DPWH Region VIII
Samar
Calbayog City
1/2/2014
116,244
116,244
100
18.078
11/18/2014
(9)
(10)
(11)
Total
(12)=(10+ (13)=(12/7) 11)
Target
Actual
(14)
(15)
Slippage
Performance
(16)=(15-14) (17)=(15/14)
Substantially Completed
98.24
Colab-og-Lungib-BuenasuertePasabuena-Maxville Road, GRAVEL TO PAVED, Victoria, Northern Samar 1st DEO, DPWH Region VIII
DPWH PMO-MCC
Northern Samar
Victoria
11/12/201 6/18/2013 2
48,500
48,500
100
60
Tucdao Bridge and Approaches, Kawayan, Biliran DEO, DPWH Region VIII
DPWH PMO-Special Bridges
Biliran
Kawayan
2/13/2013 10/12/2013
20,252
20,252
100
62.18
Talibong Bridge and Approaches, Cabucgayan, Biliran DEO, DPWH Region VIII
DPWH PMO-Special Bridges
Biliran
Cabucgayan
1/13/2013 9/11/2013
24,802
24,802
100
29.81
PMC Form O-2 FINANCIAL AND PHYSICAL STATUS OF CAPITAL INVESTMENT PROGRAMS/PROJECTS As of 31 December 2014 Eastern Visayas (Region VIII)
Location
Schedule Target Municipality/City Date Started Completion Date
Total Program Amount
Financial (PhP '000) Funding Unpaid Disbursement Support Obligations (%)
Physical (%)
Project Title
Agency
(1)
(2)
(3)
HCAAPD-C-1, Construction of Hagbay Diversion Dam and Appurtenant Structures including Supply, Delivery and Stockpilling
NIA HCAAP-PMO
Northern Samar
Las Navas
7/2/2010
5/13/2014
231,888.88
231,888.88
100
29,800.64
29,800.64
12.85
100.00
HCAAPD-C-2, Construction of the remaining works of Bulao Diversion Dam and Appurtenant Structures including Supply, Delivery and Installation of Steel Gates
NIA HCAAP-PMO
Northern Samar
Las Navas
9/9/2011
1/5/2015
172,723.00
172,723.00
100
81,092.89
81,092.89
46.95
HCAAPD-C-3, Construction of Pinipisakan Siphonic Bridge Flume and Concrete Lining for Critical Portion of Catubig Right Main Canal
NIA HCAAP-PMO
Northern Samar
Las Navas
10/31/2012
12/11/2014
66,120.80
66,120.80
100
1,587.36
1,587.36
HCAAPD-C-4, Construction of Catubig Right Main Canal's Lateral 1, 3, 4 and 5 Structures and Creek Improvement
NIA HCAAP-PMO
Northern Samar
Las Navas
10/31/2012
5/10/2015
104,988.06
104,988.06
100
12,980.39
12,980.39
HCAAP-LCB-C2-2012, Construction of On-Farm Facilities (Pinipisakan IA)
NIA HCAAP-PMO
Northern Samar
Las Navas
11/24/2012
6/30/2014
15,995.36
15,995.36
100
HCAAP-LCB-C3-2012, Construction of On-Farm Facilities (Haremasan IA)
NIA HCAAP-PMO
Northern Samar
Las Navas
12/14/2012
8/30/2014
17,662.72
17,662.72
100
12,213.77
12,213.77
69.15
91.45
82.28
HCAAP-LCB-C4-2012, Construction of On-Farm Facilities (Robasan IA)
NIA HCAAP-PMO
Northern Samar
Las Navas
1/20/2013
6/30/2014
22,899.56
22,899.56
100
7,878.11
7,878.11
34.40
90.12
55.29
HCAAP-LCB-C5-2012, Construction of On-Farm Facilities (Saliba IA)
NIA HCAAP-PMO
Province
(4)
(5)
(6)
(7)
HELP for Catubig Agricultural Advancement Project (HCAAP) - Irrigation and Drainage Component
AA Issued to Date (8)
(9)
(10)
(11)
Employment Generated (man-days)
Remarks
(18)
(19)
Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
59.03
-40.97
59.03
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
77.54
46.95
-30.59
60.55
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
2.40
84.11
22.15
-61.96
26.33
Under suspension due to canal opening at CRMC effective November 2014.
