PLAN REVIEW REPORT for Compliance with Batas Pambansa Bilang 344 (Accessibility Law)

For the Proposed UP Manila Eight (8) Storey Student Dormitory University of the Philippines Manila

Prepared by:

ARMAND MICHAEL R. EUSTAQUIO, UAP Architect, Accessibility Consultant

Schematic Design Plan Review Report of the Proposed UP Manila 8-Storey Student Dormitory

TABLE OF CONTENTS Section I.

Introduction

Page 2

II. Findings and Recommendations A. Proposed Ground Floor Plan

2

B. Accessible Bedrooms

6

C. Proposed Typical 2nd (to 3rd) Floor Plan

6

D. Schedule of Doors

6

E. Elevators

6

F. Total Number of Accessible Dormitory Rooms/Bedrooms

7

G. Stairs

7

H. Front Elevation

7

I.

7

Others

III. References

Prepared by: Armand Michael R. Eustaquio, Architect, Accessibility Consultant

8

Page 1 of 8

Schematic Design Plan Review Report of the Proposed UP Manila 8-Storey Student Dormitory

I.

INTRODUCTION In January 1983, the United Nations declared 1983 to 1992 the International Decade of Disabled Persons [Persons with Disabilities]. Less than two months after this declaration, Batas Pambansa Bilang 344 (BP344), otherwise known as An Act to Enhance the Mobility of Disabled Persons [Persons with Disabilities] by Requiring Certain Buildings, Institutions, Establishments, and Public Utilities to Install Facilities and Other Devices, or the accessibility Law was passed into law on February 25, 1983. The Implementing Rules and Regulations of BP 344 were amended in 1994 and is the current version in use and being implemented by all Local Government Units, the DPWH, the DOTC, and all other concerned government agencies. The contents of this Plan Review Report for Compliance with Batas Pambansa Bilang 344 (BP344) or the Accessibility Law were based primarily on the current version of BP344 and the Draft Amendments to the Implementing Rules and Regulations (IRR) of BP344. Reference to the Draft Amendments of BP344 were made to cover provisions not yet incorporated in the current version of BP344 like walk-in or accessible showers, areas of refuge and enhancements to grab bar configurations that need updating or in the current version of BP344. Recommendations that are based on the Draft BP 344 IRR Amendments are noted in this Plan Review Report.

II. FINDINGS AND RECOMMENDATIONS A. Proposed Ground Floor Plan 1. Findings 1.1 Given the finish ground floor elevation of 450MM and assuming that elevation 0.00M is at the start of the ramp at the Portico, the length of the ramp is not sufficient to have a slope of 1:12. The slope of the ramp at the moment seems to be in the vicinity of 1:6 which does not comply with Batas Pambansa Bilang 344 (BP344) or the Accessibility Law. 1.2 The sizes of T & B 2 are not BP344 compliant. 1.3 T & B 1 is not BP344 compliant. The watercloset is located too far from the adjacent wall. Door D-4 is only 700MM wide. 2. Recommendations 2.1 Provide a 5.40M long accessible ramp at the Portico. 2.2 The ground floor is the most ideal location for accessible dormitory rooms. Provide an accessible toilet and accessible shower at the bedrooms in the ground floor as shown in Fig. A.2.1; Fig. A.2.2; A.2.3; and A.2.4 2.3 Provide an accessible shower cubicle/compartment as shown in Fig.A.2.5 2.4 Make door sashes (D-4) for both accessible toilet and accessible shower 950mm wide to have a minimum clear door opening of 900MM. Make these doors swing out or sliding type and maintain a minimum clear door opening of 900MM. 2.5 Make door D-5 located along Grid Line 2, 950MM wide to achieve a minimum clear door opening of 900MM. 2.6 Modify toilets labeled T & B 1 with dimensions and details as shown in Fig. A.2.1; Fig. A.2.2; A.2.3; and A.2.4 2.7 Provide clearances in the occupancy plan for bedrooms as shown in Fig.A.2.6 for ease of mobility for persons with disabilities especially persons who use wheelchairs.

Prepared by: Armand Michael R. Eustaquio, Architect, Accessibility Consultant

Page 2 of 8

Schematic Design Plan Review Report of the Proposed UP Manila 8-Storey Student Dormitory

Fig. A.2.1

Image above shows minimum dimensions of an accessible toilet. (“Fig. C.6.1 PLAN OF ACCESSIBLE TOILET FOR PERSONS WITH DISABILITIES” in the Draft BP 344 IRR Amendments, page 33)

Fig. A.2.2

Image above shows a 3D view of an Accessible Toilet (“Fig. C.6.2 3D VIEW OF ACCESSIBLE TOILET FOR PERSONS WITH DISABILITIES” in the Draft BP 344 IRR Amendments, page 33)

Prepared by: Armand Michael R. Eustaquio, Architect, Accessibility Consultant

Page 3 of 8

Schematic Design Plan Review Report of the Proposed UP Manila 8-Storey Student Dormitory

Fig. A.2.3 Image above shows the detailed dimensions of an Accessible Toilet (“Fig C.6.3 BLOW UP FLOOR PLAN OF ACCESSIBLE TOILET FOR PERSONS WITH DISABILITIES” in the Draft BP 344 IRR Amendments, page 34)

Fig. A.2.4 Image above shows detailed dimensions of L-type grab bar. (“Fig. C.6.4 L-TYPE GRAB BAR” in the Draft BP 344 IRR Amendments, page 34)

Prepared by: Armand Michael R. Eustaquio, Architect, Accessibility Consultant

Page 4 of 8

Schematic Design Plan Review Report of the Proposed UP Manila 8-Storey Student Dormitory

Fig. A.2.5 Image above shows details of accessible shower cubicle/compartment. (“Fig. C.6.8 3D VIEW OF WALK-INSHOWER)” in the Draft BP 344 IRR Amendments, page 37)

Fig. A.6

Image above shows clearances between furniture for ease of mobility of persons with disabilities in dormitory rooms. (“Fig. C.18.1 ACCESSIBLE GUEST ROOM CLEARANCES)” in the Draft BP 344 IRR Amendments, page 37

Prepared by: Armand Michael R. Eustaquio, Architect, Accessibility Consultant

Page 5 of 8

Schematic Design Plan Review Report of the Proposed UP Manila 8-Storey Student Dormitory

2.8 Use lever type faucets, lever type shower valves, and lever type flush valve handles for waterclosets.

B. Accessible Bedrooms Recommendations: 1. Provide Horn strobe type fire alarm with additional vibrating alert mechanism that can be mounted on the bed for persons with hearing impairment. 2. Provide door peephole 1000mm high from floor. rd

C. Proposed Typical 2nd (to 3 ) Floor Plan 1. Findings 1.1 There are no accessible rooms. 2. Recommendations 2.1 If bedrooms at ground floor are not intended for students and accessible bedrooms are to be provided on these floors: a. Provide an accessible toilet and accessible shower at the bedrooms in the ground floor as shown in Fig. A.2.1; Fig. A.2.2; A.2.3; and A.2.4 b. Provide an access toilet and accessible shower at the bedrooms in the ground floor as shown in Fig. A.2.1; Fig. A.2.2; A.2.3; and A.2.4 c.

Provide an accessible shower cubicle/compartment as shown in Fig.A.2.5

d. Make door sashes (D-4) for both accessible toilet and accessible shower 950mm wide to have a minimum clear door opening of 900MM. Make these doors swing out or sliding type and maintain a minimum clear door opening of 900MM. e. Provide clearances in occupancy plan as shown in Fig.A.2.6 for ease of mobility for persons with disabilities especially persons who use wheelchairs. D. Schedule of Doors Recommendations 1. Make the use of lever-type locksets explicit. 2. Provide door peephole 1000mm high from floor for doors of accessible bedrooms.

E. Elevators Recommendations 1. Provide handrails mounted at a height of 900MM from the elevator finish floor. 2. Elevator doors should have a minimum clear opening of 900MM. 3. Elevator call buttons and control buttons shall be tactile and shall have Braille installed at the left of the control buttons. 4. The minimum dimensions of an accessible elevator are 1.40M deep X 1.20M wide. 5. The topmost button on the elevator control panel shall be no higher than 1.20M from the elevator finish floor.