12.36
34.54
23.98
-10.56
69.43
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
100
Project Completed
-9.17
89.97
Time extension still under evaluation. Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
-34.83
61.35
Time extension still under evaluation. Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
20.09
Time extension still under evaluation. Project under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
100
49.12
100
9.87
0
Northern Samar
Las Navas
5/18/2013
8/31/2014
22,899.56
22,899.56
100
1,305.57
1,305.57
5.70
-39.25
Pinipisakan IP-CP No.01-2013, Diversion Road to Catubig Left Main Canal (CLMC) Access Road
NIA Regional Office Northern Samar VIII
Las Navas
11/6/2013
7/23/2014
11,593.04
11,593.04
100
541.45
541.45
4.67
70.45
62.54
-7.91
88.77
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
Pinipisakan IP-CP No.02-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 20+000 to Sta. 22+585
NIA Regional Office Northern Samar VIII
Las Navas
6/26/2013
8/21/2014
29,804.85
29,804.85
100
14,955.99
14,955.99
50.18
85.45
86.93
1.48
101.73
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
Pinipisakan Irrigation Project (PIP)
Location Project Title
Agency
(1)
(2)
Province (3)
Schedule Target Municipality/City Date Started Completion Date (4)
(5)
(6)
Total Program Amount (7)
AA Issued to Date (8)
Financial (PhP '000) Funding Unpaid Disbursement Support Obligations (%) (9)
(10)
(11)
Physical (%) Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
Employment Generated (man-days)
Remarks
(18)
(19)
Pinipisakan IP-CP No.03-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 18+000 to Sta. 20+000
NIA Regional Office Northern Samar VIII
Las Navas
11/26/2013
8/15/2014
31,030.29
31,030.29
100
27.54
15.38
-12.16
55.85
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
Pinipisakan IP-CP No.04-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 15+800 to Sta. 18+000
NIA Regional Office Northern Samar VIII
Las Navas
11/8/2013
8/17/2014
25,700.46
25,700.46
100
25.64
10.99
-14.65
42.86
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
Pinipisakan IP-CP No.05-2013, NIA Preparatory Works for CLMC Lateral 4 Regional Office Northern Samar and Construction of Service Road at VIII Sta. 0+000 to Sta. 4+108
Las Navas
7/1/2013
8/17/2014
39,342.82
39,342.82
100
61.43
50.39
-11.04
82.03
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
Pipisakan IP-CP No.06-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 13+300 to Sta. 15+400
NIA Regional Office Northern Samar VIII
Las Navas
7/1/2013
1/27/2014
39,980.29
39,980.29
100
18.06
3.32
-14.74
18.38
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
Pinipisakan IP-CP No.07-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 12+000 to Sta. 13+300
NIA Regional Office Northern Samar VIII
Las Navas
7/1/2013
1/27/2014
28,306.65
28,306.65
100
27.54
30.17
2.63
109.55
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
Pinipisakan IP-CP No. 08-2013, NIA Preparatory Works for CLMC Lateral 3 Regional Office Northern Samar & Const of Service Road, Sta. 0+000 VIII to Sta. 1+500
Las Navas
11/7/2013
6/5/2014
25,734.33
25,734.33
100
14.91
0
-14.91
0.00
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
Pinipisakan IP-CP No. 09-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 9+900 to Sta. 12+000
NIA Regional Office Northern Samar VIII
Las Navas
6/28/2013
1/24/2014
37,032.67
37,032.67
100
20.51
5.83
-14.68
28.43
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
Pinipsakan IP-CP No. 10-2013, Preparatory Works for CLMC and Construction of Service Road at Sta. 8+600 to Sta. 9+900
NIA Regional Office Northern Samar VIII
Las Navas
6/28/2013
6/28/2014
30,069.46
30,069.46
100
21.47
6.84
-14.63
31.86
Under suspension due to typhoon Ruby and continuous unfavorable weather condition experienced at site.
11,985.93
11,985.93
100
34,880.16
34,880.16
100
Mondragon
92,150.00
92,150.00
100
98
90.09
-7.91
91.93
Project still ongoing.
San Roque
138,225.00
138,225.00
100
71.93
80.15
8.22
111.43
Project still ongoing.
Calbiga
156,655.00
156,655.00
100
100
100.00
Project completed.
Sta. Rita
27,645.00
27,645.00
100
100
95.44
Project still ongoing.
Pinipisakan IP-CP No. 11-2013, Hinaga Siphonic Box Culvert Pinipisakan IP-CP No. 12-2013, Hinaga Bridge Flume
NIA Regional Office Northern Samar VIII NIA Regional Office Northern Samar VIII
Las Navas
Las Navas
11/7/2013
5/6/2014
6,817.38
6,817.38
17.33
No Notice To Proceed Yet
-
-
Under suspension.
-
OTHER MAJOR IRRIGATION PROJECTS Bugko Irrigation Project
Bantayan Irrigation Project
Calbiga Irrigation Project
Sta. Rita SRIP
NIA Regional Office Northern Samar VIII NIA Regional Office Northern Samar VIII NIA Samar Regional Office VIII NIA Samar Regional Office VIII
100
95.44
0
-4.56
Location Project Title (1)
Hibulangan SRIP
Agency (2)
NIA Regional Office VIII
Province (3)
Leyte
Schedule Target Municipality/City Date Started Completion Date (4)
Villaba
(5)
(6)
Total Program Amount (7)
92,150.00
AA Issued to Date (8)
92,150.00
Financial (PhP '000) Funding Unpaid Disbursement Support Obligations (%) (9)
100
(10)
(11)
Physical (%) Total
Expenditure Rate
Target
Actual
Slippage
Performance
(12)=(10+11)
(13)=(12/7)
(14)
(15)
(16)=(15-14)
(17)=(15/14)
100
100
0
100.00
Employment Generated (man-days)
Remarks
(18)
(19)
Project completed.