Prepared by: Armand Michael R. Eustaquio, Architect, Accessibility Consultant

Page 6 of 8

Schematic Design Plan Review Report of the Proposed UP Manila 8-Storey Student Dormitory

F. Total Number of Accessible Dormitory Rooms/Bedrooms 1. Findings 1.1 The total number of bedrooms/dormitory rooms is 42 based on the plans provided. There is no accessible bedroom. 2. Recommendations 2.1 The current version of BP344 requires one (1) accessible dormitory room for every 50 to 150 rooms. In the proposed amendments to the IRR of BP 344 this provision has been upgraded. Based on the updated provisions provide at least two (2) accessible rooms preferably on the ground floor. 2.2 If the 7th and 8th floors are to be converted into more dormitory rooms in the future to say a total of 58 rooms provide a minimum of four (4) accessible rooms preferably rooms located on the ground floor and second floor. All accessible rooms shall be provided with accessible toilets and accessible showers as recommended in the Proposed Ground Floor.

G. Stairs 1. Findings 1.1 The stairs have protruding nosings. 1.2 The clear space between wall-mounted handrails and the adjacent walls is 38mm. 2. Recommendations 2.1 Use slanted nosings. 2.2 Provide a minimum clear space of 50MM between the wall-mounted handrails and the adjacent wall.

H. Front Elevation 1. Findings 1.1 The ramp is steeper than the 1:12 slope required by BP344 1.2 The handrails for the ramp do not comply with BP344. 2. Recommendations 2.1 Provide an accessible ramp with a slope of 1:12 2.2 Provide two (2) handrails on both sides of the accessible ramp at a height of 900MM and 700MM in accordance with BP344.

I.

Others Recommendations: 1. Please verify if Fire Code Requirements will require Smoke Proof Fire Exit Stairs. 2. If required provide Area of Refuge in protected Fire Exit Stairs on floors where accessible bedrooms (or floors) for persons with disabilities are located as shown in Fig.H.1 3. Use horn-strobe type fire alarms.

Prepared by: Armand Michael R. Eustaquio, Architect, Accessibility Consultant

Page 7 of 8

Schematic Design Plan Review Report of the Proposed UP Manila 8-Storey Student Dormitory

Fig.H.1

Image above shows Area of Refuge inside Fire Exit Stairs (“Fig.D.1.1” in the Draft BP 344 IRR Amendments, page 45)

IV. REFERENCES 1. National Council for the Welfare of Disabled Persons (NCWDP) Batas Pambansa Bilang 344 (Accessibility Law) and it’s Implementing Rules and Regulations, NCWDP, 1995. 2. Draft Amendments to Batas Pambansa Bilang 344 July 10, 2013

Prepared by: Armand Michael R. Eustaquio, Architect, Accessibility Consultant

Page 8 of 8

UPManila_Plan Review Report of the UP Manila Student Dormitory ...

UPManila_Plan Review Report of the UP Manila Student Dormitory.pdf. UPManila_Plan Review Report of the UP Manila Student Dormitory.pdf. Open. Extract.

351KB Sizes 0 Downloads 179 Views

Recommend Documents

UPManila_Plan Review Report of the UP Manila Sports & Wellness ...
UPManila_Plan Review Report of the UP Manila Sports & Wellness Center.pdf. UPManila_Plan Review Report of the UP Manila Sports & Wellness Center.pdf.

UP-BGC_Plan Review Report for BP344 Compliance for the UP ...
UP-BGC_Plan Review Report for BP344 Compliance for the UP Professional Schools.pdf. UP-BGC_Plan Review Report for BP344 Compliance for the UP ...

UPManila_Plan Review Report of the UP PALO SHS Admin Bldg.pdf ...
Page 3 of 10. UPManila_Plan Review Report of the UP PALO SHS Admin Bldg.pdf. UPManila_Plan Review Report of the UP PALO SHS Admin Bldg.pdf. Open.

UPMin_Schematic Design Plan Review Report for the UP Mindanao ...
UPMin_Schematic Design Plan Review Report for the UP Mindanao Human Kinetics Building.pdf. UPMin_Schematic Design Plan Review Report for the UP ...

WWC Review of the Report "Impacts of Comprehensive Teacher ...
Sep 1, 2013 - The study examined the effects of a comprehensive teacher induction program for beginning teachers. (i.e., teachers new to the profession) on teacher and student outcomes in 17 school districts across. 13 states. The program includes me

Final Report of the Student Transportation Taskforce 2009-2010.pdf ...
Final Report of the Student Transportation Taskforce 2009-2010.pdf. Final Report of the Student Transportation Taskforce 2009-2010.pdf. Open. Extract.

speed up - UKZN Student Funding
You should be in your 1st to final year of studying your Bachelors Degree. All studies should be focused on the below disciplines: Mechanical, Industrial or ...

UPMin_Schematic Design Plan Review Report of the CARIM Bldg.pdf ...
Whoops! There was a problem previewing this document. Retrying. ... UPMin_Schematic Design Plan Review Report of the CARIM Bldg.pdf. UPMin_Schematic ...

UPMin_Schematic Design Plan Review Report of the SOM Building ...
UPMin_Schematic Design Plan Review Report of the SOM Building.pdf. UPMin_Schematic Design Plan Review Report of the SOM Building.pdf. Open. Extract.

COMP meeting report on the review of applications for orphan ...
Jun 27, 2017 - 62 (24%). 2 (1%). 187. 15. 16. 2013 ... 0 (0%). 14. 0. 0. Total. 2820. 2664. 1897 (71%). 743 (28%). 24 (1%). 1876. 135. 149 ... Active substance.

COMP meeting report on the review of applications for orphan ...
Oct 4, 2016 - Applications for marketing authorisation for orphan medicinal products. Details of those ... +44 (0)20 3660 8427. E-mail: [email protected] ...

COMP meeting report on the review of applications for orphan ...
Jun 27, 2017 - Public summaries of opinions will be available on the EMA website following adoption of the .... where two identical synthetic peptide domains.

COMP meeting report on the review of applications for orphan ...
Apr 25, 2017 - ... where two identical synthetic peptide domains are ... Public summaries of opinions will be available on the EMA website following adoption ...

Report of the OK Death Penalty Review Comm'n_April 2017.pdf ...
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. Report of the OK ...Missing:

COMP meeting report on the review of applications for orphan ...
Dec 7, 2017 - Public summaries of opinions will be available on the EMA website following adoption of the respective decisions on orphan designation1 by the European Commission. Please also refer to the Community. Register of orphan medicinal product

Manila Metropolitan Theater.pdf
Page 2 of 5. A. E. F. C. B. H. D. B. H. A. E. F. C. MANILA METROPOLITAN THEATER. G. D. B. H. A. E. F. C. 1. 2. 3. 4. Whoops! There was a problem loading this ...

Manila-based Vacancies.pdf
ACCOUNT EXECUTIVE. • Must be college graduate, preferably in Business or Marketing courses. • Knows his / her way around Metro Manila, willing to travel / ...

ThorCon: Powering Up Our World Status Report
Oct 5, 2016 - ThorCon 2. ThorCon Is a Block ... 2. 8. G. W. 35. 8. G. W. World population 7200 million people. P er c apita elec tric ity us ... ulsan-korea1.html ...

THE PHILIPPINES HOSTS THE 3RD MADRID FUSIÓN MANILA Top ...
catalyze trade and business partnerships in tourism and gastronomy. With Filipino cuisine cited as one of top food trends in 2017 by publications like New York ... in 2016. Sally Camacho Mueller, runner up in the second season of Top Chef, ...

THE PHILIPPINES HOSTS THE 3RD MADRID FUSIÓN MANILA Top ...
acenter of gastronomy in Asia, it is hosting the 3rd Madrid Fusión Manila on April 6-8, 2017 at the SMX Convention ... settings, and services. In keeping with the ...

student set up hw.pdf
Page 1 of 1. ENROLL. Either your instructor enrolled you in a class and created a WebAssign account for you, or she gave. you a class key to enroll yourself and ...

Report to the Secretary of State on the Review of ...
Jun 11, 2009 - Secretary of State on the. Review of. Elective Home Education in England. Graham Badman. Ordered by the House of Commons to be printed on. 11 June 2009 ... I enclose my report which I trust accurately reflects the wide variety of infor

pdf-1321\the-manila-water-concession-a-key ...
... apps below to open or edit this item. pdf-1321\the-manila-water-concession-a-key-government ... -water-privatization-directions-in-development-by.pdf.

pdf-1321\the-manila-water-concession-a-key ... - Drive
There was a problem loading more pages. pdf-1321\the-manila-water-concession-a-key-government ... -water-privatization-directions-in-development-by.pdf.